Capital Projects Updates

UPDATE 6/14/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.14
Through June 21 (estimated) : SFPUC plans to upgrade the storm sewer line on Parker between McAllister and Fulton. Trenching & traffic re-routes. This is a PUC project and not related to USF or ST Ignatius Church.  
PG&E will also start underground work in the same area around June 17, digging a trench & installing pipe across Parker at McAllister. A third effort will be the installation of a water line in the same area, est June 10-14. The work will be noisy. Please follow traffic controls. 
 
Fromm Hall Residential Window Replacement 
  • June 17  begin painting building exterior, about 2 weeks duration
  • Scaffolding install & window demo complete. 
  • On going window installations. Saturday work as needed.
  • Faculty and students access to Xarts through the NW loading dock door -  6am and 2:30pm.
Malloy Hall Exterior Rehab
  • June 12 -Aug 14 Locate and resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Scaffold install ongoing. 
  • Work hours 7:30a to 3:30pm (noisy work starts after 8am)
  • The work will be done is three sections, starting from the southwest corner, moving east along the south wall on Fulton. Each section is expected to take about 3 weeks. The workers will start each section by grinding & chipping away the exterior material & draining water bubbles. This work will be noisy, with interior vibrations. The second two weeks per section should be less disruptive as they clean out & replace joints, waterproof and paint the exterior wall. 
School of Education, 2350 Turk 
  • June 10-21 Continuing form & rebar work 
  • June 21 Concrete pour. Will be noisy at times
Malloy Basketball Practice Facility/War Memorial Gym 
  • TBD: Landscaping at Golden Gate frontage
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • May 30-June 21 install flashings, lights at vrs roof locations
  • Thru June 28 ongoing interior work
  • June 3-28 Stain glass installation  

Campus Events 

  • May 20 - Aug 9 Summer sessions
  • June 18  Goats on Lone Mountain. 
  • Aug 10 New Student Move-in Day
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 

UPDATE 6/7/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Through June 21 (estimated) : SFPUC plans to upgrade the storm sewer line on Parker between McAllister and Fulton. Trenching & traffic re-routes. This is a PUC project and not related to USF or ST Ignatius Church.  PG&E will also start underground work in the same area around June 15, digging a trench & installing pipe across Parker at McAllister. A third effort will be the installation of a water line in the same area, est June 10-14. The work will be noisy. Please follow traffic controls. 
 
Fromm Hall Residential Window Replacement 
  • Scaffolding install & millwork demo complete. 
  • On going window installations. Saturday work as needed.
  • Faculty and students access to Xarts through the NW loading dock door -  6am and 2:30pm.
Malloy Hall Exterior Rehab
  • South facade (on Fulton): locate and resolve leaks. Paint. Scaffold install ongoing. Some noise during discovery work

School of Education, 2350 Turk 
  • May 28-31: Prep work for fountain installation in back garden area
  • June 3-7: Build forms for concrete footings (some noise)
  • June 10-14 Continue form work (possible concrete pour later in week, otherwise the following week)
  • TBD early - mid June concrete pour
Malloy Basketball Practice Facility/War Memorial Gym 
  • TBD: Landscaping at Golden Gate frontage
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • May 30-June 21 install flashings, lights at vrs roof locations
  • Thru June 28 ongoing interior work
  • June 3-28 Stain glass installation  

Campus Events 

  • May 20 - Aug 9 Summer sessions
  • June 18  Goats on Lone Mountain. 
  • Aug 10 New Student Move-in Day
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 

UPDATE 5/31/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
May 28 - June 10:  SFPUC plans to upgrade the storm sewer line on Parker between McAllister and Fulton. Trenching & traffic re-routes. This is a PUC project and not related to USF or ST Ignatius Church.
 
Fromm Hall Residential Window Replacement 
  • Thru June 7- Scaffolding install, window demo. 
  • Saturday work as needed.
Malloy Hall Exterior Rehab
  • South facade (on Fulton): locate and resolve leaks. Paint. Scaffold install ongoing. Some noise during discovery work
  • May 29 power washing begins
School of Education, 2350 Turk 
  • May 28-31: Prep work for fountain installation 
  • June 3-7: Build forms for concrete footings (some noise)
  • TBD early June concrete pour
Malloy Basketball Practice Facility/War Memorial Gym 
  • TBD: Landscaping at Golden Gate frontage
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • June 3 stair tower removal 
  • May 30-June 21 install flashings, lights at vrs roof locations
  • Thru June 14 ongoing interior work
  • June 3-28 Stain glass installation  

Campus Events 

  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm: Load-out 1pm -9pm
  • June 18  Goats on Lone Mountain. 
  • Aug 10 New Student Move-in Day
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 

UPDATE 5/24/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
May 28 - June 10:  SFPUC plans to upgrade the storm sewer line on Parker between McAllister and Fulton. Trenching & traffic re-routes. This is a PUC project and not related to USF or ST Ignatius Church.
 
Fromm Hall Residential Window Replacement 
  • May 20-31- Scaffolding install. Noisy at times
    • move furniture, deliver materiel, abate & demo
      No work May 25 &28
    • May 28-31: Deliveries for new windows and additional scaffolding at the XArts loading dock
Malloy Hall Exterior Rehab
  • South facade (on Fulton): locate and resolve leaks. Paint. Scaffold install ongoing. Some noise during discovery work
  • May 29 power washing begins
School of Education, 2350 Turk 
  • May 24 & 28: Complete paving west section of pathway
  • May 28-31: Fountain contractor to do minimal excavation and begin fountain installation (some noise)
  • June 3-7: Fountain contractor to continue fountain installation (some noise)
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • May 28-31 Scaffold removal at Dome & mid-roof. Detail work at upper roof. 
  • June 3 stair tower removal 
  • May 30-June 7 install flashings, lights at vrs roof locations
  • June 3-14 Stain glass installation  

Campus Events 

  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm: Load-out 1pm -9pm
  • June 18  Goats on Lone Mountain. 
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 

UPDATE 5/17/2024:

 
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement 
  • May 20 project start date, Mon - Sat, 8am start (9am Sat)
  • May 20-31- Scaffolding install. Noisy at times
  • move furniture, deliver materiel, abate & demo
  • No work May 25 &28
Malloy Hall Exterior Rehab
  • May 21 estimated start, work will continue through most of the summer
  • South facade (on Fulton): locate and resolve leaks. Paint
  • Scaffold install ongoing. Some noise during discovery work
School of Education, 2350 Turk 
  • May 6-17  ongoing paver install (some noise as trucks deliver sand and gravel)
  • Workers will not do loud work on 5/10 and during Finals Week 5/11-16
  • Date TBD Concrete pour for footings & pedestal 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
 
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • May 23 - crane at NE corner of Church to help remove scaffolding
  • Scaffold removal at Dome & mid-roof through 5/23
  • May 20-24 install lighting & flashing
  • June 3-14 Stain glass installation 

Campus Events 

  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June 18  Goats on Lone Mountain. 
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 

UPDATE 5/10/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement 
  • May 20 estimated start date
Malloy Hall Exterior Rehab
  • May 21 estimated start
  • South facade (on Fulton): locate and resolve leaks. Paint
  • Scaffold install ongoing. Some noise during discovery work
School of Education, 2350 Turk 
  • May 13-17 Finals week. No work will occur at the project site
  • May 20-24  ongoing paver install (some noise as trucks deliver sand and gravel)
  • Date TBD Concrete pour for footings & pedestal 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
  • April 22 -29  concrete coring, 
  • Apr 22 - May 13 planter bed & retaining wall waterproofing 
  • May 16 - 29  landscaping 
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Dome painting extended through May 15
  • Roof: re-roof work, by section, through 6/3
  • Stain glass restoration through 6/14 

Campus Events 

  • May 9 Last day of Spring semester classes
  • May 16 Commencement Mass 3p St Ignatius Church
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

 


UPDATE 5/3/2024:

 
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement 
  • May 20 estimated start date
Malloy Hall Exterior Rehab
  • May 21 estimated start
  • South facade (on Fulton): locate and resolve leaks. Paint
  • Scaffold install ongoing. Some noise during discovery work
School of Education, 2350 Turk 
  • May 6-17  ongoing paver install (some noise as trucks deliver sand and gravel)
  • Workers will not do loud work on 5/10 and during Finals Week 5/11-16
  • Date TBD Concrete pour for footings & pedestal
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
  • April 22 -29  concrete coring, 
  • Apr 22 - May 13 planter bed & retaining wall waterproofing 
  • May 16 - 29  landscaping 

LoSchiavo Science 

  • May 20 -24 Date tentative. A large crane will be positioned in the Gleeson Plaza limiting pedestrian travel during work hours in that area as well as the west side of CSI and the CSI building itself. CSI building ventilation will be offline. CSI will be inaccessible during crane lift.  Please exercise caution in the area.
  • Crane delivery will be via truck from Parker entrance.
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Scaffold removal, various frontages through 5/9
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- remove scaffold 4/15 - 4/29
  • Painting - various elevations through 4/24
  • Install upper roof through 4/26
  • Stain glass restoration through 4/30/24 

Campus Events 

  • May 9 Last day of Spring semester classes
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 4/26/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement 
  • May 20 estimated start date
Malloy Hall Exterior Rehab
  • South facade (on Fulton): locate and resolve leaks. Paint
  • Scaffold install ongoing. Some noise during discovery work
School of Education, 2350 Turk 
  • April 29-May 1 begin paver install (some noise as trucks deliver sand and gravel)
  • Date TBD Concrete pour for footings & pedestal 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
    • April 22 -29  concrete coring, 
    • Apr 22 - May 13 planter bed & retaining wall waterproofing May 16 - 29  landscaping 

LoSchiavo Science 

  • May 20 -24 Date tentative. A large crane will be positioned in the Gleeson Plaza limiting pedestrian travel during work hours in that area as well as the west side of CSI and the CSI building itself. CSI building ventilation will be offline. CSI will be inaccessible during crane lift.  Please exercise caution in the area.
  • Crane delivery will be via truck from Parker entrance.
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Scaffold removal, various frontages through 5/9
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- remove scaffold 4/15 - 4/29
  • Painting - various elevations through 4/24
  • Install upper roof through 4/26
  • Stain glass restoration through 4/30/24 

Campus Events 

  • April 26 Admissions Tours, Sobrato Center 9am - 1pm. Buses will load and unload in front of War Memorial Gym
  • May 9 Last day of Spring semester classes
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 4/19/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
School of Education, 2350 Turk 
  • April 15-26 Install electrical conduit and irrigation lines.
  • April 29-May 1 begin paver install (some noise as trucks deliver sand and gravel)
  • Date TBD Concrete pour for footings & pedestal 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
  • April 22 -29  concrete coring, 
  • Apr 22 - May 13 planter bed & retaining wall waterproofing 
  • May 16 - 29  landscaping 

LoSchiavo Science 

  • May 20 -24 Date tentative. Finalizing schedule for a crane lift to replace ventilation related equipment on the roof of CSI. Once time is set, the plaza area in front of Gleeson and CSI building will be cordoned off. CSI building ventilation will be offline. Access to CSI will be inaccessible during crane lift.
  • Crane delivery will be via truck from Parker entrance.
Masonic East, 270 Masonic (formerly the Blood Bank)
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Scaffold removal, various frontages through 5/9
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- remove scaffold 4/15 - 4/29
  • Painting - various elevations through 4/24
  • Install upper roof through 4/26
  • Stain glass restoration through 4/30/24 

Campus Events 

  • April 19 Donaroo Campus Concert. Sobrato Center. 4/19 9A -10:30pm: Production Team load-in, soundcheck. Doors open 6:30, Concert 7-9pm, 10:30 Lights off. 4/20: Production team load-out
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • May 9 Last day of Spring semester classes
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 4/15/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
School of Education, 2350 Turk 
  • April 15-26 Install electrical conduit and irrigation lines.
  • April 29-May 1 begin paver install (some noise as trucks deliver sand and gravel)
  • Date TBD Concrete pour for footings & pedestal.
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
  • April 22 -29  concrete coring, 
  • Apr 22 - May 13 planter bed & retaining wall waterproofing 
  • May 16 - 29  landscaping 

LoSchiavo Science 

  • May 20 -24 Date tentative. Finalizing schedule for a crane lift to replace ventilation related equipment on the roof of CSI. Once time is set, the plaza area in front of Gleeson and CSI building will be cordoned off. CSI building ventilation will be offline. Access to CSI will be inaccessible during crane lift.
  • Crane delivery will be via truck from Parker entrance.
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Scaffold removal, various frontages through 5/9
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- remove scaffold 4/15 - 4/29
  • Painting - various elevations through 4/24
  • Install upper roof through 4/26
  • Stain glass restoration through 4/30/24 

Campus Events 

  • April 19 Donaroo Campus Concert. Sobrato Center. 4/19 9A -10:30pm: Production Team load-in, soundcheck. Doors open 6:30, Concert 7-9pm, 10:30 Lights off. 4/20: Production team load-out
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • May 9 Last day of Spring semester classes
  • May 16-18 CommencementsMay 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 4/15/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
School of Education, 2350 Turk 
  • April 15-26 Trenching for irrigation and electrical. Begin installing electrical conduit and irrigation lines.
  • Date TBD Concrete pour for footings & pedestal 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Landscaping at Golden Gate frontage to be scheduled for May, Details TBD
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Scaffold removal, various frontages through 5/9
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- remove scaffold 4/15 - 4/29
  • Painting - various elevations through 4/24
  • Install upper roof through 4/26
  • Stain glass restoration through 4/30/24 

Campus Events 

  • April 19 Donaroo Campus Concert. Sobrato Center. 4/19 9A -10:30pm: Production Team load-in, soundcheck. Doors open 6:30, Concert 7-9pm, 10:30 Lights off. 4/20: Production team load-out
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • May 9 Last day of Spring semester classes
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

 


UPDATE 4/05/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
School of Education, 2350 Turk 
  • April 8-12  Landscape work including grading, dirt removal, and drain pipe installation will continue in the outdoor areas behind and adjacent to 2350 Turk and 2340 Turk. 8:30am - 5:00pm.  There will be some noise when trucks remove offhaul. No jackhammering or concrete cutting is expected
  • April 15-19 Trenching for irrigation and electrical. 
  • Concrete pour for footings & pedestal, date TBD
Malloy Basketball Practice Facility/War Memorial Gym 
  • Landscaping at Golden Gate frontage to be scheduled.
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • April 12 Crane will be placed on Parker frontage between Fulton and McAllister for loading materials onto church roof. Several trucks will deliver materials. Traffic controls will be in place.
    • Scaffold removal, various frontages through 5/9
    • West Spire - scaffold removal 3/4-4/24, subject to weather
    • Fulton frontage- painting 1st & 2nd coats
    • Painting - various elevations through 4/24
    • Stain glass restoration through 4/30/24

Campus Events 

  • April 13-14 Destination USF Campus wide event for students admitted Fall24. Multiple campus locations and events. Buses at various campus drop off zones
  • April 19 Donaroo Campus Concert. Sobrato Center. 4/19 9A -10:30pm: Production Team load-in, soundcheck. Doors open 6:30, Concert 7-9pm, 10:30 Lights off. 4/20: Production team load-out
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • May 9 Last day of Spring semester classes
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 03/29/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
School of Education, 2350 Turk 
  • March 25 - April 5  Landscape work including grading, dirt removal, and drain pipe installation will continue in the outdoor areas behind and adjacent to 2350 Turk and 2340 Turk. 8:30am - 5:00pm, no work 3/30-31.  There will be some noise when trucks remove offhaul. No jackhammering or concrete cutting is expected
Malloy Basketball Practice Facility/War Memorial Gym 
  • Landscaping at Golden Gate frontage to be scheduled.
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • April 1 Crane will be placed on Parker frontage between Fulton and McAllister for loading materials onto church roof. Several trucks will deliver materials. Traffic controls will be in place.
    • East Spire - scaffold removal of spire complete.
    • West Spire - scaffold removal 3/4-4/24, subject to weather
    • Fulton frontage- painting 1st & 2nd coats
    • Mid-rooof and Dome - Paint Dome through 3/25
    • Bell tower - remove scaffold complete
    • Painting - north and west sides through 3/29
    • Stain glass restoration through 4/30/24 

Campus Events 

  • April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • May 9 Last day of Spring semester classes
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • June Goats on Lone Mountain. Details TBD

UPDATE 03/22/2024:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
School of Education, 2350 Turk 
  • March 25 - April 5  Landscape work including grading will continue in the outdoor areas behind and adjacent to 2350 Turk and 2340 Turk. 8:30am - 5:00pm.
  • No work 3/30-31.  There will be some noise when trucks remove offhaul. No jackhammering or concrete cutting is expected.
Malloy Basketball Practice Facility/War Memorial Gym 
  • Landscaping at Golden Gate frontage to be scheduled.
  • March 25-26 Complete installation of handrails in areas around parking lot and Hayes Healy courtyard.
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • East Spire - scaffold removal of spire complete.
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-rooof and Dome - Paint Dome through 3/25
  • Bell tower - remove scaffold complete
  • Painting - north and west sides through 3/29
  • Stain glass restoration through 4/30/24 

Campus Events 

  • March 25 Admissions Tours, Sobrato Center 9am - 1pm
  • April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 03/15/2024:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Harney Science Center, loading dock area
 March 11 - 12  Plumbing contractor will replace plumbing clean outs at the Harney loading dock area. 8am starts. The work will be noisy at times. 
 
Lone Mountain Drive, center spur
 March 15 Lone Mtn Drive, center spur closure for tree removal
 
School of Education, 2350 Turk
  • March 18 - March 22. Grading work in landscaped area behind building, noisy at times. 
  • March 19 Concrete demo, jackhammering. Trucks will be onsite to remove debris.
Malloy Basketball Practice Facility/War Memorial Gym 
  • March 15 & 16: removal of 4 trees in front of Malloy BB Facility site. 
  • Landscaping at Golden Gate frontage to be scheduled.
  • Installation of handrails in areas around parking lot and Hayes Healy courtyard delayed due to manufacturer schedule.  
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired.
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • East Spire - scaffold removal of spire complete.\
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-rooof and Dome - sheet metal repair through 3/15/34. Paint Dome through 3/25
  • Bell tower - remove scaffold est. through 3/18-3/22
  • Painting - north and west sides through 3/29
  • Stain glass restoration through 4/1/24 
Campus Events 
  • March 25 Admissions Tours, Sobrato Center 9am - 1pm
  • April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 03/08/2024:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Harney Science Center, loading dock area
  •  March 11 - 12  Plumbing contractor will replace plumbing clean outs at the Harney loading dock area. 8am starts. The work will be noisy at times. 
Lone Mountain Drive, center spur
  •  March 15 Lone Mtn Drive, center spur closure for tree removal.
School of Education, 2350 Turk
  • March 11 - March 20. Landscaping work in the area behind and to the east of 2350 Turk. The work will include the demolition of concrete pathways, the removal of some grass areas, and grading. This work is expected to last about 7 days (8:30am-4:30pm) , not including Saturday and Sunday and so should be completed by Wed March 20. The demolition work will be noisy for the first few days and will involve jackhammering to break up concrete. Trucks will be onsite to remove debris.
 
Malloy Basketball Practice Facility/War Memorial Gym 
Installation of handrails in areas around parking lot and Hayes Healy courtyard delayed due to manufacturer schedule. 
  • March 8: removal of 4 trees in front of Malloy BB Facility site.  Landscaping at Golden Gate frontage to be scheduled. 
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • East Spire - scaffold removal of spire complete.
  • West Spire - scaffold removal 3/4-3/29, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-rooof and Dome - sheet metal repair through 3/15/34
  • Bell tower - remove scaffold est. through 3/12
  • Painting - north and west sides through 3/29
  • Stain glass restoration through 4/1/24 

Campus Events 

  • March 1 - USF campus Post Office substation permanently closed
  • March 11-15 Spring Break
  • March 25 Admissions Tours, Sobrato Center 9am - 1pm
  • April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 03/01/2024:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Installation of handrails in areas around parking lot and Hayes Healy courtyard delayed due to manufacturer schedule.
  • Landscaping at Golden Gate frontage to be scheduled. 
Masonic East (formerly the Blood Bank)
  • The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • East Spire - scaffold removal of spire complete.
  • West Spire - scaffold removal 3/4-3/29, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-roof and Dome - sheet metal repair through 3/15/34
  • Bell tower - remove scaffold est. 3/8, subject to weather
  • Painting - north and west sides through 3/29
  • Stain glass restoration through 4/1/24 

Campus Events 

  • March 1 - USF campus Post Office substation permanently closed
  • March 11-15 Spring Break
  • March 11-15 Lone Mtn Drive, center spur closure for tree removal; dates TBD
  • March 25 Admissions Tours, Sobrato Center 9am - 1pm
  • April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 02/26/2024:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Installation of handrails in areas around parking lot and Hayes Healy courtyard delayed due to manufacturer schedule. 
  • Landscaping at Golden Gate frontage to be scheduled.  
Lone Mountain Viaduct, 330 Parker Ave 
  • Preparing for final inspection
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
  • Jan 29- Feb22 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • East Spire - scaffold removal of spire complete.
  • West Spire - paint dome by 2/22, scaffold removal 3/4-3/29, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-rooof and Dome - sheet metal repair through 3/15/34
  • Bell tower - remove scaffold est. 3/4
  • Stain glass restoration through 3/11/24 

Campus Events 

  • February 26 Baseball vs Seattle 1pm
  • February 29: USF plans to provide bus service for USF students to the USF vs Gonzaga MBB at the Chase Center
  • Buses for students will be staged at the passenger loading zone in front of War Memorial Gym, departures at about 6:15 and 6:30pm, 7pm, 7:15pm. Return buses drop off on Parker, near McAllister. The USF team bus will return to the WMG location at about 11:30-midnight.  USF is working to minimize idling & noise. 

UPDATE 02/16/2024:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Malloy Basketball Practice Facility/War Memorial Gym 
Landscaping at Golden Gate frontage to be scheduled. 
 
Lone Mountain Viaduct, 330 Parker Ave 
  • Preparing for final inspection
Masonic East (formerly the Blood Bank)
  • The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
  • Jan 29- Feb22 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Week of Feb 19- Concrete pour, north interior of church. One truck and one pump trailer via Parker entrance. Specific date TBD due to weather 
  • East Spire - scaffold removal of spire complete.
  • West Spire - paint dome by 2/22, scaffold removal 3/4-3/29, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-rooof and Dome - sheet metal repair through 3/15/34
  • Bell tower - remove scaffold est. 3/4
  • Stain glass restoration through 3/11/24
School of Education Projects,  2350 Turk
  • Presentation Theater refurbishment: project complete 

Campus Events 

  • February 23-25 Baseball vs Nevada: 2/23 2pm; 2/24 1pm; 2/25 12pm
  • February 26 Baseball vs Seattle 1pm
  • February 29: USF plans to provide bus service for USF students to the USF vs Gonzaga MBB at the Chase Center. 
  • Buses will be staged at the passenger loading zone in front of WMG, departures at about 6:15 and 6:30pm, 7pm, 7:15 Return buses time and location TBD. USF is developing plans to minimize idling & noise. 

UPDATE 02/02/2024:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
Hayes Healy & Gillson entry paths
  • Feb 13 Complete water proofing in patio areas (subject to rain delay)
  • Feb 14 Complete rebar install
  • Feb 15 Concrete pour for HH plaza between Malloy BB Facility and Hayes Healy. 8am start.
Malloy Basketball Practice Facility/War Memorial Gym 
  • Landscaping at Golden Gate frontage to be scheduled. 
Lone Mountain Viaduct, 330 Parker Ave 
  • Finishing fencing install below roadway 
  • Preparing for final inspection
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
  • Jan 29- Feb22 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Feb 13 & 14- debris box delivered at Parker entrance, to place near trailer, remove morning of 2/14
  • East Spire - scaffold removal by 2/19, subject to weather.
  • West Spire - paint dome by 2/22, scaffold removal 3/4-3/29, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-rooof and Dome - sheet metal repair through 3/15/34
  • Bell tower - remove scaffold est. 3/4
  • Stain glass restoration through 3/11/24
School of Education Projects,  2350 Turk
  • Presentation Theater:
  • Final inspection to be scheduled. 

Campus Events 

  • February 16 3-7pm Black History Month Cookout, Welch Field
  • February 16-17 USF Baseball vs Fairleigh Dickinson 2pm Friday; 10a & 2p Saturday
  • February 29: USF plans to provide bus service for USF students to the USF vs Gonzaga MBB at the Chase Center. 
  • 5 buses will be staged at the passenger loading zone in front of WMG, departures at 6:15 and 6:30pm and returns at 10:15 and 10:30pm. USF is developing plans to minimize idling & noise. 

UPDATE 02/02/2024:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
Hayes Healy & Gillson entry paths
  • Feb 5  Finish paver installation underneath Malloy BB facility and HH patio area, including delivery of pavers and base rock via Golden Gate entry drive.  8am start 
  • Feb 13 Complete water proofing in patio areas (subject to rain delay)
  • Feb 14 Complete rebar install
  • Feb 15 Concrete pour for HH plaza between Malloy BB Facility and Hayes Healy. 8am start.
Malloy Basketball Practice Facility/War Memorial Gym 
  • Building punch list walk TBD 
Lone Mountain Viaduct, 330 Parker Ave 
  • Finishing fencing install below roadway 
  • Preparing for final inspection
Masonic East (formerly the Blood Bank)
  • The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
    • Jan 29- Feb22 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • East Spire - finish coat complete, reinstall glass.
  • West Spire - sheet metal restoration complete; finish coat through 2/13, subject to rain delays remove scaffold on west spire through 2/26
  • Fulton frontage sheet metal restoration through Feb 9
  • Mid-rooof and Dome - sheet metal repair through 3/1/34
  • Bell tower - finish coat thru 2/16, remove scaffold est. 2/22
  • Feb 6- install new light poles, east side. 
  • Stain glass restoration through 3/11/24
School of Education Projects,  2350 Turk
Presentation Theater:
  • Final inspection to be scheduled. 

Campus Events 

  • February 2, 5:30pm Presentation Theater, Goodbye Mr. Chips, A Gordon Getty Opera
  • February 6, 7-8pm Silk Series Speaker in Sobrato Center, Clarence B. Jones & Sterling K. Brown

UPDATE 01/26/2024:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
Hayes Healy & Gillson entry paths
  • Jan 29  Sawcutting in area underneath Malloy BB facility and HH patio area. 8am start 
  • Jan 30 Concrete pour for HH plaza between Malloy BB Facility and Hayes Healy. 8am start.
  • Jan 31 Light pole installation, sections of the perimeter
 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Building punch list walk TBD
Lone Mountain Viaduct, 330 Parker Ave 
  • Finishing fencing install below roadway 
  • Preparing for final inspection
Masonic East (formerly the Blood Bank)
  • The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
    • Jan 29- Feb22 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Delivery of new lights poles for east side TBD 
  • Feb 2 - install new light poles, east side. 
  • West spire: sheet metal restoration complete; Paint 2 coats through 1/30
  • Fulton frontage: sheet metal restoration through 2/14/24
  • MidRoof and Dome: sheet metal repair through 3/1/24
  • Stain glass restoration through 3/11/24
School of Education Projects,  2350 Turk
Presentation Theater:
  • Final inspection to be scheduled. 

Campus Events 

  • February 6, 7-8pm Silk Series Speaker in Sobrato Center, Clarence B. Jones & Sterling K. Brown

 


UPDATE 01/19/2024:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Harney Science plumbing leak
  • Repair work complete. Fence to be removed by 1/22
Hayes Healy & Gillson entry paths
  • Jan 23.  Concrete pour for HH plaza between Malloy BB Facility and Hayes Healy. 8am start.
  • Jan 29.   Waterproofing patio and ramp areas
 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Jan 25: Paving activity in area beneath building.  
  • Ongoing deliveries - 2-3/week
 
Lone Mountain Viaduct, 330 Parker Ave 
  • Finishing fencing install below roadway 
  • Preparing for final inspection
 
Masonic East (formerly the Blood Bank)
  • The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
    • Jan 22-29 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Week of Jan 22: delivery of new lights poles for east side. Specific day TBD 
  • Jan 24-25: debris container delivery, fill, and removal 
  • Feb 2 - install new light poles, east side. 
  • West spire: sheet metal restoration thru 1/15/24; Exterior lighting through 1/12/24
  • Fulton frontage: sheet metal restoration through 2/14/24
  • MidRoof and Dome: prepping sheet metal and windows for painting
School of Education Projects,  2350 Turk
Presentation Theater:
  • Final inspection to be scheduled. 
  • Jan 19-23 - cleaning space

Campus Events 

  • January 20 - 7pm Men’s BB vs St Mary’s. CBS TV trucks arrive at UC lot about 9am
  • January 22 - First day of Spring Semester
  • February 6, 7-8pm Silk Series Speaker in Sobrato Center, Clarence B. Jones & Sterling K. Brown

UPDATE 12/20/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Transformer cleaning schedule for winter break
The transformer cleaning requires a two hour electrical power down of each building
Please note buildings, dates and times below.
  • Dec 26 6AM to 8AM - Sobrato Gym & University Center
  • Dec 27 6AM to 8AM - Gleeson Library & Koret Rec
Harney Science plumbing leak
Leak in connection between Harney Science Center and the City storm sewer line at the loading dock driveway (Golden Gate & Chabot). 
  • 12/22 Update:  Concrete work will continue through 12/29, weather permitting. Area fenced off for safety; please heed safety instructions. 
Hayes Healy & Gillson entry paths
  • Dec 25, 26, Jan 1: Site closed 
  • Dec 27 - 29.  8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. 
  • Demo will involve saw cutting and jack hammering. It will be loud and disruptive. 
  • No work Dec 25. 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Dec 25, 26, Jan 1: Site closed 
  • Dec 26 - 29: install fiberglass tubing on north facade. Leveling work beneath building to prepare for pavers may be moderately noisy.  
  • Ongoing deliveries - 2-3/week
Lone Mountain Viaduct, 330 Parker Ave 
  • Ongoing: install fencing below roadway; preparing for final inspection
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
  • Dec 21-31 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Dec 18 - 23 delivery of light poles for east side, turf removal at light sitesexcavation for footings
  • Dec 26-29 conduit installation at Welch Field for light poles
  • East spire; sheet metal restoration through 12/23
  • West spire: sheet metal restoration thru 1/15/24; Exterior lighting through 1/12/24
  • Fulton frontage: sheet metal restoration through 2/14/24
  • MidRoof and Dome: prepping sheet metal and windows for painting
School of Education Projects,  2350 Turk
Presentation Theater:
  • No work scheduled

Campus Events 

  • January 2 - Intersession classes begin
  • January 18 - Move-In Day, new and returning students
  • January 22 - First day of Spring Semester
  • February 6, 7-8pm Silk Series Speaker in Sobrato Center

❄️Happy Holidays to all ❄️


UPDATE 12/15/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Transformer cleaning schedule for winter break
The transformer cleaning requires a two hour electrical power down of each building
Please note buildings, dates and times below.
  • Dec 20 5AM to 7AM:  Kendrick Hall & Zief Library
  • Dec 26 6AM to 8AM - Sobrato Gym & University Center
  • Dec 27 6AM to 8AM-  Gleeson Library & Koret Rec
Harney Science plumbing leak
  • Dec 1- Dec 8 
  • Leak in connection between Harney Science Center and the City storm sewer line at the loading dock driveway (Golden Gate & Chabot). 
  • 12/15 Update:  Backfill complete; inspection complete. Concrete work will begin Thursday 12/21, weather permitting. Area fenced off for safety; please heed safety instructions. 
Hayes Healy & Gillson entry paths
  • Dec 18 - 29.  8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. 
  • Demo will involve saw cutting and jack hammering. It will be loud and disruptive. 
  • Pausing outdoor work for end of semester & Finals: no work Nov 23-Dec 15 and Dec 25. 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Dec 20-22: Fiberglass tubing delivery and paintingPunchlist  
  • Dec 26 - 29: install fiberglass tubing on north facade. Leveling work beneath building to prepare for pavers may be moderately noisy.  
  • Ongoing deliveries - 2-3/week
Lone Mountain Viaduct, 330 Parker Ave 
  • Ongoing: install fencing below roadway; preparing for final inspection
 
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Dec 18-22 No work scheduled on site
 
School of Education Projects,  2350 Turk
Presentation Theater:
  • No work scheduled 
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Dec 18 - 23 delivery of light poles for east side, turf removal at light sitesexcavation for footings
  • East spire; sheet metal restoration through 12/23
  • West spire: sheet metal restoration thru 1/15/24; Exterior lighting through 1/12/24
  • Fulton frontage: sheet metal restoration through 2/14/24
  • MidRoof and Dome: prepping sheet metal and windows for painting

Campus Events 

  • December 15 - Mid Year Commencement
  • January 2 - Intersession classes begin
  • January 18 - Move-In Day, new and returning students
  • January 22 - First day of Spring Semester
  • February 6, 7-8pm Silk Series Speaker in Sobrato Center

UPDATE 12/08/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Transformer cleaning schedule for winter break. 
The transformer cleaning requires a two hour electrical power down of each building. 
Please note buildings, dates and times below.
Dec 20 5AM to 7AM:  Kendrick Hall & Zief Library
Dec 26 6AM to 8AM - Sobrato Gym & University Center
Dec 27 6AM to 8AM-  Gleeson Library & Koret Rec
 
Harney Science plumbing leak
Dec 1- Dec 8 USF has found a leak in a pipe drain connection between Harney Science Center and the City stormsewer line at the loading dock driveway (Golden Gate & Chabot). 
12/8 Update: Excavation complete. Plumbing repair will continue into next week. Backfill and reconstruction of sidewalk will occur after plumbing is repaired. Area fenced off for safety; please heed safety instructions.  
 
Hayes Healy & Gillson entry paths
Dec 18 - 29.  8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. 
Demo will involve saw cutting and jack hammering. It will be loud and disruptive. 
Pausing outdoor work for end of semester & Finals: no work Nov 23-Dec 15 and Dec 25. 
 
Malloy Basketball Practice Facility/War Memorial Gym 
Dec 11 - 15: Fiberglass tubing delivery and paintingPunchlist  
Dec 18- 22: install fiberglass tubing on north facade. Leveling work beneath building to prepare for pavers may be moderately noisy.  
Ongoing deliveries - 2-3/week
 
Lone Mountain Viaduct, 330 Parker Ave 
Ongoing: install fencing below roadway; preparing for final inspection
 
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
Dec 11-15 No work scheduled on site
 
School of Education Projects,  2350 Turk
  • Presentation Theater: Dec 11-13 - Complete lift installation
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Dec 18 - 23 delivery of light poles for east side, turf removal at light sitesexcavation for footings
  • East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
  • West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
  • MidRoof and Dome: prepping sheet metal and windows for painting

Campus Events 

  • December 15 - Mid Year Commencement
  • January 2 - Intersession classes begin
  • January 18 - Move-In Day, new and returning students
  • January 22 - First day of Spring Semester

 

UPDATE 12/01/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Harney Science plumbing leak
  • Dec 1- Dec 8 USF has found a leak in a pipe drain connection between Harney Science Center and the City stormsewer line at the loading dock driveway (Golden Gate & Chabot). The leak requires immediate repair. Contractors will remove a section of the sidewalk and expose the pipe. The work will require heavy equipment and may also initially involve saw-cutting and jack hammering. Once excavation is complete, quieter repair work will continue through next week.
  • 12/1 Update: The excavation work is done for today 12/1. Because of underground utilities near this location, some of the excavation work will require hand digging which will slow things down.
Hayes Healy & Gillson entry paths
  • Nov 13 - 22; Dec 18 - 29.  8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. 
  • Demo will involve saw cutting and jack hammering. It will be loud and disruptive. 
  • Pausing outdoor work for end of semester & Finals: no work Nov 23-Dec 15 and Dec 25. 
Malloy Basketball Practice Facility/War Memorial Gym 
Dec 1 - 11am - 5pm concrete demo at stairs landing near HH garage, needed to complete waterproofing and form new pathway. 
Completing remaining installation tasks, inspections underway. Installation of outdoor pavers. 
Dec 18- 22 install fiberglass tubing on north facade
Ongoing deliveries - 2-3/week
 
Lone Mountain Viaduct, 330 Parker Ave 
  • Ongoing: seal joints, minor concrete repairs, install fencing below roadway
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Dec 3-8 No work scheduled on site
School of Education Projects,  2350 Turk
  • Presentation Theater: Completing lift installation
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Dec 15 No work at site
  • East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
  • West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
  • MidRoof and Dome: prepping sheet metal and windows for painting

Campus Events 

  • December 15 - Mid Year Commencement
  • January 2 - Intersession classes begin
  • January 18 - Move-In Day, new and returning students
  • January 22 - First day of Spring Semester

UPDATE 11/17/2023:

Hayes Healy & Gillson entry paths
  • Nov 13 - 22; Dec 18 - 29.  8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. 
  • Demo will involve saw cutting and jack hammering. It will be loud and disruptive. 
  • Pausing outdoor work for end of semester/final: no work Nov 23-Dec 15 and Dec 25. 
     
Malloy Basketball Practice Facility/War Memorial Gym 
  • Completing remaining installation tasks, inspections underway. Installation of outdoor pavers. 
  • Dec 18- 22 install fiberglass tubing on north facade
  • Ongoing deliveries - 2-3/week
Lone Mountain Viaduct, 330 Parker Ave 
  • Ongoing: seal joints, minor concrete repairs, install fencing below roadway
  • Nov 14-21 guardrail work
Masonic East (formerly the Blood Bank)
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Nov 13-17 No work scheduled on site
School of Education Projects,  2350 Turk
Presentation Theater:
  • 11/17 & 11/20 - 22: install lift (3-5 days; if needed, work will continue 11/27)
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
  • West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
  • MidRoof and Dome: prepping sheet metal and windows for painting

Campus Events 

  • December 15 - Mid Year Commencement

UPDATE 11/10/2023:

Hayes Healy & Gillson entry paths
  • Nov 13 - 29. 8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. Demo will involve saw cutting and jack hammering. It will be loud and disruptive. No work on Nov 23 & 24. 
Malloy Basketball Practice Facility/War Memorial Gym
Nov 11 10am-noon Donor recognition event:  a brief ceremony on the parking deck parking of the facility from about 10am-10:30 will include comments from the podium, appearance by USF’s ROTC Color Guard and the National Anthem played by the USF band. A reception will follow in the Sobrato Center.  Event will end at 12pm. Guests will be provided parking in the HH parking lot. 
  • Ongoing: Completing remaining installation tasks, installing graphics, wall pads, inspections underway. Installation of outdoor pavers. 
  • Nov 13: ADA work on west side of Hayes Healy. Details TBD
  • Ongoing deliveries - 2-3/week
Lone Mountain Viaduct, 330 Parker Ave 
  • Ongoing: seal joints, minor concrete repairs, install fencing below roadway
  • Nov 14: demobilize access road
  • Nov 14-21 guardrail work
 
Masonic East (formerly the Blood Bank)
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Nov 13-17 No work scheduled on site
School of Education Projects,  2350 Turk
Presentation Theater:
  • 11/13 - 14 - install door stops for exit doors
  • Mid to late next week - begin lift installation (work will last about 1 week)
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
  • West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
  • MidRoof and Dome: prepping sheet metal and windows for painting
McLaren Center & Toler Hall Coil replacement
  • Coils in the AC units on the McLaren Complex roof have been replaced. Technicians will return to continue work on minor parts. 
  • 10/23 8am Technicians will be on site to replace some additional parts for the AC units located on McLaren Complex roof.  Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units. 

Campus Events 

  • Nov 16, 11-1pm Student event, Library Plaza
  • December 15 - Mid Year Commencement

UPDATE 11/03/2023:


UPDATE 10/27/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Hayes Healy Garage Closure Oct30-Nov2
  • The Hayes Healy Garage will be closed for mandated driveway repairs from 8am Monday Oct 30 to 8am Thursday November 2.
  • There will be no egress nor entry to the garage during that time. 
  • All vehicles must be removed from the garage by 8am Monday 10/30.  Vehicles remaining in the garage after Monday morning will not be available for use until 8am Thursday. 
Lone Mountain Viaduct, 330 Parker Ave 
Oct 6-23
  • Continued shut down road for paving and overlay work, expected completion on Monday Oct 23. The work will be noisy and disruptive at times.  Please follow flag person directions and signage.
Masonic East (formerly the Blood Bank)
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Oct 30-Nov 3 No work scheduled on site
School of Education Projects,  2350 Turk
Presentation Theater:
  • 10/30 - 11/3: dense drywall and plaster work (minimal noise)
 
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
  • West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
  • MidRoof and Dome: prepping sheet metal and windows for painting
  • Masonry restoration ongoing through 10/31
 
Malloy Basketball Practice Facility/War Memorial Gym
  • Ongoing: Completing remaining installation tasks, installing graphics, wall pads, inspections underway. Installation of outdoor pavers. 
  • Oct 30-Nov2 mandatory repair to Hayes Healy garage entry. HH garage will be closed. All vehicles must be removed  from Hayes Healy garage by Monday 8am Oct 30 
  • Oct 31 Remove construction trailer
  • Nov 2 Remove stair tower 
  • Ongoing deliveries - 2-3/week
McLaren Center & Toler Hall Coil replacement
  • Coils in the AC units on the McLaren Complex roof have been replaced. Technicians will return to continue work on minor parts. 
  • 10/23 8am Technicians will be on site to replace some additional parts for the AC units located on McLaren Complex roof.  Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units. 
Campus Events 
Saturday, October 28: Day In the Bay/Admissions Open House. 8am-4pm
  • Large attendance expected. USF lots will be ’no cite’ and open to guests
  • Workshop,seminars and tours for prospective students
November 3, 4-6pm 
  • USF Rising Mentorship Program at Gleeson Plaza - permit for amplified sound

 


UPDATE 10/13/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Lone Mountain Main/Pacific Wing Plumbing Repair
  • Monday Oct 16 Water shut off in LMM and Pac Wing for approximately 4 hours (8am - noon).
  • Oct 16 - 17  Plumbing repair and pipe replacement in ROTC spaces, LMM
Lone Mountain Viaduct, 330 Parker Ave 
  • Oct 6 -20.  Shut down west half of viaduct for road overlay work. The work will be noisy and disruptive at times. 
  • Once the west section is complete, the work will move to the eastern section. Final stage will be to install overlay layer to roadway surface. Please follow flag person directions and signage.
  • Please do not park on the Viaduct between the Parker entrance and the Anza St exit during this period. Such vehicles will be subject to towing. 
Crane at Center for Scientific Innovation (CSI)
One of the primary exhaust fans on the roof of CSI must be replaced. Replacing the exhaust fan requires that the ventilation system in the CSI building must be shut off so the work must be completed during the Fall Break (no classes). Placing the crane on the roof requires a crane which will arrive on Sunday morning at 8am at the Golden Gate driveway entrance between WMGym and University Center. 
  • Oct 15 -17: Installation postponed. Date TBD
Masonic East (formerly the Blood Bank)
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. 
  • Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Oct 16-20 No work scheduled on site
School of Education Projects,  2350 Turk
Presentation Theater:
  • 10/13 & 10/16: removal of scaffolding from stage (some noise)
  • 10/13: install steel by lift (minimal noise)
  • 10/16 - 20: framing by lift (some noise)
  • 10/17 - 20: remove exterior scaffolding (some noise)
  • 10/18: begin refinishing stage
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • East spire: sheet metal restoration through 12/23
  • West spire: sheet metal restoration to start 10/16, duration TBD
  • MidRoof and Dome: prepping sheet metal and windows for painting
  • Masonry restoration ongoing through 10/31
Malloy Basketball Practice Facility/War Memorial Gym
  • Oct 14-16  Driveway btw Malloy BB facility and WMG closed until Oct 16 pm; sidewalk will be open to pedestrians Oct 16 am
  • Ongoing: Flooring installation in lobbies, ongoing plastering, panel work on building’s south side (will be noisy during work hours at times), installation of outdoor pavers. 
  • Ongoing deliveries - 2-3/week
McLaren Center & Toler Hall Coil replacement
  • Coils in the AC units on the McLaren Complex roof have been replaced. Technicians will return to continue work on minor parts. 
  • Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units. 

Campus Events 

  • October 14. Student Leadership Conference at KoretParker btw Fulton and Golden Gate blocked off for buses. 
  • October 20 - 22 CelebrateUSF - alumni and family weekend 
  • Oct 20, Welch Field outdoor concert 12-3pm
  • Oct 21 Silk Speaker Series at War Memorial Gym 11am - 12 pm
 

UPDATE 10/06/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Lone Mountain Viaduct, 330 Parker Ave 
  • Oct 6 -20.  Shut down west half of viaduct for road overlay work. The work will be noisy and disruptive at times. 
  • Once the west section is complete, the work will move to the eastern section. Final stage will be to install overlay layer to roadway surface. Please follow flag person directions and signage.
  • Please do not park on the Viaduct between the Parker entrance and the Anza St exit during this period. Such vehicles will be subject to towing. 
Crane at Center for Scientific Innovation (CSI)
One of the primary exhaust fans on the roof of CSI must be replaced. Replacing the exhaust fan requires that the ventilation system in the CSI building must be shut off so the work must be completed during the Fall Break (no classes). Placing the crane on the roof requires a crane which will arrive on Sunday morning at 8am at the Golden Gate driveway entrance between WMGym and University Center. 
  • Oct 15 Sunday: Crane delivery and placement
  • Oct 16 -17: Installation 
McLaren Center & Toler Hall
  • Oct 9-11 Engineering will be replace coils in the AC units on the McLaren Complex roof starting 8AM Monday 10/9/2023 through 10/11/2023. The coils will be delivered via truck at the Fulton St loading dock behind McLaren. 
  • Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units. 
 
Masonic East (formerly the Blood Bank)
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. 
Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled. 
  • 10/9 - Geotech work on site (minimal noise, start time 9:00am)
School of Education Projects,  2350 Turk
Presentation Theater:
  • 10/6: Demo exterior roof ladder
  • 10/9 - 13: scaffolding removal from stage (some noise)
  • 10/9: Install new exterior roof ladder (some noise)
    • Located on outer south wall of theater loft
  • 10/13: Steel installation for lift
St Ignatius Church
St Ignatius Church exterior envelope restoration project.
This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Through 9/29 -Ground level: strip west elevation, masonry restoration.
  • MidRoof & Dome - sheet metal restoration, masonry restoration
  • 10/2-17 Install east balustrades
  • Thru Feb 2024 - stain glass restoration
 
Malloy Basketball Practice Facility/War Memorial Gym
  • Oct 9-13  Flooring installation in lobbies, ongoing plastering, panel work on building’s south side (will be noisy at times). 
  • Oct 11-13 Driveway between WMG and Malloy BB: Oct 11: demo and saw cut existing drive (noisy work), Oct 12: install forms; Oct 13: concrete pour. 
  • Ongoing deliveries - 2-3/week

Campus Events 

  • October 20 - 22 CelebrateUSF - alumni and family weekend 

UPDATE 9/15/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Lone Mountain Viaduct, 330 Parker Ave 
  • Oct 2 -4.  Shut down west half of viaduct for road overlay work. The work will be noisy and disruptive at times. Once the west section is complete, it will be opened and the work will move to the eastern section. 
Please follow flag person directions and signage.
  • Oct 9-12 tentative: install overlay layer to roadway surface, partial road closures
Ulrich Baseball Field
  • Complete; minor cleanup work through 9/29.
Lone Mountain Main & Lone Mountain North
Saturday Sept 23 Fire Inspection & Emergency generator test: 4 hour test of LMM generator; the work may be noisy at times. 
 
Masonic East (formerly the Blood Bank)
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. 
Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled. 
  • 9/26: boring 1 hole in parking lot (some noise)
School of Education Projects,  2350 Turk
Presentation Theater:
  • 9/25 - 26: finish painting loft above stage; install emergency exit door; install handrails by emergency exit doors
  • 9/27 - 29: install stage lights
St Ignatius Church
St Ignatius Church exterior envelope restoration project.
This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Through 9/29 -Ground level: strip west elevation, masonry restoration.
  • MidRoof & Dome - sheet metal restoration, masonry restoration
  • 10/2-17 Install east balustrades
  • Thru Feb 2024 - stain glass restoration
Malloy Basketball Practice Facility/War Memorial Gym
  • Sept 22  Complete/ close up street utility tie-in work near driveway between WMGym and Malloy site
  • Sept 26-29 Installation of new driveway path at drive between WMG & Malloy BB site. 
  • Sept 5-26  Installation of new walkway and stairs between Malloy Pavilion and Gillson. Will involve concrete demo which will be loud at times. Please follow directions and signage.
  • Ongoing - Removal of scaffolding, interior glazing, paint, hardware install, elevator, railings, exterior plastering etc. 
  • Ongoing deliveries - 2-3/week

Campus Events 

  • October 20 - 22 CelebrateUSF - alumni and family weekend 

UPDATE 9/15/2023:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 

Lone Mountain Viaduct, 330 Parker Ave

The Lone Mountain Viaduct, located on the north slope of Lone Mountain, will be closed all day on Thursday Sept 21 Please follow flag person directions and signage.
 
Screenshot 2023-09-14 at 11.31.55 AM.png
 
 

University Community, please note: 

Sept 12-19 The Hayes Healy garage will be closed for adjacent driveway and sidewalk construction next week.
  • The garage will close end of the business day on Tuesday Sept 12.  
  • The garage will reopen in the morning on Tuesday Sept 19. 
The garage is completely closed to all vehicle traffic during this time.  
Any cars remaining in the garage after Sept 12 will not be able to be retrieved until the garage reopens. 
 

Ulrich Baseball Field

Sept 8-12 - Patch and repair turf; infield, bullpen, pitching mound. 95% complete; minor patching through 9/22.
 

Lone Mountain Main & Lone Mountain North

Saturday Sept 23 Fire Inspection & Emergency generator test: 4 hour test of LMM generator; may be noisy at times. 
 

Masonic East (formerly the Blood Bank)

Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. That work requires us to pull up the asphalt and waterproof the basement structure’s roof. Work has yet to be scheduled. 
 

School of Education Projects,  2350 Turk

Presentation Theater:
  • 9/15 & 9/18: set up scaffolding on stage
  • 9/16 - 17: cut concrete on east side of stage (classes and seminars have been notified/relocated)
  • 9/18 - 22: paint loft, paint smoke hatches, install stage lights

St Ignatius Church

St Ignatius Church exterior envelope restoration project. This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Through 9/22 -Ground level: strip west elevation, masonry restoration.
  • Through 9/15 - East and West Spires: continue stripping paint, masonry restoration, repair balustrades
  • Sept 18: work on interior to start; electrical infrastructure 
  • Thru Feb 2024 - stain glass restoration

Malloy Basketball Practice Facility/War Memorial Gym

  • Sept 8 - 15  Street Utility Tie-in Work near driveway between WMGym and Malloy site Work will take place during normal hours 8am-3:30pm (not Saturday).There will be some saw cutting at beginning of work, then they will move on to the utility install. Flaggers in the street to assist with traffic. On off-hours, trench plates will be placed over work area per SFDPW requirements.
  • Sept 5-26  Installation of new walkway and stairs between Malloy Pavilion and Gillson. Will involve concrete demo which will be loud at times. Please follow directions and signage. 
  • Sept 12-19 Rebuild the sidewalk and driveway in front of the Malloy worksite. The garage driveway entrance so the driveway will be closed 9/6-11 After that they will pour the sidewalk to the west and will mark a path allow for ped traffic. The HH garage will be closed during this time. 
  • Ongoing - Removal of scaffolding, interior glazing, paint, hardware install, elevator, railings, etc. 
  • Ongoing deliveries - 2-3/week

Campus Events 

  • October 20 - 22 CelebrateUSF - alumni and family weekend 

 

UPDATE 9/1/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 

University Community, please note: 

The lower floor at Hayes Healy Parking lot  is locked at 3pm. Please do not park on the lower level. Please obey signage.

 

Masonic East (formerly the Blood Bank)

Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. That work requires us to pull up the asphalt and waterproof the basement structure’s roof.
  • Sept 4 job site closed

School of Education Projects,  2350 Turk

Presentation Theater:
  • Sept 4 job site closed
  • Sept 7-8: Install emergency exit door

St Ignatius Church

St Ignatius Church exterior envelope restoration project.
This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Sept 4 job site closed
  • Through 9/8 -Ground level: strip north elevation, masonry restoration.
  • Through 9/15 - East and West Spires: continue stripping paint, masonry restoration, repair balustrades
  • Sept 18: work on interior to start; electrical infrastructure 

Malloy Basketball Practice Facility/War Memorial Gym

  • Sept 4 job site closed]
  • Sept 5-26  Installation of new walkway and stairs between Malloy Pavilion and Gillson. Will involve concrete demo which will be loud at times. Please follow directions and signage.
  • Sept 6-11 Rebuild the sidewalk and driveway in front of the Malloy worksite. The garage driveway entrance so the driveway will be closed 9/6-11 After that they will pour the sidewalk to the west and will mark a path allow for ped traffic. 
  • Ongoing - Removal of scaffolding, interior glazing, paint, hardware install, elevator, railings, etc. 
  • Ongoing deliveries - 2-3/week

Hayes Healy Parking lot is open to campus community except for the lower level which is reserved for construction vehicles and materiel. The lower Hayes Healy lot is locked at 3pm. Please do not park on the lower level. Please obey signage.

Lone Mountain Viaduct, 330 Parker Ave

Ongoing- Closure of small sections of the Viaduct, progressively section by section, to repair and fill road surface cracks. Starting at Parker entrance, ending at Loyola Village. Each of the six sections will take about a week. When a section is undergoing repair, traffic will be limited to one lane. Please follow flag person directions and signage.
 

Campus Events 

  • September 12, 7:30pm - Bruce Mahoney Volleyball Game, War Memorial Gym, Sacred Hearth Prep

  • October 20 - 22 CelebrateUSF - alumni and family weekend


UPDATE 8/14/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
University Community, please note: The lower floor at Hayes Healy Parking lot  is locked at 3pm. Please do not park on the lower level. Please obey signage.
 
Masonic East (formerly the Blood Bank)
 
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. 
 
Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. That work requires us to pull up the asphalt and waterproof the basement structure’s roof. Once complete, we will restore the parking lot to its current configuration.  
 
To understand the substrate in preparation for the waterproofing, contractors will begin ‘pot-holing’ the Turk/Masonic lot.  We expect that project to begin in 1or 2 weeks.  The work will last for about a week and will require jack-hammering, so it will be noisy at times.  At about the same time, a security fence will be installed around the property and will be in place for the duration of the renovation project. 
 
August 28 8am Masonic East field operations for potholes begins.
 
 
School of Education Projects,  2350 Turk
West Entrance, handrails
  • 8/18 - 8/25 repair and paint handrails at west entrance
Presentation Theater:
  • 8/14 - 18: install seat cushions
  • 8/14 - 15: demo exterior roof ladder
  • Crane pick (4 hrs) sometime in the next 10 days; back of  SOE parking lot will be closed off during that time

School of Education:

  • Cutover pushed to Christmas break; no more work will be done until then

St Ignatius Church

St Ignatius Church exterior envelope restoration project.
Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Ongoing work on masonry, paint, window restoration, etc
  • Through 9/15 - West Spire, continue stripping paint. 
  • Through 8/11 - East spire: strip paint, restore windows, masonry restoration.
Malloy Basketball Practice Facility/War Memorial Gym
  • Flooring Delivery 
  • Interior work ongoing - glazing, paint, hardware install, elevator, railings, etc. 
  • Ongoing deliveries - 2-3/week
  • Hayes Healy Parking lot is open to campus community except for the lower level which is reserved for construction vehicles and materiel. 
  • The lower Hayes Healy lot is locked at 3pm. Please do not park on the lower level. Please obey signage.
 
Viaduct, 330 Parker Ave
Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • From Aug 21: Closure of small sections of the Viaduct, progressively section by section, to repair and fill road surface cracks. Starting at Parker entrance, ending at Loyola Village. Each of the six sections will take about a week. When a section is undergoing repair, traffic will be limited to one lane. Please follow flag person directions and signage. 
Pacific Wing, Lone Mountain Main
Refresh & upgrade dorm rooms in Pacific Wing. Project complete
 
Campus Events
  • Move-In Day August 19 Lone Mountain Residence halls and Loyola Village; approx 9am-4pm
  • August 12 - 21 Student Orientation.  Various events on campus. 
  • October 20 - 22 CelebrateUSF - alumni and family weekend 

UPDATE 8/14/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
University Community, please note: The lower floor at Hayes Healy Parking lot  is locked at 3pm. Please do not park on the lower level. Please obey signage.
 
Masonic East (formerly the Blood Bank)
 
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. 
 
Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. That work requires us to pull up the asphalt and waterproof the basement structure’s roof. Once complete, we will restore the parking lot to its current configuration.  
 
To understand the substrate in preparation for the waterproofing, contractors will begin ‘pot-holing’ the Turk/Masonic lot.  We expect that project to begin in 1or 2 weeks.  The work will last for about a week and will require jack-hammering, so it will be noisy at times.  At about the same time, a security fence will be installed around the property and will be in place for the duration of the renovation project. 
 

School of Education Projects,  2350 Turk

Presentation Theater:
8/14 - 18: install seat cushions
8/14 - 15: demo exterior roof ladder
Crane pick (4 hrs) sometime in the next 10 days; back of  SOE parking lot will be closed off during that time
 
School of Education:
Cutover pushed to Christmas break; no more work will be done until then

St Ignatius Church

St Ignatius Church exterior envelope restoration project.

Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 

  • Ongoing work on masonry, paint, window restoration, etc
  • Through 9/15 - West Spire, continue stripping paint. 
  • Through 8/11 - East spire: strip paint, restore windows, masonry restoration.

Malloy Basketball Practice Facility/War Memorial Gym

  • Interior work ongoing - glazing, paint, hardware install, elevator, railings, etc. 
  • Ongoing deliveries - 2-3/week
  • Hayes Healy Parking lot is open to campus community except for the lower level which is reserved for construction vehicles and materiel. 
  • The lower Hayes Healy lot is locked at 3pm. Please do not park on the lower level. Please obey signage.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • Ongoing- Piers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices

Pacific Wing, Lone Mountain Main

Refresh & upgrade dorm rooms in Pacific Wing. Project complete
 
Campus Events
  • Move-In Day August 19 Lone Mountain Residence halls and Loyola Village 
  • August 12 - 21 Student Orientation.  Various events on campus. 
  • October 20 - 22 CelebrateUSF - alumni and family weekend 

UPDATE 8/4/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 

Pacific Wing, Lone Mountain Main

Refresh & upgrade dorm rooms in Pacific Wing through Aug 14. 

  • Ongoing, plumbing upgrades, paint dorm rooms and clean carpets on 2nd & 3rd floor, carpet hallway on 3rd floor.

School of Education Projects,  2350 Turk

SOE Fire Alarm Upgrade
  • Final cutover work will occur over Christmas break; no more work will occur until then.

Presentation Theater

  • 8/7-11: cut concrete, chip beam, building temporary support wall beneath stage, install cushions for seats (work will be louder all week)
 

St Ignatius Church

St Ignatius Church exterior envelope restoration project.
Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Ongoing work on masonry, paint, window restoration, etc
  • Through 9/15 - West Spire, continue stripping paint. 
  • Through 8/11 - East spire: strip paint, restore windows, masonry restoration.

Malloy Basketball Practice Facility/War Memorial Gym

Gillson Hall Power Shut Down August 11,  7-9am

  • Monday 8/7:  Crane pick for air handlers - secure crane placement & fencing, crane moves materiel, crane removal, fence removal
  • Interior work ongoing - glazing, paint, hardware install, elevator, railings, etc. 
  • Ongoing deliveries - 2-3/week
  • Hayes Healy Parking lot is open to campus community except for the lower level which is reserved for construction vehicles and materiel. 
  • The lower lot is locked at 3pm. Please do not park on the lower level. Please obey signage.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.

  • Viaduct Closure: Monday Aug 7 at 7am through Friday Aug 11 at 7am, 24 hours/day. 
  • There will be no through traffic from Parker to Anza nor access to Lone Mtn North. 
  • Ongoing- Piers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices

Campus Events

  • Move-In Days August 12-13 Residence hall Upper & Lower campus, all dorms. 
  • The Loyola Terrace Gate will be used for move-in to Gillson Hall on August 12
  • August 12 - 21 Student Orientation.  Various events on campus. 
  • October 20 - 22 CelebrateUSF - alumni and family weekend 

UPDATE 8/3/2023:

Please note: 

Work next week on the Lone Mountain viaduct next week will require its shutdown. There will be no through traffic from Parker to Anza nor access to Lone Mtn North. 

The closure will start Monday Aug 7 at 7am through Friday Aug 11 at 7am, 24 hours/day. 


UPDATE 8/2/2023:

Lone Mountain Main Drive west entrance will be closed Wednesday 8/2 - Thursday 8/3.

Landscaping has a crane up there for tree removals. 

Middle spur & School of Ed entrances will be opened up for two-way traffic.


UPDATE 7/30/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 

Pacific Wing, Lone Mountain Main

Refresh & upgrade dorm rooms in Pacific Wing through Aug 14. 
  • Ongoing, plumbing upgrades, paint dorm rooms and clean carpets on 2nd & 3rd floor, carpet hallway on 3rd floor.

School of Education Projects,  2350 Turk

SOE Fire Alarm Upgrade

  • Final cutover pending permit.

Presentation Theater

  • 7/31 - 8/4 - continue painting and refinishing seats,  work on roof smoke hatches, remove steel beam near east side of stage

St Ignatius Church

St Ignatius Church exterior envelope restoration project.
Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Ongoing work on masonry, paint, window restoration, etc
  • Through 9/15 - West Spire, continue stripping paint. 
  • Through 8/11 - East spire: strip paint, restore windows, masonry restoration.

Malloy Basketball Practice Facility/War Memorial Gym

Hayes Healy Parking lot is open to campus community except for the lower level which is reserved for construction vehicles and materiel. The lower lot is locked at 3pm. Please do not park on the lower level. Please obey signage. 

  • 7/31 - 8/2:  Crane pick for air handlers - secure crane placement & fencing, crane moves materiel, crane removal, fence removal
  • Glazing installation ongoing.
  • Plaster & lathing ongoing, Sheetrock main walls in gym
  • MEP install ongoing
  • Ongoing deliveries - 2-3/week

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • Ongoing- Piers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices

Campus Events

  • July 29-31 Student early arrivals (Residence Hall Advisors, Student-AthletesOrientation. Deliveries at University Center lot will ramp up.
  • August 12 - 21 Student Orientation.  Various events on campus. 
  • October 20 - 22 CelebrateUSF - alumni and family weekend 

UPDATE 7/21/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Pacific Wing, Lone Mountain Main
Refresh & upgrade dorm rooms in Pacific Wing through Aug 14. 

Ongoing, plumbing upgrades, paint dorm rooms and clean carpets on 2nd & 3rd floor, carpet hallway on 3rd floor.

 
School of Education Projects,  2350 Turk
SOE Fire Alarm Upgrade
  • Final cutover pending permit.

Presentation Theater

  • 7/20 - 28: removal of grid structure, ropes, sandbags and curtain
  • 7/24 - 28: setting forms and pouring concrete for exit door landings and stairs
St Ignatius Church
St Ignatius Church exterior envelope restoration project.
Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Ongoing work on masonry, paint, window restoration, etc
  • Through 7/28 - West Spire, continue stripping paint. 
  • Through Aug 4 - East spire: strip paint, restore windows, masonry restoration.
Malloy Basketball Practice Facility/War Memorial Gym
Hayes Healy Parking lot is open to campus community except for the lower level which is reserved for construction vehicles and materiel. The lower lot is locked at 3pm. Please do not park on the lower level. Please obey signage. 
  • 7/31 - 8/2:  Crane pick for air handlers - secure crane placement & fencing, crane moves materiel, crane removal, fence removal
    • Glazing installation ongoing.
    • Plaster & lathing ongoing, Sheetrock main walls in gym
    • MEP install ongoing
    • Ongoing deliveries - 2-3/week
  • July 27-28 - Concrete pour between Malloy BB and Gillson Hall. Concrete pump truck and concrete truck will set up and operate at Loyola Terrace Gate, south side of Gillson Hall.
 
Lone Mountain Viaduct, 330 Parker Ave
Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • Ongoing- Piers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices

Campus Events

  • July 29-31 Student early arrivals (Residence Hall Advisors, Student-AthletesOrientation. Deliveries at University Center lot will ramp up. 
  • August 12 - 21 Student Orientation.  Various events on campus. 
  • October 20 - 22 CelebrateUSF - alumni and family weekend 

UPDATE 7/14/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Lower Campus WiFi Outages
USF is initiating WIFI recabling in SONHP and Kalmanovitz and will involve replacement of outdated connectors and cables in all of the ITS closets.  Internet (wired and wireless; internet/wifi) and phone services (including elevator and emergency phones) will be unavailable during the work period. 
USF will prioritize the analog phone services to minimize outage to the elevator and emergency phone.
  • 7/12 W – 7/18 Tu Ground floor (basement) of both Kalmanovitz & Cowell. Testing will occur on the 4th floor connections, which may have result in disruptions to wifi/phone)
  • 7/19 W – 7/24 Mon Testing will occur on the ground floor (basement) connections, which may result in disruptions to wifi/phone
Pacific Wing, Lone Mountain Main
Refresh & upgrade dorm rooms in Pacific Wing through Aug 14. 
  • Ongoing, plumbing upgrades, paint dorm rooms and clean carpets on 2nd & 3rd floor, carpet hallway on 3rd floor.
School of Education Projects,  2350 Turk
SOE Fire Alarm Update:
  • 7/17 - 28: replace old devices; install the new panel
  • 7/31 - 8/4: tentative test schedule

Presentation Theater:

  • 7/14 - 18: install scaffolding on stage for sand bag, ropes and grid removal. USF Public Safety fire watch will be in effect.
  • 7/17 - 18: saw cut concrete 
  • 7/19 - 21: install stage front trim
  • 7/17 - 21: continue refinishing seats if painters' strike ends
School of Ed Cell Tower Decommission:
  • July 16, Sunday, Crane lift for removal of equipment. Start 8am.
St Ignatius Church
St Ignatius Church exterior envelope restoration project. Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Through July 14 - remove paint, window restoration, demo exterior lighting, window repair (7/17)
  • July 17: crane pick. NW corner of church.
  • Through 7/21 - Fulton frontage, complete scaffolding
  • Through July 28 - East spire: strip paint, restore windows, start masonry restoration.
Malloy Basketball Practice Facility/War Memorial Gym
Hayes Healy Parking lot is open to campus community except for the lower level which is reserved for construction vehicles and materiel. The lower lot is locked at 3pm. Please do not park on the lower level. Please obey signage. 
  • 7/21 - crane pick for air handlers
  • Aug 24 Main roof target competition date
  • Glazing installation ongoing.
  • Plaster & lathing ongoing, Sheetrock main walls in gym
  • MEP install ongoing
  • Ongoing deliveries - 2-3/week
Lone Mountain Viaduct, 330 Parker Ave
Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • Ongoing- Piers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices

Campus Events

  • August 12 - 21 Student Orientation.  Various events on campus. 
  • October 20 - 22 CelebrateUSF - alumni and family weekend 

UPDATE 7/7/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.

Loyola Village, Anza Street

  • 7/10-13 Exterior window washes, northside exterior. 

Lower Campus WiFi Outages

USF is initiating WIFI recabling in SONHP and Kalmanovitz and will involve replacement of outdated connectors and cables in all of the ITS closets.  Internet (wired and wireless; internet/wifi) and phone services (including elevator and emergency phones) will be unavailable during the work period. 

USF will prioritize the analog phone services to minimize outage to the elevator and emergency phone.

  • 7/5 W – 7/11 Tu 4th floor of both Kalmanovitz & Cowell. Testing will occur on the 3rd floor connections, which may result in disruptions to wifi/phone 
  • 7/12 W – 7/18 Tu Ground floor (basement) of both Kalmanovitz & Cowell. Testing will occur on the 4th floor connections, which may have result in disruptions to wifi/phone)
  • 7/19 W – 7/24 Mon Testing will occur on the ground floor (basement) connections, which may result in disruptions to wifi/phone

Pacific Wing, Lone Mountain Main

Refresh & upgrade dorm rooms in Pacific Wing through Aug 14. 

  • Ongoing, plumbing upgrades, paint dorm rooms and clean carpets on 2nd & 3rd floor, carpet hallway on 3rd floor.

School of Education Projects,  2350 Turk

  • School of Education Fire Alarm Upgrade 
    • Continue work on all floors
  • Presentation Theater
    • Pour concrete for exit landing/stairs
    • Work on smoke hatches
    • Continue refinishing seats

School of Ed Cell Tower Decommission:

  • July 10: 8-5:00pm
  • July 12: 8-5:00pm
  • July 13: 8-5:00pm
  • July 16, Sunday, Crane lift for removal of equipment. Start 9am

St Ignatius Church

St Ignatius Church exterior envelope restoration project. Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 

  • Through July 14 - remove paint, window restoration, demo exterior lighting, window repair (7/17)
  • Through 7/21 - Fulton frontage, complete scaffolding
  • Through July 28 - East spire: strip paint, restore windows, start masonry restoration.

Malloy Basketball Practice Facility/War Memorial Gym

Hayes Healy Parking lot is open to campus community except for the lower level which is reserved for construction vehicles and materiel. The lower lot is locked at 3pm.

  • Please do not park on the lower level; please obey signage. 
  • 7/13 -14 - crane pick for air handlers
  • Aug 1 Main roof target competition date
  • Glazing installation ongoing.
  • Plaster & lathing ongoing, Sheetrock main walls in gym
  • MEP install ongoing
  • Ongoing deliveries - 2-3/week

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.

  • Ongoing- Piers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices

Campus Events

CelebrateUSF - alumni and family weekend 

  • Oct 20 Friday, 
    • Family Welcome Reception (main campus)
  • Oct 21 Saturday 
    • Faculty Talks and Info Sessions (Main Campus)
    • Silk Speaker Series (St. Ignatius Church)
    • CelebrateUSF Festival (Welch Field)
    • Reunions (Main Campus)
  • Oct 22 Sunday
    • Fun Run (in and around campus)
    • Reunions (Lone Mountain and Main Campus)

UPDATE 6/19/2023:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Lower Campus WiFi Outages
USF is initiating WIFI recabling in SONHP and Kalmanovitz and will involve replacement of outdated connectors and cables in all of the ITS closets
Internet (wired and wireless; internet/wifi) and phone services (including elevator and emergency phones) will be unavailable during the work period. 
USF will prioritize the analog phone services to minimize outage to the elevator and emergency phone.
  • 6/20 Tu – 6/26 Mon 2nd floor of both Kalmanovitz & Cowell. Testing will occur on the 1st floor connectors, which may result in disruptions to wifi/phone
  • 6/27 Tu – 7/3 Mon 3rd floor of both Kalmanovitz & Cowell. Testing will occur on the 2nd floor connections, which may result in disruptions to wifi/phone
  • 7/5 W – 7/11 Tu 4th floor of both Kalmanovitz & Cowell. Testing will occur on the 3rd floor connections, which may result in disruptions to wifi/phone 
  • 7/12 W – 7/18 Tu Ground floor (basement) of both Kalmanovitz & Cowell. Testing will occur on the 4th floor connections, which may have result in disruptions to wifi/phone)
  • 7/19 W – 7/24 Mon Testing will occur on the ground floor (basement) connections, which may result in disruptions to wifi/phone
Pacific Wing, Lone Mountain Main
Refresh &upgrade dorm rooms in Pacific Wing through Aug 14. 
Work through June 30 includes:
 
  • Swap plumbing in adjoining rooms on 2nd & 3rd floor 
  • Paint dorm rooms and clean carpets on 2nd & 3rd floor 
  • Carpet the hallway on 3rd floor
  • Demo main communal bathrooms and rough in plumbing on all floors.
School of Education Projects,  2350 Turk
Presentation Theater:  Refresh & update parts of Presentation Theater interior.
  • 6/19: Coring exit stairs 
  • 6/21 - 23: Concrete excavation in SOE basement storage area behind cafe. Build forms for new exit stairs and landings
  • 6/23 - 26: Build forms and rebar for lift

SOE Fire Alarm Upgrade:

  • 6/19 - 23: Begin project (installing conduits, pulling wire)

School of Ed Fire Alarm Upgrade:

  • 6/12 - 16: mobilization of tools and materials on site (staged in basement by cafe)
  • 6/19: work to begin (project to last all summer)

School of Ed Cell Tower Decommission:

  • July 3:  8-5:00pm
  • July 5: 8-5:00pm
  • July 6: 8-5:00pm
  • July 10: 8-5:00pm
  • July 12: 8-5:00pm
  • July 13: 8-5:00pm
St Ignatius Church
St Ignatius Church exterior envelope restoration project. Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Through July 14 - remove paint, window restoration, demo exterior lighting, window repair (7/17)
  • Through July 24 - erect scaffolding, west spire & Fulton
  • Malloy Basketball Practice Facility/War Memorial Gym
  • Hayes Healy Parking lot is open to campus community however please note the gates lock at 3pm each day
  • Aug 1 Main roof target competition date
  • Ongoing MEP rough-in, metal framing, fireproofing
  • Plaster & lathing ongoing, Sheetrock & plywood installation, skylight installation underway
  • Ongoing deliveries - 2-3/week
 
Lone Mountain Viaduct, 330 Parker Ave
Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • OngoingPiers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices
Ulrich Field/Benedetti Diamond - Batter’s Eye screening - Work complete 6/14

UPDATE 6/14/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Pacific Wing, Lone Mountain Main
Refresh & Upgrade dorm rooms in Pacific Wing through Aug 14. 
  • June 12-16 Troubleshoot and prep plumbing work
  • On-going painting 
 
School of Education Projects,  2350 Turk
Presentation Theater:  Refresh & update parts of Presentation Theater interior.
  • 6/12 - 16: continuing demo work in theater
  • 6/14 - 16: set up scaffolding outside on east side of theater for roof access

School of Ed Fire Alarm Upgrade:

  • 6/12 - 16: mobilization of tools and materials on site (staged in basement by cafe)
  • 6/19: work to begin (project to last all summer)

School of Ed Cell Tower Decommission:

  • July 3:  8-5:00pm
  • July 5: 8-5:00pm
  • July 6: 8-5:00pm
  • July 10: 8-5:00pm
  • July 12: 8-5:00pm
  • July 13: 8-5:00pm
St Ignatius Church
St Ignatius Church exterior envelope restoration project. Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Thru July 12  erect west spire scaffold
  • Thru July 19  strip paint east spire
  • No work May 29, Memorial Day
Malloy Basketball Practice Facility/War Memorial Gym
  • Aug 1 Main roof target competition date
  • Ongoing MEP rough-in, metal framing, fireproofing
  • Glazing installation, Sheetrock & plywood installation, skylight installation underway
  • Ongoing deliveries - 2-3/week
Ulrich Field/Benedetti Diamond
Install two aluminum screens (#1: 20’ W x 30ft H; #2: 40ft W x 30 ftH) at the center field fence near Masonic Ave. This is a safety installation intended to improve the batter's tracking of pitches to avoid injury.
  • Work complete 6/14
Lone Mountain Viaduct, 330 Parker Ave
Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • OngoingPiers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices

UPDATE 5/26/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Presentation Theater 2350 Turk
Refresh & update parts of Presentation Theater interior. Expected mobilization week of May 30. 
  • Refinish seats and wood floors, install new carpet
  • Paint interior
  • Upgrade side exit doors and stage access to be ADA compliant
St Ignatius Church
St Ignatius Church exterior envelope restoration project. Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Thru May 26 strip paint west elevation
  • Thru May 31 Install Dome scaffold
  • Thru June 7 erect scaffold at Bell Tower
  • Thru June 5 erect scaffold north elevation
  • Thru June 7 erect scaffold at Bell Tower
  • Thru July 12  strip paint east spire
  • Thru June 12 erect scaffold on east side
  • No work May 29, Memorial Day
     
    Malloy Basketball Practice Facility/War Memorial Gym
    • Ongoing MEP rough-in, metal framing, fireproofing
    • Glazing installation, plywood installation, skylight installation underway
    • Ongoing deliveries - 2-3/week
    • No work May 29, Memorial Day
    Ulrich Field/Benedetti Diamond
    USF will install two aluminum screens (#1: 20’ W x 30ft H; #2: 40ft W x 30 ftH) at the center field fence near Masonic Ave. This is a safety installation intended to improve the batter's tracking of pitches to avoid injury. Project duration approximately 5 weeks.  8am - 4pm 
    • May 27 - May 30 Work paused
    • June 1. Drilling for piers continues
    Lone Mountain Viaduct, 330 Parker Ave
    Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
    • OngoingPiers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices
    Events
    • May 27. St Ignatius High School graduation, St Ignatius Church

    UPDATE 5/23/2023:

    All dates below are best estimates, subject to weather and other external impacts and may change without notice.
     
    Presentation Theater 2350 Turk
    Refresh & update parts of Presentation Theater interior. Expected mobilization week of May 30. 
    • Refinish seats and wood floors, install new carpet
    • Paint interior
    • Upgrade side exit doors and stage access to be ADA compliant
    St Ignatius Church
    St Ignatius Church exterior envelope restoration project. Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
    • Thru May 26 strip paint west elevation
    • Thru May 26 Install Dome scaffold
    • Thru June 7 erect scaffold at Bell Tower
    • Thru June 9 erect scaffold north elevation
    • Thru June 7 erect scaffold at Bell Tower
    • Thru July 12  strip paint east spire
    • No work May 29, Memorial Day
       
      Malloy Basketball Practice Facility/War Memorial Gym
      • Ongoing MEP rough-in, metal framing, fireproofing
      • Glazing installation, plywood installation, skylight installation underway
      • Ongoing deliveries - 2-3/week
      • No work May 29, Memorial Day
      Ulrich Field/Benedetti Diamond
      USF will install two aluminum screens (#1: 20’ W x 30ft H; #2: 40ft W x 30 ftH) at the center field fence near Masonic Ave. This is a safety installation intended to improve the batter's tracking of pitches to avoid injury. Project duration approximately 5 weeks.  8am - 4pm 
      • May 22. Mobilization
      • May 30. Start drilling for piers 
      Lone Mountain Viaduct, 330 Parker Ave
      Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
      • OngoingPiers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices

      UPDATE 5/12/2023:

       
      All dates below are best estimates, subject to weather and other external impacts and may change without notice.
       
      St Ignatius Church
      St Ignatius Church plans an exterior envelope restoration project. Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
      • May 12-26 Install dome scaffold
      • May 15 Strip paint, east spire
      • May 15-June 7 install bell tower scaffold
      • May 26  Install ground level scaffold, north and west sides of Church. Approx 2 weeks. 
      Welch Field Project
      • May 15  Turf installation will be complete
      • May 16  Fence will be removed
      Malloy Basketball Practice Facility/War Memorial Gym
      • Ongoing MEP rough-in, metal framing, fireproofing
      • Glazing installation, plywood installation, skylight installation underway
      • Ongoing deliveries - 2-3/week
      Ulrich Field/Benedetti Diamond
      USF will install two aluminum screens (#1: 20’ W x 30ft H; #2: 40ft W x 30 ftH) at the center field fence near Masonic Ave. This is a safety installation intended to improve the batter's tracking of pitches to avoid injury. 
      • May 22. Mobilization. Project duration approximately 5 weeks.  8am - 4pm 
      Lone Mountain Viaduct, 330 Parker Ave
      Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
      • OngoingPiers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices
      Events & Other Activities
      • May 12 Goodwill donation collection at LME Res Hall and Gillson/Hayes Healy forecourt
      • May 17 Goodwill donation collection at LME Res Hall and Gillson/Hayes Healy forecourt
      • May 18 - 20 USF Graduation, St Ignatius Church
      • May 20 - 21 Move-out period for campus residence halls

      UPDATE 5/5/2023:

      All dates below are best estimates, subject to weather and other external impacts and may change without notice.

      St Ignatius Church

      St Ignatius Church plans an exterior envelope restoration project. Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
      • May 11. Crane pick, one day. 
      • May 8 Install scaffold, east side+ interior east elevation, then north and west sides. Approx 4 weeks
      • May 8 start stripping paint, mid roof
      • May 15 strip paint, east spire

      Welch Field Project

      • May 1 - 10:   Base rock delivery
      • May 4 - 15: Pad and turf installation
      • May 16: Fence removal

      Malloy Basketball Practice Facility/War Memorial Gym

      • Ongoing deliveries - 2-3/week
      • Roofing installation 98% complete
      • Interior work continues (plumbers, electricians, etc)
      • Early May - Hayes Healy Parking Lot  - Expected partial re-opening (two floors only)

      Ulrich Field/Benedetti Diamond

      USF will install two aluminum screens (#1: 20’ W x 30ft H; #2: 40ft W x 30 ftH) at the center field fence near Masonic Ave. This is a safety installation intended to improve the batter's tracking of pitches to avoid injury. 
      • May 22. Mobilization. Project duration approximately 5 weeks.  8am - 4pm 

      Lone Mountain Viaduct, 330 Parker Ave

      Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.

      • OngoingPiers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices

      Events & Other Activities

      • May 18 - 20 USF Graduation 
      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San 

      UPDATE 4/28/2023:

      All dates below are best estimates, subject to weather and other external impacts and may change without notice.
      Periodic rain delays may affect work schedule and other activities.
       

      St Ignatius Church

      St Ignatius Church plans an exterior envelope restoration project. Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
      • Crane setup - timing TBD
      • Apr 20 - 28  Install scaffold, east side + interior east elevation
      • May 5 start stripping paint, west elevation mid roof
      • May 15 strip paint, east spire

      Welch Field Project

      • Apr 27 - 28: Nail board work
      • May 1 - turf and pad delivery (4 trucks)
      • May 1 - 5: Base rock delivery (5 trucks)
      • May 1-12: Turf installation

      Malloy Basketball Practice Facility/War Memorial Gym

      • Ongoing deliveries - 2-3/week
      • Roofing installation nearing completion
      • Interior work continues (plumbers, electricians, etc)
      • Early May - Hayes Healy Parking Lot  - Expected partial re-opening (two floors only)

      Lone Mountain Viaduct, 330 Parker Ave

      Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
      • OngoingPiers: bearing repairs, prep hydraulic hoists, installation of structural lock-up devices

      Events & Other Activities

      • May 18 - 20 USF Graduation
      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San 

      UPDATE 4/21/2023:

      Welch Field Project
      Apr 26 - May 2 Base rock delivery and installation 4/26 - 5/2

      Malloy Basketball Practice Facility/War Memorial Gym

      • Apr 25 9am Small concrete pour, 1-2 trucks
      • Ongoing deliveries - 2-3/week
      • Roofing installation nearing completion
      • Interior work continues (plumbers, electricians, etc)
      • May 1 Hayes Healy Parking Lot  - Expected partial re-opening (two floors only)

      Lone Mountain Viaduct, 330 Parker Ave

      Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
      • OngoingPiers: bearing repairs, prep hydraulic hoists, installation of structural lock-up device.

      Events & Other Activities

      • Apr 21  Movie Night at Benedetti Diamond 7:45 - 9:45pm, USF students only
      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San 

      UPDATE 4/14/2023:

      All dates below are best estimates, subject to weather and other external impacts and may change without notice.
      Periodic rain delays may affect work schedule and other activities.

      St Ignatius Church

      St Ignatius Church plans an exterior envelope restoration project. Scaffolding will be erected around the perimeter of the building. Vehicles and equipment will access the site from Parker Ave, near McAllister. This project is managed by St. Ignatius Church. which is independent of the University
      • Apr 20  A crane will be positioned at the northeast corner of the Church to hoist scaffolding material along the east side. The process will be take most of the day.Please adhere to traffic and pedestrian controls on the sidewalk as needed for each overhead pick.

      Welch Field Project
      Apr 13 -21  Build forms and pour concrete around edges of field (total of 3 concrete trucks Monday 4/17 and Thursday 4/20)

      Malloy Basketball Practice Facility/War Memorial Gym