Capital Projects Updates

08/27/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

USF students are returning to campus.  USF will continue to make every effort to minimize impacts, however, you can expect to see the volume of pedestrians and auto traffic return to something closer to pre-pandemic levels. We will continue to focus on minimizing parking impacts on the neighborhood, encouraging positive community behavior through student education programs in the dorms and through the Off-Campus Services Office, minimizing and managing construction impacts, implementing strategies to reduce noise and disruptive traffic.

Dogs on Campus:

Dogs on campus must be leashed at all times.

The policy was relaxed during the past year as a benefit to USF’s neighbors and the broader community during Covid Lockdown. However, the policy is being reinstated due to safety concerns, including the well-being of the sight-impaired person and their service dog who were adversely affected in a recent incident on campus.  USF Public Safety will immediately begin to enforce this policy.

Lone Mountain Trash & Recycling Facility

  • Demo work at Trash/Recycling site  Previously scheduled for Aug 18, this work will be rescheduled. The work will involve jackhammers and will be noisy. 
  • Aug 2-31 - Work on utility infrastructure.
  • Excavation and grading subject to utility survey.  Dates TBD.
  • Parking on the Lo Schiavo Drive viaduct will be reduced when construction starts, approximately early June. Alternative parking will be available in the garages beneath the new Lone Mtn Residence Hall; opening date TBD.

War Memorial Gym

  • UC parking lot, west of WMG, will be cleared, slurried, and striped. The project will take 2 days. Dates TBD
  • Renovaton of North Lobby: WMG North Lobby will be converted to the USF Athletic Hall of Fame. Entrance from WMG SW entrance; no access from north doors on Golden Gate Ave. Interior framing will begin on August 25, 7 am-3 pm.  The work will be noisy. The renovation will take about 6 weeks.
  • Planter at the north end: Drain rock and soil to be delivered early Sept. Date TBD.
  • Ongoing: Finishing interior work: staining, polishing; installation of spectator seating.

Lone Mountain East (LME) Residence Hall

  • Aug 23-Oct 1 Tree Removal: cypress trees east of LME are dead or declining.  USF plans to replace the trees, details to follow as plan develops.
  • August 30,  Furniture delivery, one truck.
  • Landscaping work for the area east of Drive is finishing up.
  • On-going interior punch list

Lone Mountain/Turk Landscape

Ongoing work on plantings on the center area of Lone Mountain. The priorities for the project are:

  1. reducing water usage by changing our approach to plant selection;
  2. increasing curb appeal while reducing water usage;
  3. changing out spray fixtures for more efficient drip irrigation. Work is underway and is scheduled through August 14.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


8/21/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.  USF students are returning to campus. Classes start on August 24. USF will continue to make every effort to minimize impacts, however, you can expect to see the volume of pedestrians and auto traffic return to something closer to pre-pandemic levels. We will continue to focus on minimizing parking impacts on the neighborhood, encouraging positive community behavior through student education programs in the dorms and through the Off-Campus Services Office, minimizing and managing construction impacts, implementing strategies to reduce noise and disruptive traffic.

Student Resident Move-In Days

August 21-22 Lower Campus Res Halls, Loyola VillageMove-in day procedures will be similar to prior years. Students and their families will be scheduled for staggered arrivals, For the lower campus, portions of the Golden Gate parking spaces will be cordoned off for traffic flow and drop off. USF Public Safety, SFPD, USF Housing staff will manage traffic and drop-off logistics.

Campus Events:

Events to welcome USF students to campus. The max capacity is 750 attendees for Dons Night Out, reduced from standard capacity. USF Public Safety Officers will be on site. All SF Health protocols will be followed. The University will verify full vaccination of all event attendees. The entrance to the event is in the campus interior(SW entrance).  No attendee access from Golden Gate Ave.

  • Preparations - August 20 8am-7pm - Set up in Gym. Unloading trucks at WMG white zone, UC lot
  • Dons Night Out 1 - August 21 / 8:30pm-10pm - War Memorial Gym
  • Convocation - August 22 / 3pm - Students enter at SW entrance
  • Dons Night Out 2 - August 23 / 7pm-10:30pm Students enter at SW entrance
  • Event Load Out - August 24 / 1pm-7pm - Loading trucks at WMG white zone, UC lot

Lone Mountain Trash & Recycling Facility

  • Demo work at Trash/Recycling site - Previously scheduled for Aug 18, this work will be rescheduled. The work will involve jackhammers and will be noisy.
  • Aug 2-31 - Work on utility infrastructure
  • Excavation and grading subject to utility survey - Dates TBD
  • Parking on the Lo Schiavo Drive viaduct will be reduced when construction starts, approximately early June. Alternative parking will be available in the garages beneath the new Lone Mtn Residence Hall; opening date TBD.

War Memorial Gym

  • Renovaton of North Lobby: WMG North Lobby will be converted to the USF Athletic Hall of Fame. Entrance from WMG SW entrance; no access from north doors on Golden Gate Ave. Interior framing will begin on August 25, 7 am-3 pm. The initial work is cutting and attaching metal framing to the ceiling and the floor.  The work will be noisy. The renovation will take about 6 weeks.
  • Landscape & waterproof planter at the north end.
  • Installation of pavers for drive west of WMG scheduled to complete Aug 19.
  • Ongoing: Finishing interior work: staining, polishing, sealing concrete floors; installation of spectator seating.

Lone Mountain East (LME) Residence Hall

  • Aug 23-Oct 1 - Tree Removal: cypress trees east of LME are dead or declining.  USF plans to replace the trees, details to follow as the plan develops.
  • August 30 - Furniture delivery, one truck.
  • Landscaping work for the area east of Drive finishing up.
  • On-going interior punch list.

Dining Project

  • Project completed

Lone Mountain/Turk Landscape

Ongoing work on plantings on the center area of Lone Mountain. The priorities for the project are:

  1. reducing water usage by changing our approach to plant selection.
  2. increasing curb appeal while reducing water usage.
  3. changing out spray fixtures for more efficient drip irrigation. Work is underway and is scheduled through August 14.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


08/16/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Student Resident Move-In Days:

  • August 21-22 Lower Campus Res Halls, Loyola Village

Move-in day procedures will be similar to prior years. Students and their families will be scheduled for staggered arrivals, For the lower campus, portions of the Golden Gate parking spaces will be cordoned off for traffic flow and drop off. USF Public Safety, SFPD, USF Housing staff will manage traffic and drop-off logistics.

Negoesco Field, Turf Replacement:

Work is complete for the artificial turf replacement at Negoesco field.

Lone Mountain Trash & Recycling Facility

  • August 16 - Work is complete for the gas line cutover/boiler shutdown. Hot water, heat, and gas are back on. You may need to run your hot water faucet for a few minutes to clear accumulated sediments.
  • August 18 - 8am.  Demo work at Trash/recycling site; will involve jackhammers and will be noisy.
  • Aug 2-31 - Work on utility infrastructure
  • Excavation and grading subject to utilities survey.  Dates TBD
  • Parking on the Lo Schiavo Drive viaduct will be reduced when construction starts, approximately early June. Alternative parking will be available in the garages beneath the new Lone Mtn Residence Hall; opening date TBD.

War Memorial Gym

  • Landscape & waterproof planter
  • Installation of pavers for drive west of WMG through approximately August 20
  • Ongoing: Finishing interior work: staining, polishing, sealing concrete floors; installation of wood slat ceiling.

Lone Mountain East (LME) Residence Hall

  • August 24 or 25, TBD.    Furniture delivery, one truck. 
  • Tree Removal: cypress trees east of LME are dead or declining. Work to remove the trees is currently scheduled Aug 23-Oct 1. USF plans to replace the trees, details to follow as the plan develops.
  • Landscaping work for the area east of Drive finishing up.
  • On-going interior punch list

Dining Project

  • On-going interior work to prepare for opening.
  • August 17 - Dining Commons operations begin

Lone Mountain/Turk Landscape

Ongoing work on plantings on the center area of Lone Mountain. The priorities for the project are

  1. reducing water usage by changing our approach to plant selection.
  2. increasing curb appeal while reducing water usage.
  3. changing out spray fixtures for more efficient drip irrigation. Work is underway and is scheduled through August 14.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c  April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


08/10/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Negoesco Field, Turk Replacement:

The artificial turf at Negoesco field will be replaced. The project will take 21 days, starting the week of July 19. Equipment and materials will be off-loaded on Parker, near the Negoesco Parker gate and/or the Koret/Parker stairs. Work will begin daily after 8 am. Work on Saturdays is possible but not currently planned.

  • Aug 3-12 - Infill placement
  • Aug 13 - Demobilization

Lone Mountain Trash & Recycling Facility

  • August 16 - Boiler shutdown. No Hot water, heat, gas service all day in LMMain, LMNorth, Rossi, PacWing, Dining Commons (this date is subject to external scheduling and may change)
  • Aug 2-31 - Work on utility infrastructure
  • Excavation and grading subject to utility survey.  Dates TBD
  • Parking on the Lo Schiavo Drive viaduct will be reduced when construction starts, approximately early June. Alternative parking will be available in the garages beneath the new Lone Mtn Residence Hall; opening date TBD.

War Memorial Gym

  • Landscape & waterproof planter
  • Installation of pavers for drive west of WMG through approximately August 13
  • Ongoing: Finishing interior work: staining, polishing, sealing concrete floors; installation of wood slat ceiling.

Lone Mountain East (LME) Residence Hall

  • Tree Removal: cypress trees east of LME are dead or declining. Work to remove the trees is currently scheduled from Aug 23-Oct 1. USF plans to replace the trees, details to follow as the plan develops.
  • August 14: Move-in Day for student residents
  • Landscaping work for the area east of Drive ongoing. There will be some truck activity next week involving the delivery of soil and plants.
  • On-going interior punch list

Dining Project

  • On-going interior work to prepare for opening.
  • August 17 - Dining Commons operations begin

Lone Mountain/Turk Landscape

USF will update plantings on the center area of Lone Mountain. The priority for the project are

  1. reducing water usage by changing our approach to plant selection.
  2. increasing curb appeal while reducing water usage.
  3. changing out spray fixtures for more efficient drip irrigation. Work is underway and is scheduled through August 14.

Student Resident Move-In Days:

  • August 14 - Lone Mountain East Residence Hall
  • August 21-22 - Lower Campus Res Halls, Loyola Village

Move-in day procedures will be similar to prior years. Students and their families will be scheduled for staggered arrivals, For the lower campus, portions of the Golden Gate parking spaces will be cordoned off for traffic flow and drop off. USF Public Safety, SFPD, USF Housing staff will manage traffic and drop-off logistics.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c  April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


07/30/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Negoesco Field, Turk Replacement:

The artificial turf at Negoesco field will be replaced. The project will take 21 days, starting the week of July 19. Equipment and materials will be off-loaded on Parker, near the Negoesco Parker gate and/or the Koret/Parker stairs. Work will begin daily after 8am. Work on Saturdays is possible but not currently planned.

  • July 26-Aug 3 - Turk installation
  • Aug 3-12 - Infill placement
  • Aug 13 - Demobilization

Lone Mountain Trash & Recycling Facility

  • August 16 - Boiler shutdown. No Hot water, heat, gas service all day in LMMain, LMNorth, Rossi, PacWing, Dining Commons. Details will follow.
  • August 4 - Existing compactor will be moved to a temporary location at School of Ed Parking lot.
  • Aug 2-31 - Work on utility infrastructure.
  • Excavation and grading subject to utility survey - Dates TBD.
  • Parking on the Lo Schiavo Drive viaduct will be reduced when construction starts, approximately early June. Alternative parking will be available in the garages beneath the new Lone Mtn Residence Hall; opening - date TBD.

War Memorial Gym

  • On-going: Concrete work @WMG Golden Gate frontage/planters. Possibly noisy at times.
  • Installation of pavers for drive west of WMG through approximately 1st week of August.
  • Ongoing: Finishing interior work: staining, polishing, sealing concrete floors; installation of wood slat ceiling.

Lone Mountain East Residence Hall

Delivery and installation of furnishings for dorm rooms, 2 classrooms and staff apartments will occur periodically through July and early August. Details and dates are subject to change without notice. Trucks will deliver onsite, unloading will occur throughout the day. Covid continues to disrupt and delay supply chains.

  • August 2 -6 Continued deliveries, 1-2 trucks/day except Aug 5 & 6 there will be up to 3 trucks/day.
  • Landscaping work for the area east of Drive on-going. There will be some truck activity next week involving the delivery of soil and plants.
  • On-going interior punch list    

The Lone Mtn Res Hall site remains is closed to the public and the campus community.

Dining Project

  • On-going interior work to prepare for opening.

The Lone Mtn Dining Commons site remains closed to the public and the campus community.

Lone Mountain/Turk LandscapE

USF will update plantings on the center area of Lone Mountain. The priority for the project are

  1. reducing water usage by changing our approach to plant selection.
  2. increasing curb appeal while reducing water usage.
  3. changing out spray fixtures for more efficient drip irrigation. Work is underway and is scheduled through August 14.

Student Resident Move-In Days:

  • August 14 - Lone Mountain East Residence Hall
  • August 21-22 - Lower Campus Res Halls, Loyola Village

Move-in day procedures will be similar to prior years. Students and their families will be scheduled for staggered arrivals, For the lower campus, portions of the Golden Gate parking spaces will be cordoned off for traffic flow and drop off. USF Public Safety, SFPD, USF Housing staff will manage traffic and drop-off logistics.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


7/16/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Negoesco Field, Turk Replacement: 

The artificial turf at Negoesco field will be replaced. The project will take 21 days, starting the week of July 19. Equipment and materials will be off-loaded on Parker, near the Negoesco Parker gate and/or the Koret/Parker stairs. Work will begin daily after 8 am. Work on Saturdays is possible but not currently planned.

  • July 19 - Mobilization
  • July 22-30 - DemoJuly 26-30 - Turf Off-HaulJuly 26-Aug 3 - Turk installation Aug 3-12 - Infill placementAug 13 - Demobilization

Lone Mountain Trash & Recycling Facility

  • The existing compactor will be moved to a temporary location at the School of Ed Parking lot-specific date TBD
  • Excavation and grading subject to utility survey. Start date TBD
  • Parking on the Lo Schiavo Drive viaduct will be reduced when construction starts, approximately early June. Alternative parking will be available in the garages beneath the new Lone Mtn Residence Hall; opening date TBD.

War Memorial Gym

  • On-going: Concrete work @WMG Golden Gate frontage/planters. Possibly noisy at times.
  • Concrete pour, July 19 & 20. 1-3 trucks. Possibly noisy at times.
  • Grading and site prep for pavers starts the week of July 19. Installation of pavers for drive west of WMG approximately 1st week of August
  • Ongoing: Finishing interior work: staining, polishing, sealing concrete floors; installation of wood slat ceiling.

Lone Mountain Residence Hall

Delivery and installation of furnishings for dorm rooms, 2 class rooms, and staff apartments will occur periodically through June and July. Details and dates are subject to change without notice. Trucks will deliver onsite, unloading will occur throughout the day.

The Lone Mtn Res Hall site remains is closed to the public and the campus community.

Dining Project

The Lone Mtn Dining Commons site remains closed to the public and the campus community.

Lone Mountain/Turk Landscape

USF plans to update plantings on the center area of Lone Mountain. The plan will focus on water use reduction and plant selection that is sensitive to the environmental changes brought about by climate change while maintaining the formality and gravitas of the existing green spaces.

The priorities for the project are (1) reducing water usage by changing our approach to plant selection; (2) increasing curb appeal while reducing water usage; (3) changing out spray fixtures for more efficient drip irrigation.

Work will begin by the Turk frontage near the Spanish Steps and, later, the landscape within the smaller loop of the drive (i.e. between the Temescal entrance and the Kittridege exit ramp).  Specific start date TBD however this phase is expected to be completed by August 1, 2021.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


7/09/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

War Memorial Gym

  • On-going: Concrete work, WMG Golden Gate frontage/planters
  • Concrete pour week of July 12, specific date TBD. 1-3 trucks
  • Concrete pour, July 19 & 20. 1-3 trucks
  • July/early August: grading and site prep for pavers. Installation of pavers for drive west of WMG approximately 1 week of August
  • Ongoing: Finishing interior work: staining, polishing, sealing concrete floors; installation of wood slat ceiling.

Lone Mountain Residence Hall

Delivery and installation of furnishings for dorm rooms, 2 class rooms, and staff apartments will occur periodically through June and July. Details and dates are subject to change without notice. Trucks will deliver onsite, unloading will occur throughout the day.

  • July 19- July 23: Office/Classroom/Study room furniture; 2 trucks/day. ETA 8:30 am
  • July 26 - July 30 Furniture for res hall lounges.  8:30- 4:30pm. Duration: 2-3 days. 3 trucks (# of trucks per day TBD)
  • Landscaping work for the area east of Drive on-going
  • On-going interior punch list

The Lone Mtn Res Hall site remains is closed to the public and the campus community.

Dining Project

  • On-going interior work to prepare for opening.

The Lone Mtn Dining Commons site remains closed to the public and the campus community.

Lone Mountain Trash & Recycling Facility

  • The existing compactor will be moved to a temporary location at School of Ed Parking lot - week of July 12, specific date TBD
  • Excavation and grading subject to utility survey. Start date TBD
  • Parking on the Lo Schiavo Drive viaduct will be reduced when construction starts, approximately early June. Alternative parking will be available in the garages beneath the new Lone Mtn Residence Hall; opening date TBD.

Lone Mountain/Turk Landscape

USF is developing a plan for landscape planning on the center area of Lone Mountain. The plan will focus on water use reduction and plant selection that is sensitive to the environmental changes brought about by climate change while maintaining the formality and gravitas of the existing green spaces.

The priorities for the project are (1) reducing water usage by changing our approach to plant selection; (2) increasing curb appeal while reducing water usage; (3) changing out spray fixtures for more efficient drip irrigation.

Work will begin by the Turk frontage near the Spanish Steps and, later, the landscape within the smaller loop of the drive (i.e. between the Temescal entrance and the Kittridege exit ramp).  Specific start date TBD however this phase is expected to be completed by August 1, 2021.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


6/11/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

War Memorial Gym

  • Thru June 25 (est): Concrete work, WMG Golden Gate frontage/planters; work will continue through mid-June.
  • Thru June 18 (est):  Roof work: application of new roof exterior membrane. This work will be noisy and disruptive at times.
  • Early July: delivery and installation of pavers for drive west of WMG. Specific dates TBD
  • Ongoing: Finishing interior drywall, framing, duct work, tile work.

Lone Mountain Residence Hall

Delivery and installation of furnishings for dorm rooms, 2 class rooms, and staff apartments will occur periodically through June and July. Details and dates are subject to change without notice. Trucks will deliver onsite, unloading will occur throughout the day.

  • June 14- June 30: Furniture for dorm rooms.  8:00 AM - 4:30 PM.  2 trucks per day (one at 8 AM and the other around 1 PM)
  • July 1- July 2:  Dorm room mattresses; 2 trucks per day
  • July 19- July 23: Office/Classroom/Study room furniture; 2 trucks/day. ETA 8:30 am
  • July 26 - July 30 (Specific dates TBD) Furniture for res hall lounges.  8:30- 4:30pm. Duration: 2-3 days. 3 trucks (# of trucks per day TBD)
  • Landscaping work for the area east of Drive on-going  

The Lone Mtn Res Hall site remains is closed to the public and the campus community.

Dining Project

  • June 17 : Delivery and installation of Dining Commons furniture.
  • June 28-30 : Delivery and installation of Dining Commons furniture.

The Lone Mtn Dining Commons site remains closed to the public and the campus community.

Lone Mountain Trash & Recycling Facility

Construction of the proposed Trash & Recycling Facility, approved by the SF Planning Commission as Component #3 of the Residence Hall Approval Motion March 2018, will begin this month. The 1600sf facility will be located on the north side of Lone Mountain, near the western edge of Lone Mtn North residence hall.  Construction-related traffic will use LoSchiavo Drive on Lone Mountain, entering campus on Parker and exiting on Anza. As with other campus construction, USF will require that contractors adhere to requirements such as following defined traffic patterns and other restrictions to minimize neighborhood impact. Project completion is expected in December 2021.

Parking on the Lo Schiavo Drive viaduct will be reduced when construction starts, approximately early June. Alternative parking will be available in the garages beneath the new Lone Mtn Residence Hall; opening date TBD.

  • June 21 - June 30 - Start site preparation, remove selected trees, and scrub.
  • Late June - Excavation, and grading to begin

Lone Mountain/Turk Landscape

USF is developing a plan for landscape planning on the center area of Lone Mountain. The plan will focus on water use reduction and plant selection that is sensitive to the environmental changes brought about by climate change while maintaining the formality and gravitas of the existing green spaces.

The priorities for the project are (1) reducing water usage by changing our approach to plant selection; (2) increasing curb appeal while reducing water usage; (3) changing out spray fixtures for more efficient drip irrigation.

Work will begin by the Turk frontage near the Spanish Steps and, later, the landscape within the smaller loop of the drive (i.e. between the Temescal entrance and the Kittridege exit ramp). Specific start date TBD however this phase is expected to be completed by August 1, 2021.

Kaiser Vaccine Clinic at USF Koret Rec Center 

  • Kaiser will host its vaccine clinic at the Swig Pavilion in Koret through Friday, June 18 after which it will close.
  • The Kaiser team will break down its setup June 21-25.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


6/4/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

War Memorial Gym

  • Thru June 11 (est): Concrete work, WMG Golden Gate frontage/planters; work will continue through mid-June.
  • Concrete pour, week of June 8, specific date TBD.
  • Thru June 11 (est):  Roof work: application of new roof exterior membrane. This work will be noisy and disruptive at times.
  • June 5:  Power offline inside WMG 7 am-7 pm
  • June 8 (est):  delivery of stadium seating components. Two semis are expected to deliver pallets to Res Hall site at 2500 Turk to temporarily store materiel
  • Early July: delivery and installation of pavers for drive west of WMG. Specific dates TBD.
  • Ongoing: Finishing interior drywall, framing, duct work, tile work.

Lone Mountain Residence Hall

Delivery and installation of furnishings for dorm rooms, 2 class rooms, and staff apartments will occur periodically through June and July. Details and dates are subject to change without notice. Trucks will deliver onsite, unloading will occur throughout the day.

  • June 14- June 30: Furniture for dorm rooms.  8:00 AM - 4:30 PM.  2 trucks per day (one at 8 AM and the other around 1 PM)
  • July 1- July 2:  Dorm room mattresses; 2 trucks per day
  • July 19- July 23: Office/Classroom/Study room furniture; 2 trucks/day. ETA 8:30 am
  • July 26 - July 30 (Specific dates TBD) Furniture for res hall lounges.  8:30- 4:30pm. Duration: 2-3 days. 3 trucks (# of trucks per day TBD)
  • Landscaping work for the area east of Drive on-going

The Lone Mtn Res Hall site remains is closed to the public and the campus community.

Dining Project

  • June 17: Delivery and installation of Dining Commons furniture.
  • June 28-30: Delivery and installation of Dining Commons furniture.

The Lone Mtn Dining Commons site remains closed to the public and the campus community.

Lone Mountain Trash & Recycling Facility

Construction of the proposed Trash & Recycling Facility, approved by the SF Planning Commission as Component #3 of the Residence Hall Approval Motion March 2018, will begin this month. The 1600sf facility will be located on the north side of Lone Mountain, near the western edge of Lone Mtn North residence hall.  Construction-related traffic will use LoSchiavo Drive on Lone Mountain, entering campus on Parker and exiting on Anza. As with other campus construction, USF will require that contractors adhere to requirements such as following defined traffic patterns and other restrictions to minimize neighborhood impact. Project completion is expected in December 2021.

Parking on the Lo Schiavo Drive viaduct will be reduced when construction starts, approximately early June. Alternative parking will be available in the garages beneath the new Lone Mtn Residence Hall; opening date TBD.

  • June 21 - June 30 - Start site preparation, remove selected trees and scrub
  • Late June - Excavation, and grading to begin

Lone Mountain/Turk Landscape 

USF is developing a plan for landscape planning on the center area of Lone Mountain. The plan will focus on water use reduction and plant selection that is sensitive to the environmental changes brought about by climate change while maintaining the formality and gravitas of the existing green spaces.

The priorities for the project are (1) reducing water usage by changing our approach to plant selection; (2) increasing curb appeal while reducing water usage; (3) changing out spray fixtures for more efficient drip irrigation.

Work will begin by the Turk frontage near the Spanish Steps and, later, the landscape within the smaller loop of the drive (i.e. between the Temescal entrance and the Kittridege exit ramp).  Specific start date TBD however this phase is expected to be completed by August 1, 2021.

Kaiser Vaccine Clinic at USF Koret Rec Center

  • Kaiser continues to host a vaccine clinic at the Swig Pavilion in Koret

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


5/28/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

War Memorial Gym

  • May 31: No work at site
  • Thru June 4: Site concrete work along the western facade. Concrete pours for sidewalk, curbs, etc in 2 weeks; date TBD
  • Thru June 11 (est): Concrete work, WMG Golden Gate frontage/planters; work will continue through mid-June. A concrete pour for planter footings next Wednesday June 2; 3-4 trucks will rotate through passenger zone in front of WMG
  • Thru June 11 (est):  Roof work: application of new roof exterior membrane. Removal of existing membrane material first. This work will be noisy and disruptive at times.
  • Ongoing: Finishing interior drywall, framing, duct work, tile work.

Lone Mountain Residence Hall

Delivery and installation of furnishings for dorm rooms, 2 classrooms and staff apartments will occur periodically through June and July. Details and dates are subject to change without notice. Trucks will deliver onsite, unloading will occur throughout the day.

  • May 28: Furnishings for staff apartments 8:30 AM - 4:30 PM. Two trucks
  • June 14- June 30: Furniture for dorm rooms.  8:00AM - 4:30PM.  2 trucks per day (one at 8AM and the other around 1PM)
  • July 1- July 2:  Dorm room mattresses; 2 trucks per day
  • July 19- July 23: Office/Classroom/Study room furniture; 2 trucks/day. ETA 8:30am
  • July 26 - July 30 (Specific dates TBD): Furniture for res hall lounges.  8:30- 4:30pm. Duration: 2-3 days. 3 trucks (# of trucks per day TBD)
  • Landscaping work for area east of Drive on-going

The Lone Mtn Res Hall site remains is closed to the public and the campus community.

Dining Project

  • June: Delivery and installation of Dining Commons furniture. Dates TBD

The Lone Mtn Dining Commons site remains closed to the public and the campus community.

Lone Mountain Trash & Recycling Facility

Construction of the proposed Trash & Recycling Facility, approved by the SF Planning Commission as Component #3 of the Residence Hall Approval Motion March 2018, will begin this month. The 1600sf facility will be located on the north side of Lone Mountain, near the western edge of Lone Mtn North residence hall.  Construction-related traffic will use LoSchiavo Drive on Lone Mountain, entering campus on Parker and exiting on Anza. As with other campus construction, USF will require that contractors adhere to requirements such as following defined traffic patterns and other restrictions to minimize neighborhood impact. Project completion is expected in December 2021.

Parking on the Lo Schiavo Drive viaduct will be reduced when construction starts, approximately early June. Alternative parking will be available in the garages beneath the new Lone Mtn Residence Hall; opening date TBD.

  • May 24 - Clear site, remove selected trees, and scrub.
  • Early June - Excavation, and grading to begin

Lone Mountain/Turk Landscape

USF is developing a plan for landscape planning on the center area of Lone Mountain. The plan will focus on water use reduction and plant selection that is sensitive to the environmental changes brought about by climate change while maintaining the formality and gravitas of the existing green spaces. The priorities for the project are (1) reducing water usage by changing our approach to plant selection; (2) increasing curb appeal while reducing water usage; (3) changing out spray fixtures for more efficient drip irrigation.

Work will begin by the Turk frontage near the Spanish Steps and, later, the landscape within the smaller loop of the drive (i.e. between the Temescal entrance and the Kittridege exit ramp).  Specific start date TBD however this phase is expected to be completed by August 1, 2021.

Kaiser Vaccine Clinic at USF Koret Rec Center

  • Kaiser continues to host a vaccine clinic at the Swig Pavilion in Koret

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


5/24/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

War Memorial Gym

  • Thru May 28: Installation of metal panels on WMG facade
  • Thru June 4  Site concrete work along the western facade. The work will be noisy and disruptive at times.
  • Thru June 11 (est):  Roof work: application of new roof exterior membrane. Removal of existing membrane material first. This work will be noisy and disruptive at times.
  • Thru June 11 (est): Concrete demo work of WMG Golden Gate frontage/planters; work will continue through mid-June. The work will be noisy and disruptive, including periodic use of jackhammers.
  • Ongoing: Finishing interior drywall, skylights, ceiling framing, ductwork, tile work.

Lone Mountain Residence Hall

Delivery and installation of residential furniture. Furnishings for dorm rooms, 2 classrooms, and staff apartments will occur periodically through June and July. Details and dates are subject to change without notice. Trucks will deliver onsite, unloading will occur throughout the day. 

  • May 28:  Furnishings for staff apartments 8:30 AM - 4:30 PM. Two trucks.
  • June 14- June 30: Furniture for dorm rooms.  8:00 AM - 4:30 PM.  2 trucks per day (one at 8 AM and the other around 1 PM)
  • July 26 - July 30 (Specific dates TBD) Furniture for res hall lounges.  8:30- 4:30pm. Duration: 2-3 days. 3 trucks (# of trucks per day TBD)
  • Landscaping work continues

The Lone Mtn Res Hall site remains is closed to the public and the campus community.,

Dining Project

  • June: Delivery and installation of Dining Commons furniture. Dates TBD

The Lone Mtn Dining Commons site remains closed to the public and the campus community. 

Lone Mountain Trash & Recycling Facility

Construction of the proposed Trash & Recycling Facility, approved by the SF Planning Commission as Component #3 of the Residence Hall Approval Motion March 2018, will begin this month. The 1600sf facility will be located on the north side of Lone Mountain, near the western edge of Lone Mtn North residence hall.  Construction-related traffic will use LoSchiavo Drive on Lone Mountain, entering campus on Parker and exiting on Anza. As with other campus construction, USF will require that contractors adhere to requirements such as following defined traffic patterns and other restrictions to minimize neighborhood impact. Project completion is expected in December 2021.

  • May 24 - June 4 - Clear site, remove selected trees, and scrub
  • June 7 - Excavation and grading to begin

Kaiser Vaccine Clinic at USF Koret Rec Center 

  • Kaiser continues to host a vaccine clinic at the Swig Pavilion in Koret

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


5/19/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

War Memorial Gym

  • Thru May 28: Installation of metal panels on WMG facade.
  • Thru June 4 Site concrete work along the western facade. The work will be noisy and disruptive at times.
  • Thru June 11 (est):  Roof work: application of new roof exterior membrane. Removal of existing membrane material first. This work will be noisy and disruptive at times.
  • Thru June 11 (est): Concrete demo work of WMG Golden Gate frontage/planters; work will continue through mid-June. The work will be noisy and disruptive, including periodic use of jackhammers. 
  • Ongoing: Finishing interior drywall, skylights, ceiling framing, ductwork, tile work.

Lone Mountain Residence Hall

  • June: Delivery and installation of residential furniture. Dates TBD. 
  • Landscaping work continues 

The Lone Mtn Res Hall site remains is closed to the public and the campus community.

Dining Project

  • June: Delivery and installation of Dining Commons furniture. Dates TBD

The Lone Mtn Dining Commons site remains closed to the public and the campus community.

Lone Mountain Trash & Recycling Facility

Construction of the proposed Trash & Recycling Facility, approved by the SF Planning Commission as Component #3 of the Residence Hall Approval Motion March 2018, will begin this month. The 1600sf facility will be located on the north side of Lone Mountain, near the western edge of Lone Mtn North residence hall.  Construction-related traffic will use LoSchiavo Drive on Lone Mountain, entering campus on Parker and exiting on Anza. As with other campus construction, USF will require that contractors adhere to requirements such as following defined traffic patterns and other restrictions to minimize neighborhood impact. Project completion is expected in December 2021.

  • May 24 - June 4 - Clear site, remove selected trees, and scrub
  • June 7 - Excavation and grading begins

Kaiser Vaccine Clinic at USF Koret Rec Center

  • May 22: Kaiser Permanente will be open Saturday, May 22 9am - 1pm to vaccinate children between 12-15 years old. 
  • Kaiser continues to host a vaccine clinic at the Swig Pavilion in Koret .

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


5/7/2021 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Residence Hall

The Lone Mtn Res Hall site remains an active construction site under control of Devcon Construction and is closed to the public and the campus community.

  • June: Delivery and installation of residential furniture. Dates to be finalized.
  • Landscaping work continues
  • War Memorial Gym

    • May 10 - June 11 (est)  : Concrete demo work of WMG Golden Gate frontage/planters; work will continue through mid-June. The work will be noisy and disruptive, including periodic use of jackhammers. 
    • Thru May 14 : installation of metal panels on WMG facade.
    • Thru May 14: Site concrete work along the western facade.  Various aspects of this work will continue through April, estimated. The work will be noisy and disruptive at times.
    • Thru May 14: Demo work will begin in the North Lobby interior of WMG.  Will be noisy and disruptive at times.Thru June 11 (est):  Roof work: application of new roof exterior membrane. Removal of existing membrane material first. This work will be noisy and disruptive at times.
    • Finishing interior drywall, skylights, ceiling framing, ductwork, tile work, etc.

    Dining Project

    • June: Delivery and installation of Dining Commons furniture. Specific dates TBD

    The Lone Mtn Dining Commons site remains closed to the public and the campus community.

      

    Kaiser Vaccine Clinic at USF Koret Rec Center

    • Kaiser continues to host a vaccine clinic at the Swig Pavilion in Koret 

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance

      

    4/30/2021 Update:

    All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

    Lone Mountain Residence Hall

    • Delivery and installation of residential unit appliances ongoing.
    • Landscaping work continues

    The Lone Mtn Res Hall site remains an active construction site under the control of Devcon Construction and is closed to the public and the campus community.

    War Memorial Gym

    • April 13 - May 14: installation of metal panels on WMG facade.  Various aspects of this work will continue through mid-May.
    • April 14 - May 5: Site concrete work along the western facade.  Various aspects of this work will continue through April, estimated. The work will be noisy and disruptive at times.
    • May 3 - 10: Work will begin in the North Lobby interior of WMG; will include substantial demo work which will be noisy and disruptive at times. 
    • May 3 - June 11 (est):  Roof work: application of new roof exterior membrane. Removal of existing membrane material first. This work will be noisy and disruptive at times.
    • May 8 - Concrete pour. Interior topping slab. 
    • May 10 - June 11 (est): Concrete demo work of WMG Golden Gate frontage/planters; work will continue through mid-June. The work will be noisy and disruptive, including periodic use of jackhammers. 
    • Finishing interior drywall, skylights, ceiling framing, ductwork, tile work, etc.

    Dining Project

    • Furnishings delivery and installation. TBD

    The Lone Mtn Dining Commons site remains closed to the public and the campus community.

    Kaiser Vaccine Clinic at USF Koret Rec Center

    • Kaiser continues to host a vaccine clinic at the Swig Pavilion in Koret

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance

      

    4/26/2021 Updates:

    All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

    Lone Mountain Residence Hall

    • Delivery and installation of residential unit appliances ongoing.
    • Landscaping work continues. 

    The Lone Mtn Res Hall site remains an active construction site under the control of Devcon Construction and is closed to the public and the campus community.

    War Memorial Gym

    • April 13 - 30: installation of metal panels on WMG facade.  Various aspects of this work will continue through April, estimated.
    • April 14 - 30: Site concrete work along the western facade.  Various aspects of this work will continue through April, estimated. The work will be noisy and disruptive at times.
    • April 26 - 30: install wooden fence panels in front of WMG to enclose the work area.
    • May 3 - 10: Work will begin in the North Lobby interior of WMG; will include substantial demo work which will be noisy and disruptive at times.
    • May 10 - June 11 (est)  : Concrete demo work of WMG Golden Gate frontage/planters; work will continue through mid June. The work will be noisy and disruptive at times.
    • Finishing interior drywall, skylights, ceiling framing, duct work, tile work, etc.

    Dining Project

    The Lone Mtn Dining Commons site remains closed to the public and the campus community.

    • Final inspection signed off.
    • Delivery and installation of residential unit appliances ongoing.
    • Landscaping work continues 

    The Lone Mtn Res Hall site remains an active construction site under the control of Devcon Construction and is closed to the public and the campus community.

    War Memorial Gym

    • April 13 - 30 : installation of metal panels on WMG facade begins about 4/13.  Various aspects of this work will continue through April, estimated.
    • April 14 - 30 : Site concrete work along western facade.  Various aspects of this work will continue through April, estimated. The work will be noisy and disruptive at times.
    • Work will begin in the North Lobby of WMG which will include substantial demo work which will be noisy and disruptive at times.  Dates TBD.
    • Finishing drywall, skylights, ceiling framing, duct work, tile work, etc

    Dining Project

    • April 14-15: Slurry coat and seal Lone Mtn back parking lot (NW back corner). Repaint parking places. Lot will be closed 4/14-15
    • Final floor polish in main dining area complete; Lone Mtn North bridge reopened. Final polish of Pavilion to be completed. Time TBD.
    • Final installation of furnishings TBD
    • Final inspection pending schedule confirmation.

    The Lone Mtn Dining Commons site remains an active construction site under control of Cahill Construction and is closed to the public and the campus community.

    KAISER VACCINE CLINIC AT USF KORET REC CENTER

    • Kaiser continues to host a vaccine clinic at the Swig Pavilion in Koret

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    4/1/2021 Update:

    All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

    Lone Mountain Residence Hall

    • Delivery and installation of residential unit appliances ongoing. 
    • Landscaping work continues 
    • Punchlist activities continue

    The Lone Mtn Res Hall site remains an active construction site under control of Devcon Construction and is closed to the public and the campus community.

    War Memorial Gym

    • April 5 - 30 : prep work for painting steel supports for screen facade on WMG north elevation. Painting likely April 5-6.  Various aspects of this work will continue through April, estimated.
    • Work will begin in the North Lobby of WMG which will include substantial demo work which will be noisy and disruptive at times.  Dates TBD.
    • Finishing drywall, skylights, ceiling framing, duct work, tile work, etc.
    • Finishing exterior glazing installation.

    Dining Project

    March 29 - April 12: Final floor polish; work has been extended to finish by April 12. Dining Area will be closed including throughway to LM North and its bridge. There will be no access to LMNorth from LMMain during this time period.

    • Final installation of furnishings TBD
    • Final inspections continue
    • Back parking lot: Re-striping date TBD

    The Lone Mtn Dining Commons site remains an active construction site under control of Cahill Construction and is closed to the public and the campus community.

    Kaiser Vaccine Clinic at USF Koret Rec Center

    • Kaiser continues to host a vaccine clinic at the Swig Pavilion in Koret

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    3/26/21 Update:

    All dates below are best estimates, subject to impacts of weather, other external events, and may change without notice.

    Lone Mountain Residence Hall

    • Delivery and installation of residential unit appliances ongoing.
    • Landscaping work continues
    • Punchlist activities continue

    The Lone Mtn Res Hall site remains an active construction site under control of Devcon Construction and is closed to the public and the campus community.

    War Memorial Gym

    • Work will begin in the North Lobby of WMG which will include substantial demo work which will be noisy and disruptive at times.  Dates TBD.
    • Finishing internal framing, vertical supports, duct work, plumbing, etc.
    • USF Athletics at WMG:
      • March 26. 6pm Wms Volleyball vs Santa Clara
      • All games closed to fans; only student-athletes and athletic staff in attendance.  Game dates & times subject to change without notice here. For men’s and women’s teams, home and away games.
      • Covid guidances require two buses per traveling team.

    Dining Project

    March 29 - April 5: Final floor polish. Dining Area will be closed including throughway to LM North and its bridge. There will be no access to LMNorth from LMMain during this time period. The LM bridge will close at approximately 6am March 29.

    • Final installation of furnishings
    • Final inspections continue
    • Back parking lot: Re-striping date TBD

    The Lone Mtn Dining Commons site remains an active construction site under control of Cahill Construction and is closed to the public and the campus community.

    Kaiser Vaccine Clinic at USF Koret Rec Center

    • Kaiser continues to host a vaccine clinic at the Swig Pavilion in Koret

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    3/19/2021 Updates:

    All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

    Lone Mountain Residence Hall

    • Delivery and installation of residential unit appliances ongoing.
    • Landscaping work continues
    • Punchlist activities continue

    The Lone Mtn Res Hall site remains an active construction site under the control of Devcon Construction and is closed to the public and the campus community.

    War Memorial Gym

    • Work will begin in the North Lobby of WMG which will include substantial demo work which will be noisy and disruptive at times.  Dates TBD.
    • Finishing framing, vertical supports, ductwork,etc
    • Finishing exterior glazing installation.
    • USF Athletics at WMG:
      • March 19. Noon Wms Volleyball vs Gonzaga
      • March 20. Noon Wms Volleyball vs Gonzaga
      • March 26. 6 pm Wms Volleyball vs Santa Clara 
      • All games closed to fans; only student-athletes and athletic staff in attendance.  Game dates & times subject to change without notice here. For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team.

    Dining Project

    March 29 - April 5: Final floor polish. Dining Area will be closed including the throughway to LM North and its bridge. There will be no access to LMNorth from LMMain during this time period.

    • Final installation of furnishings TBD
    • Final inspections continue
    • Back parking lot: Re-striping date TBD

    The Lone Mtn Dining Commons site remains an active construction site under control of Cahill Construction and is closed to the public and the campus community.

    Kaiser Vaccine Clinic at USF Koret Rec Center

    • Kaiser continues to host a vaccine clinic at the Swig Pavilion in Koret

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    3/12/Update:

    All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

    Lone Mountain Residence Hall

    • Delivery and installation of residential unit appliances ongoing.
    • Landscaping work continues
    • Punchlist activities continue

    The Lone Mtn Res Hall site remains an active construction site under control of Devcon Construction and is closed to the public and the campus community.

    War Memorial Gym

    • March 15; 7am-5pm: Water line cutover. Water service will be shut off to University Center, War Memorial Gym, Toler, Hayes, Gillson, Fromm, and Harney
    • March 13, Saturday 8am- 4pm  Steel workers finishing pan deck at SW corner of WMG. Some noise after 9am
    • Finishing framing, vertical supports, duct work,etc
    • Finishing exterior glazing installation.
    • USF Athletics at WMG:
      • March 13. 4pm Wms Volleyball vs St Mary’s
      • March 19. Noon Wms Volleyball vs Gonzaga
      • March 20. Noon Wms Volleyball vs Gonzaga
      • March 26. 6pm Wms Volleyball vs Santa Clara 
      • All games closed to fans; only student-athletes and athletic staff in attendance.  Game dates & times subject to change without notice here. For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team.

    Dining Project

    • Final polish of Dining Commons flooring last week of March, details TBD - about 2 days duration
    • Final installation of furnishings TBD
    • Final inspections continue
    • Back parking lot: Re-striping date TBD

    The Lone Mtn Dining Commons site remains an active construction site under control of Cahill Construction and is closed to the public and the campus community.

    Kaiser Vaccine Clinic at USF Koret Rec Center

    • Kaiser continues to host a vaccine clinic at the Swig Pavilion in Koret

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    3/5/2021 Update:

    All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

    Lone Mountain Residence Hall

    • Delivery and installation of residential unit appliances. Ongoing.
    • Punchlist activities continue

    The Lone Mtn Res Hall site remains an active construction site under control of Devcon Construction and is closed to the public and the campus community.

    War Memorial Gym

    • March 15; 7am-3pm: Water line cutover. Water service will be shut off to University Center; Toler, Hayes Healy, Gillson, Fromm Res Halls, and Harney 7am-3pm.
    • Finishing framing, vertical supports, ductwork,etc.
    • Finishing exterior glazing installation.
    • USF Athletics at WMG:
      • All games closed to fans; only student-athletes and athletic staff in attendance.  Game dates & times subject to change without notice here. For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team.

    Dining Project

    • Final polish of Dining Commons flooring TBD - about 2 days duration
    • Final installation of furnishings TBD
    • Final inspections continue
    • Back parking lot: Clean up and clearing out site. Re-striping date TBD
    • Barricades coming down:

    The Lone Mtn Dining Commons site remains an active construction site under control of Cahill Construction and is closed to the public and the campus community.

    Kaiser Vaccine Clinic at USF Koret Rec Center

    • Kaiser continues to host a vaccine clinic for its members at the Swig Pavilion in Koret

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c  April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    3/1/2021 Update:

    Please note:

    Water line cutover schedule at War Memorial Gym is changed and will be on March 15; 7 am-3 pm. Water service will be shut off to University Center; Toler, Hayes Healy, Gillson, Fromm Res Halls, and Harney 7 am-3 pm.


    2/26/2021 Updates:

    All dates below are best estimates, subject to impacts of weather, other external impacts and may change without notice. 

    Lone Mountain Residence Hall

    • Delivery and installation of residential unit appliances. Ongoing.
    • Punchlist activities continue

    Please remember that the Lone Mtn Res Hall site is an active construction site under the control of Devcon Construction and remains closed to the public and to the campus community.

    War Memorial Gym

    • Waterline installation:  March 9; 7 am-3 pm: water line cutover. Water service will be shut off to University Center; Toler, Hayes Healy, Gillson, Fromm Res Halls, and Harney 7 am-3 pm.
    • Finishing framing, vertical supports, ductwork, etc.
    • Finishing exterior glazing installation.
    • USF Athletics at WMG:
      • Feb 27 6pm. USF MBB vs Santa Clara. Televised. Details TBD.
      • All games closed to fans; only student-athletes and athletic staff in attendance.  Game dates & times subject to change without notice here. For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team.

    Dining Project

    • Completion of installation of interior fixtures.
    • Final installation of furnishings TBD
    • Final inspections continue
    • Back parking lot surface: re-striping date TBD
    • Steelworkers are on-site to complete installation of external handrails. 
    • Fine tuning systems and inspections: electrical, ventilation, heating systems, appliances

    Kaiser Vaccine Clinic at USF Koret Rec Center

    • Kaiser continues to host a vaccine clinic for its members at the Swig Pavilion in Koret 

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    2/19/2021 Updates:

    All dates below are best estimates, subject to impacts of weather, other external impacts and may change without notice.

    Lone Mountain Residence Hall

    • February 22:  At Loyola House parking lot, removal of camera carriage in the morning of 2/22. Please keep adjacent parking spaces clear.
    • Feb 16 - 26  finishing work on the reconstruction of lawn area along Turk frontage.
    • Delivery and installation of residential unit appliances. Ongoing.
    • Punchlist activities continue

    War Memorial Gym

    • Waterline installation continues and will involve tie-in to Golden Gate Ave. Work requires trenching, shoring, soil off-haul. 
    • Continue finishing exterior walls: framing, vertical supports, etc
    • Finishing exterior glazing installation.
    • USF Athletics at WMG:
      • Feb 27 6pm. USF MBB vs Santa Clara. Televised. Details TBD.
      • All games closed to fans; only student-athletes and athletic staff in attendance.  Game dates & times subject to change without notice here. For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team.

    Dining Project

    • Completion of installation of interior fixtures. Furnishing final installation TBD
    • Final inspections continue
    • Back parking lot surface: re-striping date TBD
    • Steelworkers are on-site to complete the installation of external handrails. 
    • Fine-tuning systems and inspections: electrical, ventilation, heating systems, appliances

    Kaiser Vaccine Clinic at USF Koret Rec Center

    • Kaiser is hosting a vaccine clinic for its members at the Swig Pavilion in Koret.
    • Monday 2/22 and Tuesday 2/23 HALF DAYS.  9am-12pm
    • Wednesday 2/24, Thursday 2/25, and Friday 2/26  FULL DAYS. 9am-4pm
    • Monday 3/1 and Tuesday 3/2: 9a-4p

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    2/12/2021 Update:

    All dates below are best estimates, subject to impacts of weather, other external impacts and may change without notice.

    Lone Mountain Residence Hall

    • Feb 15: No work on site 
    • Fire Systems testing continues:  Feb 16-19 final tests
    • Feb 16 - 19  finishing work on reconstruct lawn area along Turk frontage.
    • Delivery and installation of residential unit appliances. Ongoing.

    War Memorial Gym

    • Waterline installation, previously delayed by rain, continues with the tie-in to Golden Gate Ave. Will involve excavator, trenching, shoring, soil off-haul. 
    • Concrete pour completed. Sawcutting Feb 12; 16. 
    • Continue finishing exterior walls: framing, vertical supports, etc
    • Finishing exterior glazing installation. 
    • USF Athletics at WMG.  Please note:
      • Feb 13, 3 pm USF MBB vs Gonzaga.  Televised: TV truck will arrive onsite at 6 am
      • Feb 18, 6 pm USF MBB vs LMU. Televised. Details TBD
      • Feb 27 6pm. USF MBB vs Santa Clara. Televised. Details TBD. 
      • All games closed to fans; only student-athletes and athletic staff in attendance.  Game dates & times subject to change without notice here. For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team. 

    Dining Project

    • Wed Feb 17  Final test Ansul kitchen fire suppression systems.  Some brief alarm noise
    • Back parking lot surface: power wash complete. Re-striping date TBD
    • Fire systems testing. Most of the testing is silent but alarm tests can occur periodically
    • Finetuning systems and inspections: electrical, ventilation, heating systems, appliances

    Kaiser Vaccine Clinic at USF Koret Rec Center

    • Kaiser is hosting a vaccine clinic for its members at the Swig Pavilion in Koret. Schedule next week:  9a-4.30pm next Tuesday 2/16 and Thursday 2/18

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    2/09/2021 Update:

    Regarding the WMG Sobrato Center project, work involving the water line installation will focus this week at the southwest corner WMG, outside the lower level east entrance to the UC. Cahill will barricade a portion of the drive outside their barrier fence at the south end of the project and start pot-holing and trenching. The work is likely to continue through this week.


    2/05/2021 Update:

    All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

    Lone Mountain Residence Hall

    • Fire Systems testing:  Feb 8: 4:00 pm - 9:00 pm - Under the direction of the SF Fire Marshall, testing will involve staggered power shutdowns to test fire doors & alarm systems. Testing on 2/8 will largely occur in the West Bldg
    • Work continues to reconstruct the lawn area along the Turk frontage. Planting sod is subject to weather: 5 rainless days needed
    • Delivery and installation of residential unit appliances. Ongoing.

    War Memorial Gym

    • Feb 1-11 water line installation, previously delayed by rain, will begin with the tie-in to Golden Gate Ave. Will involve excavator, trenching, shoring, soil off-haul.
    • Feb 8 - 11 concrete pour at pan deck involving about 8 trucks, staggered throughout the day. Continue finishing exterior walls: framing, vertical supports, etc. Finishing exterior glazing installation.   USF Athletics at WMG.  Please note:
      • Feb 6, 2 pm WMBB game Feb 9:  USF WM Basketball 2 pm at WMGymFeb 10, 2 pm USF M Basketball vs Pepperdine at WMGym. Televised: The TV truck will arrive onsite at 6 am Feb 10. 7 pm. USF Volleyball vs University of the PacificFeb 13, 3 pm USF MBB vs Gonzaga.  Televised: The TV truck will arrive onsite at 6amFeb 18 at 6 pm USF MBB vs LMU. Televised. Details TBD Feb 27 6pm. USF MBB vs Santa Clara. Televised. Details TBD. All games closed to fans; only student-athletes and athletic staff in attendance.  Game dates & times subject to change without notice here. For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team.

    Dining Project

    • Feb 9, 10: Powerwash back parking lot surface. Somewhat noisy.  Re-striping date TBD
    • Wed Feb 10 and Wed Feb 17 9-10am. Test Ansul kitchen fire suppression systems.  Some brief alarm noise
    • Fire systems testing. Most of the testing is silent but alarm tests can occur periodically.
    • Finalizing installation and connections of electrical, ventilation, heating systems.
    • Finalizing hardscape, and lighting.

    Lone Mountain Power upgrade

    • Power switchover completed.

    Kaiser Vaccine Clinic at USF Koret Rec Center

    • Kaiser will host a vaccine clinic at the Swig Pavilion in Koret. Not yet open but it will be by appointment only.  Details will follow.  Automobile entry at Turk, lower lot.

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    1/29/2021 Updates:

    All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

    Lone Mountain Residence Hall

    • Fire Systems testing:  Jan 30: 7:30a - 3:30 pm - Under the direction of the SF Fire Marshall, testing will involve staggered power shutdowns to test fire doors & alarm systems. Saturday testing will start in the West Bldg.
    • Work continues to reconstruct the lawn area along the Turk frontage.
    • Landscaping /planting nearing completion in courtyards and Paseo.
    • Delivery and installation of residential unit appliances. Ongoing.

    War Memorial Gym

    • Feb 1-11 water line installation, previously delayed by rain, will begin with a tie-in to Golden Gate Ave. Will involve excavator, trenching, shoring, soil off-haul.
    • Feb 8 - 11 concrete pour at pan deck involving about 8 trucks, staggered throughout the day.
    • Continue finishing exterior walls: framing, vertical supports, etc
    • Finishing exterior glazing installation.
    • Please note:
      • Feb 2,3:  USF Volleyball 6 pm at WMGym
      • Feb 9:  USF WM Basketball 2 pm at WMGym.
      • Feb 9   USF M Basketball vs Pepperdine 6 pm at WMGym
      • games closed to fans; only student-athletes and athletic staff in attendance.
      • For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team.

    Dining Project

    • Fire systems testing. Most of the testing is silent but the alarm test will be scheduled for about noon. Specific date TBD.
    • Backlot - clearing out Cahill yard ongoing.
    • Finalizing installation and connections of furnishings & finishes.
    • Finalizing exterior painting, hardscape, and lighting

    Lone Mountain Power upgrade

    • Power switchover completed.  Powering up sequences continue periodically at Dining Commons  

    Covid-19

    at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    1/25/2021Update:

    PG&E completed its power switchover last week. Today, Paganini electricians have been working on adjusting the sensitivity of the main breaker. They will return tonight after 6 pm to run some tests. The tests this evening may trip a breaker which could cause a short power outage at Lone Mtn Main and a brief loss of hot water in Loyola House.

    Thank you for your patience.


    1/22/2021 Update:

    All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

    Lone Mountain Residence Hall

    • Fire Systems testing:
      • Jan 23,  7am - 3:30pm
      • Jan 26, Jan 27: 4 - 8:30pm
      • Under the direction of the SF Fire Marshall, testing will involve staggered power shutdowns to test fire doors & alarm systems.
      • Saturday testing will start in the West Bldg.
    • Work continues to reconstruct lawn area along Turk frontage
    • Landscaping /planting nearing completion in courtyards and Paseo.
    • Delivery and installation of residential unit appliances. Ongoing.

    War Memorial Gym

    • Jan 25 - Feb 26: water line installation with the tie into Golden Gate Ave. Will involve excavator, trenching, shoring, soil off-haul. 
    • Jan 27:  Placement of rooftop fans on WMG. A crane will be onsite to lift the fans onto the roof. 
    • Feb 8-11 estimated date window for concrete pours of pan deck. 8-10 trucks.
    • Continue finishing exterior walls: framing, vertical supports, etc
    • Finishing exterior glazing installation. 
    • Please note:
      • Jan 25, 2pm:  USF WBB vs Pepperdine
      • Feb 2,3:  USF Volleyball 6pm at WMGym
      • Feb 9:  USF WM Basketball 2 pm at WMGym
      • Feb 9   USF M Basketball  vs Pepperdine 6 pm at WMGym
      • All games closed to fans; only student-athletes and athletic staff in attendance.
      • For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team.

    Dining Project 

    • Jan 28  Fire systems testing.  Most of the testing is silent but the alarm test is scheduled for about noon.
    • Backlot - clearing out Cahill yard ongoing
    • Finalizing installation and connections of furnishings & finishes.
    • Finalizing exterior painting, hardscape, and lighting

    Lone Mountain Power upgrade

    • Power switchover completed.  Electricians will complete powering up sequences at Dining Commons the week of Jan 25.

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    01/15/2021 Update:

    All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

    Lone Mountain Residence Hall

    • Jan 19 - 20, Jan 23: Fire Alarm testing 4:30 pm - 9 pm will involve staggered power shutdowns, testing fire doors & alarm systems. Alarms will mostly be tested on Saturday 1/23.
    • Work continues to reconstruct lawn area along Turk frontage including:
      • Landscaping /planting in courtyards and Paseo.
      • Periodic concrete pours to complete curbs, stairs, walkways within the boundaries of the construction site.
      • Delivery and installation of residential unit appliances. Ongoing.

    War Memorial Gym

    • Jan 25 - Feb 26: water line installation with a tie into Golden Gate Ave. Will involve excavator, trenching, shoring, soil off-haul.
    • Continue finishing exterior walls: framing, vertical supports, etc.
    • Finishing exterior glazing installation.
    • Please note: 
      • Jan 16, Noon:  USF WBB vs Gonzaga
      • Jan 16, 7 pm:  USF MBB vs BYU. Televised, ESPN truck arrives approx 11:30 am 
      • Feb 25, 2pm   USF WBB vs Pepperdine
      • Feb 9:  USF WM Basketball 2 pm at WMGym
      • Feb 9   USF M Basketball 6 pm at WMGym
      • All games closed to fans; only student-athletes and athletic staff in attendance. For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team.

    Dining Project 

    • Punch walks continue
    • Back lot - clearing out Cahill yard ongoing
    • Finalizing installation and connections of furnishings & finishes.
    • Finalizing exterior painting, hardscape, and lighting

    Lone Mountain Power upgrade

    • Power switchover Thursday 1/21 9 pm - 7:30 am 1/22 Friday.  No power at Lone Mtn Main, Pacific Wing, Rossi Wing from 9 pm-7:30 am.  Loyola House will have no hot water, no heat during those hours. 

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    01/14/2021 Update:

    Next Thursday, PG&E will cut over power to the new Res Hall project.

    The process will occur overnight from 9 pm Thursday 1/21 until 7:30 am Friday, Jan 22.

    Lone Mountain Main, Rossi Wing, and Pacific Wing will have no lights/no power during that time except that the Data Center in Pacific Wing and Dispatch in Lone Mtn Main will run on generator power.

    We apologize for any inconvenience.


    01/08/2021 Updates:

    All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

    Lone Mountain Residence Hall

    • Work continues to reconstruct lawn area along Turk frontage including:
      • Finish hillside;  fine grading, plant hydro seed and shrubbery at trash facility
    • Landscaping /planting in courtyards and Paseo
    • Periodic concrete pours to complete curbs, stairs, walkways within the boundaries of the construction site.
    • Delivery and installation of residential unit appliances. Ongoing.

    War Memorial Gym

    • Jan 13 Concrete pour, small, 1-2 trucks; SE corner of site
    • Jan 15 Place roof top fans; will require a crane truck onsite 8am-3pm
    • Continue finishing exterior walls: framing, vertical supports, etc
    • Continued work on glazing installation. 
    • Please note: 
      • Feb 9:  USF WM Basketball 2pm at WMGym
      • Feb 9   USF M Basketball 6pm at WMGym
      • All games closed to fans; only student-athletes and athletic staff in attendance.
      • For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team.

    Dining Project 

    • Punch walks continue
    • Backlot - clearing out Cahill yard ongoing
    • Jan 21 - estimated date: slurry back lot surface
    • Finalizing installation and connections of furnishings & finishes.
    • Finalizing exterior painting, hardscape, and lighting

    Lone Mountain Power upgrade

    • PGE work complete. Remaining work onsite in Lone Mtn Main.

    Covid-19

    Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


    12/18/2020 Update:

    All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

    Lone Mountain Residence Hall

    • Work continues to reconstruct lawn area along Turk frontage including:
      • Regrade hillside, moving soils
      • Dec 21 -22 Import new soil   This will involve trucks driving on-site throughout the day.
    • Landscaping /planting in courtyards and Paseo.
    • Wrought iron fence southeast corner Dec 21.
    • Periodic concrete pours to complete curbs, stairs, walkways within the boundaries of the construction site.
    • Painting in residential units through mid-January.
    • Delivery and installation of residential unit appliances. Ongoing. 
    • War Memorial Gym

      • Dec 22: Concrete pour, small, 1-2 trucks 
      • Continue finishing exterior walls, glazing, framing, vertical supports, etc
      • Holiday schedule: 1/2 days on Christmas and New Year’s Eves; Site closed on Christmas Day and New Year’s Day.
      • Please note - Intercollegiate Athletics:
        • Jan  4   USF WM Basketball vs Loyola Marymount 2 pm at WMGym All games closed to fans; only student-athletes and athletic staff in attendance. For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team.

      Dining Project 

      • Dec 21-23  Glazing installation, outdoor canopy.
      • Finishing interior: millwork and electrical.
      • Finalizing exterior painting, hardscape, and electrical.
      • Remove construction trailer from backlot, mid-January.
      • Holiday schedule: 1/2 days on Christmas and New Year’s Eve; Site closed Christmas Day and New Year’s Day.

      Lone Mountain Power upgrade 

      • PGE has started work. PGE schedule is not subject to USF control.  Projected January completion.

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      12/11/2020 Updates:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • Dec 7 - 18: work continues to reconstruct lawn area along Turk frontage including: 
        • Demo temporary road across from Roselyn Terrace, removing asphalt, saw cutting, etc. 2-4 days.  Noisy and disruptive work. Starts on Dec 7.
        • Regrade hillside, moving soils, covering the infiltration basin. Work will require earth moving equipment and will be noisy and disruptive.
        • Off-haul the remaining soil pile on Wednesday (12/16/2020).  This will involve loading trucks throughout the day.
      • Landscaping east side - installing jute for erosion control.
      • Landscaping /planting in courtyards and Paseo.
      • Periodic concrete pours to complete curbs, stairs, walkways within the boundaries of the construction site; should be complete by next week.
      • Delivery and installation of residential unit appliances. Ongoing.

      War Memorial Gym

      • Concrete pour, small, 1-2 trucks.
      • Continue finishing exterior walls: framing, vertical supports, etc.
      • Continued work on glazing installation.
      • Dec 14: Skylights delivery.
      • Ongoing: framing, water proofing, fireproofing.
      • Holiday schedule: 1/2 days on Christmas and New Year’s Eves; Christmas Day and New Year’s Day - site closed.
      • Please note: 
        • Dec 18  USF WM Basketball vs Wm Jessop College 2pm at WM Gym.
        • Jan  4   USF WM Basketball vs Loyola Marymount  2pm at WM Gym.
        • All games closed to fans; only student-athletes and athletic staff in attendance.
        • For men’s and women’s teams, home and away games, Covid guidances require two buses per traveling team.

      Dining Project

      • Punch walks continue.
      • Dec 14 -18 Glazing installation.
      • Finalizing installation and connections of furnishings & finishes.
      • Finalizing exterior painting, hardscape, and lighting.
      • Holiday schedule: 1/2 days on Christmas and New Year’s Eves; Christmas Day and New Year’s Day - site closed

      Lone Mountain Power upgrade

      • PGE has started work. PGE schedule is not subject to USF control.  Projected January completion.

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      12/04/2020 Update:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.  

      Lone Mountain Residence Hall

      • Dec 7 - 14: work begins to reconstruct lawn area along Turk frontage including:
        • Demo temporary road across from Roselyn Terrace, removing asphalt, sawcutting, etc. 2-4 days.  Noisy and disruptive work. Starts Dec 7.
        • Regrade hillside, moving soils, covering infiltration basin. Work will require earth moving equipment and will be noisy and disruptive. 
        • 2-3 weeks overall, depending on weather and other factors.
      • Landscaping - clear & grub continues at east side hill. 
      • Landscaping /planting in courtyards and Paseo
      • Periodic concrete pours to complete curbs, stairs, walkways within the boundaries of the construction site; should be complete by next week.
      • Delivery of residential unit appliances. Ongoing.
      • Continued work on finishing installations for residential units.

      War Memorial Gym

      • Dec 8: Concrete pour, small, 1-2 trucks.
      • Continue finishing exterior walls: framing, vertical supports, etc.
      • Ongoing: framing, waterproofing, fireproofing

      Dining Project 

      • Punch walks continue
      • Finalizing installation and connections of furnishings & finishes. Finalizing exterior hardscape and lighting

      Lone Mountain Power upgrade  

      • PGE will begin work on this. Projected January completion.

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      11/20/2020 Update:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • Nov 21; Nov 27/28: The exterior construction elevator, located on the south side of the West Building was recently removed. That section of the building is open to the elements therefore construction crews will work to complete closing that wall in the next 10 days, Thanksgiving holiday and Sundays excepted.
      • Nov 23: Removal of small container boxes from site
      • Dec 1: begin removing construction trailers from site
      • Dec 7 - 14: work begins to reconstruct lawn area along Turk frontage including:
        • Demo temporary road across from Roselyn Terrace, removing asphalt, saw cutting, etc. 2-4 days.  Noisy and disruptive work.
        • Regrade hillside, moving soils, covering the infiltration basin. Work will require earth moving equipment and will be noisy and disruptive.
        • 2-3 weeks overall, depending on weather and other factors.
      • Landscaping - clear & grub continues at east side hill.
      • Landscaping /planting in courtyards and Paseo
      • Periodic concrete pours to complete curbs, stairs, walkways within the boundaries of the construction site. 
      • Delivery of residential unit appliances. Ongoing.
      • Continued work on finishing installations for residential units.

      War Memorial Gym

      • Nov 20: Temporary power shut down WMGym only. 5pm-midnight
      • Nov 23: Deliveries for glazing
      • Nov 26-27  Site closed
      • Dec 1,2: Concrete pours, small, 1-2 trucks
      • Begin finishing exterior walls: framing, vertical supports, etc
      • Continued work on glazing installation.
      • Ongoing: framing, water proofing, fireproofing

      Dining Project 

      • Nov 23: Punch walk
      • Nov 26-27  Site closed
      • Nov 30: Delivery of market shelving
      • Finalizing installation and connections of furnishings & finishes.
      • Finalizing exterior hardscape and lighting

      Lone Mountain Power upgrade

      • Test pipe inspection completed.  Further work pending scheduling decision by PGE.

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      11/13/2020 Update:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • Dec 1: begin removing construction trailers from site
      • Dec 7: work begins to reconstruct lawn area along Turk frontage including:
        • Demo temporary road across from Roselyn Terrace, removing asphalt, saw cutting, etc. 2-4 days.  Noisy and disruptive work.
        • Regrade hillside, moving soils, covering the infiltration basin. Work will require earth moving equipment and will be noisy and disruptive. 
        • 2-3 weeks overall, depending on weather and other factors.
      • Landscaping - clear & grub continues at east side hill. 
      • Landscaping /planting in courtyards and Paseo
      • Periodic concrete pours to complete curbs, stairs, walkways within the boundaries of the construction site.
      • Delivery of residential unit appliances. Ongoing.
      • Continued work on finishing installations for residential units.
      • Installation of plumbing & sprinkler systems ongoing 
      • The ongoing removal of scaffolding throughout sections of the site.

      War Memorial Gym

      • Nov 20: Temporary power shut down WMGym only. 5 pm-midnight
      • Begin finishing exterior walls: framing, vertical supports, etc
      • Glazing install: framing starts the week of Nov 16
      • Ongoing roof work on the addition: framing, waterproofing, fireproofing
      • Mechanical, electrical, plumbing subcontractors on site. 

      Dining Project

      • Finalizing installation and connections of furnishing & fixtures. 
      • Finalizing installation of millwork, casework, tilework.
      • Begin prepping and cleaning for the punch list.  

      Lone Mountain Power upgrade

      • Test pipe inspection completed.  Further work pending scheduling decision by PGE

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      11/06/2020 Updates:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • Landscaping - clear & grub of east sidehill, early November.
      • Landscaping /planting in courtyards and Paseo
      • Periodic concrete pours to complete curbs, stairs, walkways within the boundaries of the construction site.   
      • Delivery of residential unit appliances. Ongoing.
      • Continued work on finishing installations for residential units.
      • Continued work on exterior & courtyards; installing Juliette rails, balustrades, drywall, interior painting, electrical
      • Deliveries of material to finish interior units will be ongoing.
      • Installation of plumbing & sprinkler systems ongoing
      • The ongoing removal of scaffolding throughout sections of the site.

      War Memorial Gym

      • Nov 9, 10: Sawcut openings in the shear wall, west side, lower level. Noisy work. 8 am start
      • Nov 12 or 13: small concrete pour. Southside.
      • Nov 13: Temporary power shut down WMGym only. 5 pm -midnight
      • Ongoing roof work on the addition: framing, waterproofing, fireproofing
      • Mechanical, electrical, plumbing subcontractors on site.

      Dining Project

      • Ongoing installation and connections of furnishing & fixtures
      • Ongoing installation of millwork, casework, tilework
      • Periodic deliveries of materials.

      Lone Mountain Power upgrade

      • Test pipe inspection completed.  Further work pending scheduling decision by PGE.

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create,  adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety  Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are  tasked with making sure workers follow those guidelines and maintain social distance


      11/2/2020 Update:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Election Day

      The main lobby of War Memorial Gym at 2335 Golden Gate Ave will serve as an election polling station on Tuesday Nov 3, 7am - 8pm

      Lone Mountain Residence Hall

      • Landscaping - clear & grub of east side hill, early November. Landscaping /planting in courtyards and Paseo
      • Periodic concrete pours to complete curbs, stairs, walkways within the boundaries of the construction site.    
      • Delivery of residential unit appliances. Ongoing periodically. 
      • Continued work on finishing installations for residential units.
      • Continued work on exterior & courtyards; installing Juliette rails, balustrades, drywall, interior painting, electrical   
      • Deliveries of materiel to finish interior units will be ongoing. 
      • Installation of plumbing & sprinkler systems ongoing 
      • Ongoing removal of scaffolding throughout sections of the site.

      War Memorial Gym

      • Ongoing roof work on the addition: framing, water proofing, fireproofing
      • Mechanical, electrical, plumbing subcontractors on site.
      • Nov 3: North Lobby of WMG on Golden Gate will serve as an election polling station, separated from construction operations.

      Dining Project

      • Nov 3:  Small concrete pours for hardscape around Pavilion. May sometimes be noisy for immediately adjacent areas.
      • Nov 4: Sawcutting areas from Nov 3 concrete pour beginning 8 am
      • Ongoing installation and connections of furnishing & fixtures 
      • Ongoing installation of millwork, casework, tilework
      • Ongoing installation of light fixtures
      • Ongoing deliveries of materials.

      Lone Mountain Power upgrade  

      • Test pipe inspection completed.  Further work pending scheduling decision by PGE.

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety  Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      10/23/2020 Update:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • Landscaping - clear & grub of east side hill, early November, dates TBD. 
      • Landscaping /planting in courtyards and Paseo
      • Periodic concrete pours to complete LMDrive sidewalks & curbs within the boundaries of the construction site through Nov 6. 
      • Delivery of residential unit appliances. Ongoing periodically
      • Continued work on finishing installations for residential units.
      • Continued work on exterior & courtyards; installing Juliette rails, balustrades, drywall, interior painting, electrical   
      • Deliveries of material to finish interior units will be ongoing. 
      • Installation of plumbing & sprinkler systems ongoing
      • Ongoing removal of scaffolding throughout sections of the site.
      • Power switchover PG&E late October.

      War Memorial Gym

      • Construct openings in west side exterior wall for ventilation system; will involve saw-cutting. By Nov 6, specific dates TBD
      • Ongoing roof work on the addition: framing, water proofing.
      • Iron workers onsite through 10/21 working on substructure, interior walls. 
      • Mechanical, electrical, plumbing subcontractors on site. 
      • Nov 3: North Lobby of WMG on Golden Gate will serve as an election polling station, separated from construction operations. 

      Dining Project

      • Oct 28; Oct 30:  Small concrete pours for hardscape around Pavilion. May sometimes be noisy for immediately adjacent areas. 
      • Continued work on external hardscape around Pavilion.
      • Ongoing installation and connections of fixtures for restrooms and kitchen
      • Ongoing installation of mill work and casework 
      • Ongoing installation of light fixtures
      • Ongoing finishing painting ceilings & walls 
      • Ongoing deliveries of materials.  

      Lone Mountain Power upgrade  

      • Test pipe inspection completed.  Further work pending scheduling decision by PGE.

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      10/16/2020 Updates:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • Oct 16,  Removal of a dead palm tree on LM Drive, within the site. 
      • Oct 22-21:  Lone Mtn Drive: Concrete pour to complete LMDrive within the boundaries of the construction site. A concrete truck will be positioned at the site’s western gate, near the Loyola House driveway entrance. Please be careful in that area. A flagman will be on site. 
      • Oct 21: Delivery of residential unit appliances. Ongoing periodically
      • East Bldg:  Continued work on finishing installations for residential units.
      • West Bldg: Continued work on the exterior; installing Juliette rails, balustrades, drywall, interior painting, electrical
      • Deliveries of material to finish interior units will be ongoing. 
      • Installation of plumbing & sprinkler systems ongoing 
      • The ongoing removal of scaffolding throughout sections of the site.
      • Power switchover PG&E late October.

      War Memorial Gym

      • Saturday, Oct 17:  Work on stairs on the Southside of WMGym will involve some jackhammering. Will continue periodically Mon-Wed 10/19-21.
      • Ongoing roof work on the addition: framing, waterproofing, through Saturday, Oct 24.
      • Ironworkers onsite through 10/21 working on the substructure, interior walls.
      • Ongoing application of fireproofing
      • Ongoing installation of waterproofing
      • Mechanical, electrical, plumbing subcontractors on site. 
      • Nov 3: North Lobby of WMG on Golden Gate will serve as an election polling station, separated from construction operations.

      Dining Project

      • Saturday Oct 17,  Work on external hardscape around Pavilion. Periodic jack hammering may be noisy for immediately adjacent areas. 
      • Oct 19; Oct 21; Oct 26:,  Small concrete pours for hardscape around Pavilion. May sometimes be noisy for immediately adjacent areas
      • Oct 19-20,  Removal of Pavilion scaffolding
      • Ongoing installation and connections of fixtures for restrooms and kitchen
      • Ongoing installation of mill work and casework 
      • Ongoing installation of light fixtures
      • Ongoing installation of acoustic ceiling. 
      • Ongoing finishing painting ceilings & walls 
      • Ongoing deliveries of materials. 

      Lone Mountain Power upgrade 

      • Test pipe inspection completed.  Further work pending scheduling decision by PGE

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      10/9/2020 Updates:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • Oct 9: Concrete pour on that east section of the Drive
      • Oct 10 and 12-14:  Lone Mtn Drive: Work to restore the Drive and walk from Paseo to the west gate of the site. Will involve a demo of concrete by saw cutting and loading of concrete chunks. Saw cutting will take longer but is not as vibratory as jackhammering, a change made in response to neighbor concerns.
      • Oct 12: Building lights will be tested and activated throughout the residential units. 
      • East Bldg:  Continued work on finishing installations for residential units.
      • West Bldg: Continued work on the exterior; installing Juliette rails, balustrades, drywall, interior painting, electrical.
      • Deliveries of materiel to finish interior units will be ongoing. 
      • Installation of plumbing & sprinkler systems ongoing 
      • Ongoing work on campus driveways and curbs, sidewalks, starting with east slope. 
      • Ongoing removal of scaffolding throughout sections of the site.
      • Power switchover /PG&E. Probably early October

      War Memorial Gym

      • Oct 12 :  Small concrete pour, slab on grade.
      • Ongoing skylight installation including framing & flashing on roof top. 
      • Interior framing and drywall
      • Ongoing application of fireproofing
      • Ongoing installation of waterproofing
      • Continue installation of interior pan deck, which will involve deliveries of steel and other materiel
      • Nov 3: North Lobby of WMG on Golden Gate will serve as an election polling station, separated from construction operations. 

      Dining Project

      The Breezeway between Lone Mtn Main & Lone Mountain North is anticipated to open on Oct 13. This is longer than originally planned and we apologize for the inconvenience.

      Pavilion & Interior

      • Oct 12-16 Work on external hardscape around Pavilion. May sometimes be noisy for immediately adjacent areas. 
      • Oct 12-16 Completion of installation of fixtures for restrooms and kitchen
      • Ongoing installation of millwork and casework 
      • Ongoing installation of light fixtures
      • Ongoing installation of acoustic ceiling. 
      • Ongoing finishing painting ceilings & walls 
      • Ongoing deliveries of materials.  

      Lone Mountain Power upgrade

      • Test pipe inspection completed.  Further work pending by PGE expected by Nov 23.

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.


      10/2/2020 Updates:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • Oct 2-3: Lone Mtn Drive: Work to restore the Drive and walk from East Gate to Paseo. Will involve a demo of concrete and loading of concrete chunks, which will include loud with sometimes percussive noise.
      • Oct 9: Concrete pour on that east section of the Drive
      • Oct 14:  Same work on the west portion of the Drive between the Paseo & west gate near Loyola House driveway entrance which will also be loud and with percussive noise.
      • East Bldg:  Continued work on finishing installations for residential units.
      • West Bldg: Continued work on the exterior; installing Juliette rails, balustrades, drywall, interior painting, electrical   
      • Deliveries of materiel to finish interior units will be ongoing. 
      • Installation of plumbing & sprinkler systems ongoing 
      • Ongoing work on campus driveways and curbs, sidewalks, starting with east slope. 
      • Ongoing removal of scaffolding throughout sections of the site.
      • Poer switchover /PG&E. Probably early October

      War Memorial Gym

      • Oct 5:  Small concrete pour, SW corner of building. 
      • Ongoing skylight installation including framing & flashing on the rooftop. 
      • Continuing erection of steel framework
      • Ongoing application of fireproofing
      • Ongoing prep for installation waterproofing
      • Continue installation of interior pan deck, which will involve deliveries of steel and other material

      Dining Project

      • The Breezeway between Lone Mtn Main & Lone Mountain North may remain closed through approximately 
      • Oct 12. This is longer than originally planned and we apologize for the inconvenience
      • Oct 5:  Delivery of millwork to site. About 8 am 

      Pavilion & Interior

      • Ongoing installation of plumbing fixtures for restrooms and kitchen 
      • Ongoing installation of light fixtures
      • Ongoing installation of acoustic ceiling. 
      • Installation of glazing in Pavilion and breezeway. 
      • Ongoing finishing painting of ceilings & walls 
      • Ongoing deliveries of materials.

      Lone Mountain Power upgrade

      • Test pipe inspection completed.  Further work pending schedule to be set by PGE

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      9/25/2020 Updates:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • Sept 28  (est) - install pavers at Paseo, interior courtyards, & adjacent areas.
      • Oct 2-3: Lone Mtn Drive: Work to restore the Drive and walk from East Gate to Paseo. Will involve a demo of concrete and loading of concrete chunks, which will be loud with sometimes percussive noise.
      • Oct 9: Concrete pour on that east section of the Drive
      • Oct 14:  Same work on the west portion of the Drive between the Paseo & west gate near Loyola House driveway entrance. Also loud with sometimes percussive noise.
      • East Bldg:  Continued work on finishing installations for residential units.
      • West Bldg: Continued work on the exterior; installing Juliette rails, balustrades, drywall, interior painting, electrical 
      • Deliveries of material to finish interior units will be ongoing.
      • Installation of plumbing & sprinkler systems ongoing 
      • Ongoing work on campus driveways and curbs, sidewalks, starting with east slope. 
      • Ongoing removal of scaffolding throughout sections of the site.
      • Power switchover /PG&E. Probably early October

      War Memorial Gym

      • Sept 28: small pour, midday, at SW corner of the site.
      • Sept 22-25 (est) - Interior démolition is selected areas, SW corner. There will be some noise associated with this work.
      • Ongoing skylight installation including framing & flashing on the rooftop.
      • Continuing erection of steel framework
      • Ongoing application of fireproofing
      • Continue installation of interior pan deck, which will involve deliveries of steel and another materiel

      Dining Project

      • The Breezeway between Lone Mtn Main & Lone Mountain North may remain closed through approximately Oct 5. 
      • Sept 28 - 30:  Deliveries of kitchen equipment to site. After 8am 
      • Sept 22 - 28 Grind, polish & seal of concrete floors. This work will at times be noisy and could transmit odors.
      • Oct 1:  Delivery of kitchen equipment to site. About 11am 

      Pavilion & Interior:

      • Finish painting on 2nd floor, 265 LMM.  Potential for paint odors in adjacent areas.
      • Ongoing prep for installation of kitchen fixtures
      • Ongoing installation of light fixtures
      • Ongoing installation of acoustic ceiling.
      • Installation of glazing in Pavilion. 
      • Ongoing finishing painting ceilings & walls 
      • Ongoing deliveries of materials.  

      Lone Mountain Power upgrade

      • Oct 1 - Test pipe inspection scheduled by PGE

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      9/18/2020 Updates:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • East Bldg:  Continued work on finishing installations for residential units.
      • West Bldg: Continued work on the exterior; installing Juliette rails & balustrades;  drywall, interior painting, electrical   
      • Deliveries of materiel to finish interior units will be ongoing. 
      • Installation of plumbing & sprinkler systems ongoing 
      • Ongoing work on campus driveways and curbs, sidewalks, starting with east slope. 
      • Power switchover /PG&E. Probably early October
      • Sept 28  (est) - install pavers at Paseo, interior courtyards, & adjacent areas.  

      War Memorial Gym

      • Sept 22-25 (est) - Interior démolition is selected areas, SW corner. There will be some noise associated with this work. 
      • Sept 24 (est) - Small concrete pour, about 2 trucks 
      • Ongoing skylight installation including framing & flashing on the rooftop. 
      • Continuing erection of steel framework
      • Continue installation of interior pan deck, which will involve deliveries of steel and other material

      Dining Project

      • The Breezeway between Lone Mtn Main & Lone Mountain North will remain closed through approximately Oct 1.
      • Sept 25:  Finish painting on the 2nd floor, 265 LMM.  Potential for paint odors in adjacent areas.
      • Sept 28 - 30:  Deliveries of kitchen equipment to the site. 8am
      • Sept 22 - 28 Grind, polish & seal of concrete floors. This work will at times be noisy and could transmit odors.
      • Oct 1:  Delivery of kitchen equipment to site. 11am 

      Pavilion & Interior:

      • Grading, gravel, and Ongoing prep for installation of kitchen fixtures
      • Ongoing installation of light fixtures
      • Ongoing installation of acoustic ceiling. 
      • Installation of glazing in Pavilion. 
      • Finishing painting ceilings & walls 
      • Ongoing deliveries of materials.

      Lone Mountain Power upgrade 

      • Oct 1 - Test pipe inspection by PGE 

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      9/15/2020 Update:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • East Bldg: Exterior skin complete. Continued work on finishing installations for residential units.
      • West Bldg: Continued work on exterior lathe & plaster; drywall, interior painting, electrical
      • Continued work on interior courtyards - finish coats, planter walls, pavers,
      • Deliveries of materiel to finish interior units will be ongoing.
      • Installation of plumbing & sprinkler systems ongoing
      • Ongoing work on campus driveways and curbs, sidewalks, starting with east slope.
      • Sept 21 (est) - power switchover /PG&E. Details TBD.
      • Sept 28 (est) - install pavers at Paseo & adjacent areas.

      War Memorial Gym

      • Ongoing skylight installation including framing & flashing on roof top.
      • Continuing erection of steel framework
      • Continue installation of interior pan deck, which will involve deliveries of steel and other materiel

      Dining Project

      • The Breezeway between Lone Mtn Main & Lone Mountain North will remain closed through approximately Oct 1.
      • Sept 25 (est): Painting on 2nd floor, 265 LMM

      Pavilion & Interior:

      • Ongoing installation of kitchen fixtures
      • Ongoing layout & installation of light fixtures
      • Ongoing installation of acoustic ceiling.
      • Painting ceilings & walls
      • Ongoing deliveries of materials.
      • Grind, polish & seal of concrete floors. This work will at times be noisy and transmit odors.

      Lone Mountain Power upgrade

      • Sept 10 - Test pipe inspection postponed. TBD
      • PG&E will schedule their remaining work, likely in September

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      9/08/2020 Update:

      To allow for painting and ceiling installation, the pedestrian pathway along the breezeway in Lone Mountain will be closed to pedestrians starting the morning of Tuesday, 9/8 an will be closed through Tuesday, 9/15. The breezeway will be open again to pedestrians starting on the following Wednesday morning (9/16).


      9/03/2020 Update:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice. 

      Lone Mountain Residence Hall

      • East Bldg:  Continuing removal of scaffolding, application of masonry veneer, exterior painting 
      • West Bldg: Application of exterior lathe & plaster continue, drywall, interior painting, electrical
      • Work on interior courtyards - finish coats 
      • Deliveries of materiel to finish interior units will be ongoing. 
      • Installation of plumbing & sprinkler systems ongoing 
      • Ongoing work on campus driveways and curbs, sidewalks, starting with east slope. 
      • Sept 1: Shotcrete retaining walls on-campus drive within the site. 8am start. Some noise.
      • Labor Day Weekend: Most trades are off on Friday, Sept 4 so light activity. No work onsite Sept 7.
      • Sept 21  (est) - power switchover /PG&E. Details TBD. 

      War Memorial Gym

      • Ongoing skylight installation including framing & flashing on rooftop. 
      • Continuing erection of steel framework
      • Continue installation of interior pan deck, which will involve deliveries of steel and other materials
      • Labor Day Weekend: Most trades are off on Friday, Sept 4 and Sept 7. Light activity on site.

      Dining Project 

      Pavilion:

      • Ongoing installation of kitchen fixtures
      • Ongoing layout & installation of light fixtures
      • Painters prep of ceilings & walls 
      • Ongoing deliveries of materials.

      Interior 

      • Ongoing painting and prep.
      • Ongoing installation of hoods & kitchen fixtures
      • Sept 7 Anticipated grind, polish & seal of concrete floor in interior spaces. The breezeway will be closed, specific dates to follow.
      • Labor Day Weekend: Most trades are off on Friday, Sept 4 and Sept 7. Light activity on site. 

      Lone Mountain Power upgrade  

      • Sept 10 - Test pipe inspection
      • PG&E will schedule their remaining work, likely in September 

      Covid-19 

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      8/28/2020 Update:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice. 

      Lone Mountain Residence Hall

      • East Bldg:  Continuing removal of scaffolding, application of masonry veneer, exterior painting 
      • West Bldg: Application of exterior lathe & plaster continue, drywall, interior painting, electrical  
      • Work on interior courtyards - finish coats 
      • Deliveries of materiel to finish interior units will be ongoing. 
      • Installation of plumbing & sprinkler systems ongoing 
      • Ongoing work on campus driveways and curbs, sidewalks, starting with east slope. 
      • Sept 1: Shotcrete retaining walls on-campus drive within the site. 8am start. Some noise.
      • Labor Day Weekend: Most trades are off on Friday, Sept 4 so light activity. No work onsite Sept 7.
      • Sept 21  (est) - power switchover /PG&E. Details TBD.

      War Memorial Gym

      • Sept 2: Skylight installation. Preparations include framing & flashing on the rooftop.
      • Continuing erection of steel framework
      • Continue installation of interior pan deck starting, which will involve deliveries of steel and other materiel
      • Labor Day Weekend: Most trades are off on Friday, Sept 4 and Sept 7. Light activity on site.

      Dining Project 

      Pavilion:

      • Ongoing installation of kitchen fixtures
      • Ongoing layout & installation of light fixtures
      • Painters start prep of ceilings & walls 
      • Ongoing deliveries of materials.

      Interior 

      • Aug 31: painting starts inside.
      • Ongoing installation of hoods & kitchen fixtures
      • Sept 2 - Freezers & coolers install complete
      • Sept 7 Anticipated grind, polish & seal of concrete floor in interior spaces. The breezeway will be closed, specific dates to follow.
      • Labor Day Weekend: Most trades are off on Friday, Sept 4 and Sept 7. Light activity on site. 

      Lone Mountain Power upgrade

      • Sept 10 - Test pipe installations
      • PG&E will schedule their remaining work, likely in September.

      Covid-19 

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.


      8/21/2020 Update:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • East Bldg:  Continuing removal of scaffolding, exterior painting 
      • Application of exterior lathe & plaster continues, West Bldg. 
      • Work on interior courtyards - finish coats
      • Work on east and west building interiors is ongoing, including painting, installation of sheetrock, cabinetry, etc. 
      • Deliveries of sheetrock and other materials to finish interior units will be ongoing. 
      • Installation of plumbing & sprinkler systems ongoing 
      • July 27 - Aug 25  work on driveways and campus drive sidewalks, starting with east
      • slope. 
      • Mid-Sept  (est) - power switchover /PG&E. Details TBD. 

      War Memorial Gym

      • Friday, Aug 28 Concrete pour.  12-14 trucks, 2 to stage at the pump, and cycle through. Staging on Golden Gate only if necessary.
      • Continuing erection of steel framework
      • Continue installation of interior pan deck starting, which will involve deliveries of steel and other materials

      Dining Project 

      Pavilion:

      • Beginning installation of the hood, pizza oven, fireplace, and fixtures
      • Beginning layout & installation of light fixtures
      • Painters start prep of ceilings & walls, painting next week
      • Ongoing deliveries of materials.  

      Interior 

      • Beginning installation of hoods & kitchen fixtures
      • Ongoing: framing interior walls; continued installation of overhead ductwork, plumbing, electrical, light fixtures, hood systems
      • Painters start prep of ceilings & walls, painting next week
      • Sept 7 Anticipated grind, polish & seal of concrete floor in interior spaces. The breezeway will be closed, specific dates to follow. 

      Lone Mountain Power upgrade  

      • Completion of minor civil improvements near Pacific Wing. Once complete and inspected, PG&E will schedule their remaining work, likely in September 

      Covid-19 

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.


      8/14/2020 Update:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice. 

      Lone Mountain Residence Hall

      • Continuing removal of scaffolding, East Bldg
      • Exterior painting of East Building 
      • Application of exterior lathe & plaster continues, West Bldg.
      • Work on interior courtyards - finish coats
      • Work on east and west building interiors is ongoing, including painting, installation of sheetrock, cabinetry, etc. 
      • Deliveries of sheetrock and other materials to finish interior units will be ongoing. 
      • Installation of plumbing & sprinkler systems ongoing 
      • July 27 - Aug 21 (estimate)  work on driveways and campus drive sidewalks, starting with east slope.
      • Mid-Sept  (est) - power switchover /PG&E. Details TBD. 

      War Memorial Gym

      • Continuing erection of steel framework
      • Continue installation of interior pan deck starting, which will involve deliveries of steel and other materials
      • Dismantle shoring towers.

      Dining Project 

      Pavilion:

      • Grading outside area east of Pavilion, between Pavilion & Loyola House courtyard wall, in preparation for landscaping
      • Continued sheetrocking interior spaces
      • Ongoing deliveries of framing and sheetrock materials.

      Interior

      • Ongoing: framing interior walls; continued installation of overhead ductwork, plumbing, electrical, light fixtures, hood systems
      • Continued sheetrocking interior spaces  
      • Anticipated delivery of pizza oven & walk-in coolers 8/20-21
      • Anticipated grind, polish & seal of concrete floor in interior spaces week of 8/24. The breezeway will be closed, specific dates to follow.

      Lone Mountain Power upgrade

      • Finish concrete pad at transformer next to Pacific Wing, Aug 21.
      • Work on the corner ramps of the Lone Mtn Drive entry should be completed by 8/19.
      • Once the civil is complete and inspected, PG&E will schedule their remaining work, likely in September 

      Covid-19 

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance. ReplyReply allForward


      8/03/2020 Update:

      All dates below are best estimates, subject to impacts of weather and other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • August 3 - 7 (estimate) removal of plywood fence on portions of east and south construction site boundary
      • Exterior painting of East Building
      • Application of exterior lathe & plaster continues, West Bldg.
      • Work on interior courtyards - caulking, rails, finish coats
      • Work on east and west building interiors is ongoing, including painting, installation of sheet rock, cabinetry, etc.
      • Deliveries of sheet rock and other materiel to finish interior units will be ongoing.
      • Installation of plumbing & sprinkler systems ongoing
      • July 27 - Aug 21 (estimate) work on driveways and campus drive sidewalks, starting with east slope.
      • Mid-Sept (est) - power switchover /PG&E. Details TBD.

      War Memorial Gym

      • Continuing work on openings for windows & skylights some of which will be noisy, likely through August 7
      • Continuing erection of steel framework
      • Continue installation of interior pan deck starting, which will involve deliveries of steel and other materiel
      • Upcoming: concrete pour for Club deck, date TBD

      Dining Project

      Pavilion:

      • Grading outside area east of Pavilion, between Pavilion & Loyola House courtyard wall, in preparation for landscaping
      • Installation of scaffolding
      • Continued sheet rocking interior spaces, week of Aug 3
      • Ongoing deliveries of framing and sheet rock materials.

      Interior

      • On going: framing interior walls; continued installation of overhead duct work, plumbing, electrical, light fixtures, hood systems
      • Sheet rocking interior spaces week of Aug 3
      • Anticipated delivery of walk-in coolers 8/21

      Lone Mountain Power upgrade

      • Currently on pause due to PG&E scheduling.
      • Contractors will start work on the NW corner of the Lone Mtn Drive entry ramp Aug 4 - 8/7. The restoration work on the SW corner will start 8/10 and be completed by 8/14. Once the civil is complete and inspected, the civil inspector will “clear the job for construction” which will allow PG&E to schedule their remaining work, likely in September.

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.


      7/29/2020 Update:

      All dates below are best estimates, subject to impacts of weather and other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • August 3 - 7 (estimate) removal of plywood fence on portions of east and south construction site boundary
      • Construction schedule: anticipated project completion is estimated to be February 2021.
      • Application of exterior lathe & plaster continues.
      • Work on interior courtyards
      • caulking, rails, finish coats
      • Work on east and west building interiors is ongoing, including painting, installation of sheet rock, cabinetry, etc.
      • Deliveries of sheet rock and other materiel to finish interior units will be ongoing.
      • Installation of plumbing & sprinkler systems ongoing
      • July 27 - Aug 21 (estimate) work on driveways and campus drive sidewalks, starting with east slope.
      • Mid-Sept (est) - power switchover /PG&E. Details TBD. War Memorial Gym
      • Continuing demo’ing of window & skylight openings which involves saw-cutting and will be noisy, likely through August 7
      • Continuing erection of steel framework - Continue installation of interior pan deck starting, which will involve deliveries of steel and other material

      Dining Project

      The breezeway between Lone Mtn North and Lone Mtn Main will be temporarily closed Tuesday (7/28) thru Wednesday (7/29) to allow for the last concrete pour and saw cut. The breezeway will be reopened Thursday (7/30) morning once protection is down.

      Pavilion:

      • Final indoor concrete pour July 29, saw cutting July 30 which will be noisy to adjacent offices.
      • Framing.
      • Grading outside area east of Pavilion, between Pavilion & Loyola House courtyard wall, in preparation for landscaping
      • Installation of scaffolding
      • Sheet rocking interior spaces July 29 - Monday Aug 3
      • Ongoing deliveries of framing and sheetrock materials.

      Interior

      • On going: framing interior walls; continued installation of overhead ductwork, plumbing, electrical, light fixtures, hood systems
      • Sheet rocking interior spaces July 29 - Monday, Aug 3

      Lone Mountain Power upgrade

      • Currently on pause due to PG&E scheduling.

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.


      7/10/2020 Update:

      All dates below are best estimates, subject to impacts of weather and other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • July 9-14: Stucco work at West Bldg, west, and north elevations. Finishing coat will be applied after about a week of drying.
      • July 27 -31 (estimate) temporary removal of plywood fence on portions of east and south construction site boundary
      • Construction schedule: anticipated project completion is estimated to be February 2021.
      • Application of exterior lathe & plaster continues.
      • Work on interior courtyards
      • caulking, rails, finish coats
      • Work on east and west building interiors is ongoing, including painting, installation of sheetrock, cabinetry, etc.
      • Deliveries of the sheetrock and another materiel to finish interior units will be ongoing.
      • Installation of plumbing & sprinkler systems ongoing
      • July 27 - Aug 21 (estimate) work on driveways and campus drive sidewalks, starting with east slope.
      • Mid-Sept (est) - power switchover /PG&E. Details TBD.

      War Memorial Gym

      • July 13- 20: create openings for windows and skylights in sheer walls and ceiling. Work will involve saw-cutting and other noisy activities.
      • July 14 - large rebar delivery. One truck, delivery to the yard.
      • July 16 (estimate) small concrete pour.
      • Continue installation of interior pan deck starting, which will involve deliveries of steel and other material.

      Dining Project

      Pavilion:

      • Roofing of Pavilion continues, including Saturday, July 11: work will start after 8 am. No tar.
      • Framing; framing activities will involve cutting metal studs in the LM backlot/Cahill staging area. Sawcutting may be noisy to adjacent areas within Lone Mountain, Lone Mtn Main, & Pacific
      • Installation of windows nearing completion.
      • Grading outside area east of Pavilion, between Pavilion & Loyola House courtyard wall, in preparation for landscaping
      • Installation of scaffolding
      • Ongoing deliveries of framing materials.
      • Painting activities will also continue. Adjacent offices in LMMain may notice paint odors.

      Interior

      • Pedestrian bridge & breezeway between Lone Mountain North and Lone Mountain Main will be closed Monday 6/29 through Tuesday morning July 7.
      • Ongoing: framing interior walls; continued installation of overhead ductwork, plumbing, electrical, light fixtures, hood systems

      Lone Mountain Power upgrade

      • Currently on pause due to PG&E scheduling.

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.


      7/02/2020 Update:

      All dates below are best estimates, subject to impacts of weather and other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • Construction schedule update: anticipated completion is estimated to be February 2021.
      • The application of exterior lathe & plaster continues.
      • Work on interior courtyards - caulking, rails, finish coats
      • Work on east and west building interiors is ongoing, including painting, installation of sheetrock, cabinetry, etc.
      • Deliveries of the sheetrock and other materials to finish interior units will be ongoing.
      • Installation of plumbing & sprinkler systems ongoing
      • July 27 - Aug 21 (estimate) work on driveways and campus drive sidewalks, starting with east slope.
      • Mid-Sept (est) - power switchover /PG&E. Details TBD.

      War Memorial Gym

      • Stripping of forms and off-loading of related materiel.
      • July 7-17 installation of steel framing, will involve moderate noise at times.
      • Installation of interior pan deck starting, which will involve deliveries of steel and other materials.

      Dining Project

      Interior

      • Pedestrian bridge & breezeway between Lone Mountain North and Lone Mountain Main will be closed Monday 6/29 through Tuesday morning July 7
      • Ongoing: framing interior walls; continued installation of overhead ductwork, plumbing, electrical, light fixtures, hood systems

      Pavilion:

      • Framing on roof & interior; framing activities will involve cutting metal studs in the LM backlot/Cahill staging area. Sawcutting may be noisy to adjacent areas within Lone Mountain, Lone Mtn Main, & Pacific
      • Installation of windows nearing completion.
      • Grading outside area east of Pavilion, between Pavilion & Loyola House courtyard wall, in preparation for landscaping
      • Installation of scaffolding
      • Ongoing deliveries of framing materials.
      • Painting activities will also continue. Adjacent offices in LMMain may notice paint odors.

      Lone Mountain Power upgrade

      • Currently on pause due to PG&E scheduling.

      Covid-19

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29,2020.

      USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.


      6/26/2020 Update:

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29,2020.

      USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      • Construction schedule update: anticipated completion is estimated to be February 2021.
      • The application of exterior lathe & plaster continues.
      • Work on interior courtyards - caulking, rails, finish coats  
      • Work on east and west building interiors is ongoing, including painting, installation of sheetrock, cabinetry, etc.
      • Deliveries of the sheetrock and other materials to finish interior units will be ongoing. •
      • Installation of plumbing & sprinkler systems ongoing
      • August 11 - Sept 8 (est) work on driveways and campus drive sidewalks, starting with east slope.

      War Memorial Gym

      • On-going work completing below and above-grade walls, removing shoring towers, interior structural steel, and creating formwork
      • Removal of shoring towers almost complete; removal if shoring beams starts 6/15
      • Installation of interior pan deck starting, which will involve deliveries of steel and other materials.

      Dining Project

      Interior

      • Concrete pour originally scheduled for June 11/12 is scheduled for Monday 6/29.
      • Pedestrian bridge & breezeway between Lone Mountain North and Lone Mountain Main will be closed Monday 6/29 through Tuesday morning July 7.
      • Ongoing: framing interior walls; continued installation of overhead ductwork, plumbing, electrical, hood systems Pavilion:
      • Framing on roof & interior; framing activities will involve cutting metal studs in the LM backlot/Cahill staging area. Sawcutting may be noisy to adjacent areas within Lone Mountain, Lone Mtn Main, & Pacific
      • Installation of windows to begin.
      • Grading outside area east of Pavilion, between Pavilion & Loyola House courtyard wall, in preparation for landscaping
      • Installation and waterproofing windows.
      • Installation of scaffolding
      • Ongoing deliveries of framing materials.
      • Painting activities will also continue. Adjacent offices in LMMain may notice paint odors.

      Lone Mountain Power upgrade

      • Completion of this work contingent upon PGE scheduling

      6/12/2020 Update:

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29,2020.

      USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      The application of exterior lathe & plaster continues.

      Work on interior courtyards - caulking, rails, finish coats

      Work on east and west building interiors is ongoing, including painting, installation of sheetrock, cabinetry, etc.

      Deliveries of the sheetrock and other materials to finish interior units will be ongoing.

      Installation of plumbing & sprinkler systems ongoing

      August 11 - Sept 8 (est) work on driveways and campus drive sidewalks, starting with east slope.

      War Memorial Gym

      • On-going work completing below and above-grade walls, removing shoring towers, interior structural steel, and creating formwork
      • Removal of shoring towers almost complete; removal if shoring beams starts 6/15
      • Installation of interior pan deck starting, which will involve deliveries of steel and other materials.

      Dining Project

      Interior

      Concrete pour originally scheduled for June 11/12 has been postponed.

      Pedestrian bridge & breezeway between Lone Mountain North and Lone Mountain Main will remain open until the pour date is finalized.

      Ongoing: framing interior walls; continued installation of overhead ductwork, plumbing, electrical, hood systems

      Pavilion:

      Framing on roof & interior; framing activities will involve cutting metal studs in the LM backlot/Cahill staging area. Sawcutting may be noisy to adjacent areas within Lone Mountain, Lone Mtn

      Main, & Pacific Wing.

      Grading outside area east of Pavilion, between Pavilion & Loyola House courtyard wall, in preparation for landscaping

      Installation and waterproofing windows.

      Installation of scaffolding

      Ongoing deliveries of framing materials.

      Painting activities will also continue. Adjacent offices in LMMain may notice paint odors.

      Lone Mountain Power upgrade

      Tuesday, June 23-26 - marking, coring, installation of a manhole at NW corner/USF driveway entrance of Temescal & Turk.

      Completion of this work contingent upon PGE scheduling


      6/10/2020 Update:

      Please note this change: The closure of the breezeway between LMNorth & LM Main has been changed from June 10-15. Instead, it will be closed the June 18th-22nd at noon


      6/05/2020 Update:

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29,2020.

      USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      Application of exterior lathe & plaster continues.

      Work on east and west building interiors is ongoing, including painting, installation of sheet rock, cabinetry, etc.

      Deliveries of sheet rock and other materiel to finish interior units will be ongoing.

      Installation of plumbing & sprinkler systems ongoing

      August 11 - Sept 8 (est) work on driveways and campus drive sidewalks, starting with east slope.

      War Memorial Gym

      • On-going work completing below and above-grade walls, removing shoring towers, interior structural steel, and creating formwork - June 9 - Second concrete pour for vertical wall - June 11 - concrete pour, if necessary

      Dining Project

      Interior

      Pedestrian breezeway between Lone Mountain North and Lone Mountain Main is open. It will be temporarily closed in the evening Wed 6/10 through June 15. A walkway protected by temporary scaffolding will be installed to allow for pedestrian traffic.

      • June 11 - third concrete pour to complete the topping slab
      • June 12 - Saw cut last concrete section.
      • Ongoing - Framing interior walls; installation of overhead ductwork; plumbing installation

      Pavilion:

      May 26-June 10 - Framing of the Pavilion. The process will involve cutting metal studs in the LM backlot/Cahill staging area. Sawcutting may be noisy to adjacent areas within Lone Mountain, Lone Mtn Main, & Pacific Wing.

      Begin grading of the outside area east of Pavilion, between Pavilion & Loyola House courtyard wall.

      Installation of scaffolding

      Ongoing deliveries of framing materials.

      Painting activities will also continue. Adjacent offices in LMMain may notice paint odors.

      Lone Mountain Power upgrades - Work to install upgraded power to Lone Mtn Main is underway. Trenching and backfill completed. Completion of this work contingent upon PGE scheduling

      Tree Work

      Due to unsafe and/or other hazardous conditions, 3 campus trees have been removed The trunk of the pine on the north slope of Lone Mtn across from Loyola Village remains and will be removed Saturday, June 6. Work is to start after 9am.


      5/29/2020 Update:

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29,2020.

      USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      The installation of windows continues.

      The application of exterior lathe & plaster continues.

      Work on east and west building interiors is ongoing, including painting, installation of sheetrock, cabinetry, etc.

      Deliveries of sheetrock and other materiel to finish interior units will be ongoing.

      War Memorial Gym

      On-going work completing below and above-grade walls, removing shoring towers, interior structural steel, and creating formwork - June 4 Concrete pour for walls (estimated date)

      Dining Project

      Interior

      Closure of pedestrian access between Lone Mountain North and Lone Mountain Main through approximately June 5. A walkway protected by temporary scaffolding will be installed to allow for pedestrian traffic.

      The first two pours of the topping slab have been completed. The 3rd pour date is to be determined. At that time, the interior passageway will again be temporarily closed to allow for the 3rd pour. - 3rd pour and saw cut TBD. Sawcutting will be noisy to adjacent areas within Lone Mountain.

      Ongoing: Framing interior walls; installation of overhead ductwork.

      Pavilion:

      • May 26-June10 Framing of the Pavilion. The process will involve cutting metal studs in the LM backlot/Cahill staging area. Sawcutting may be noisy to adjacent areas within Lone Mountain, Lone Mtn Main, & Pacific Wing.

      Ongoing deliveries of framing materials.

      Painting activities will also continue. Adjacent offices in LMMain may notice paint odors.

      Lone Mountain Power upgrades - Work to install upgraded power to Lone Mtn Main is underway.

      Trenching and backfill completed. Completion of this work contingent upon PGE scheduling

      Tree Work

      Due to unsafe and/or other hazardous conditions, 3 campus trees are scheduled for removal on June 1-3.

      The first tree is at the west loop of Lone Mtn Drive; the second is a small group of eucalyptus on the north slope of Lone Mtn across from Loyola Village/downhill from Loyola House, and the third is a pine on the north slope of Lone Mtn across from Loyola Village.


      5/22/2020 Update:

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29,2020.

      USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      Work to complete roofing, application of exterior skin, installation of windows & Tyvek continues.

      The application of exterior plaster continues.

      Work on east and west building interiors is ongoing, including painting, installation of sheetrock throughout.

      Deliveries of sheetrock and other materiel to finish interior units will be ongoing.

      • May 23-25 No work at the site

      War Memorial Gym

      - On-going work completing below and above-grade walls, removing shoring towers, and creating formwork

      • May 22 & 25 - No work at the site
      • May 28 - Concrete pour for walls
      • June 4 - Concrete pour for walls

      Dining Project

      Interior

      Closure of pedestrian access between Lone Mountain North and Lone Mountain Main through May 27. The bridge between Lone Mtn North and Lone Mtn Main and the covered passageway within the Dining site is closed to allow for the application of topping slab in interior space in Lone Mountain Main. Installation of the interior framing.

      The application of the topping slab will involve three concrete pours and sawcutting control joints into the new slab. Sawcutting will be noisy to adjacent areas within Lone Mountain:

      • May 22 2nd pour, interior - May 23 Sawcut 2nd pour area interior: set up 8am. Sawcut 9am - 3rd pour TBD

      Pavilion:

      • May 26-June10 - Metal stud framing of the Pavilion.

      The process will involve sawcutting metal studs in the LM backlot/Cahill staging area. Sawcutting may be noisy to adjacent areas within Lone Mountain, Lone Mtn Main, & Pacific Wing. Includes deliveries of framing materials.

      Painting activities will also continue. Adjacent offices in LMMain may notice paint odors. - May 25 - No work at the site

      Lone Mountain Power upgrades - Work to install upgraded power to Lone Mtn Main is underway. Trenching and backfill completed

      • May 26-29 - Restoration of walks & drive
      • May 22-25 - No work at the site

      Tree Work

      Due to unsafe and/or other hazardous conditions, 3 campus trees are scheduled for removal on June 1-3.

      The first tree is at the west loop of Lone Mtn Drive; the second is a small group of eucalyptus on the north slope of Lone Mtn across from Loyola Village/downhill from Loyola House, and the third is pine on the north slope of Lone Mtn across from Loyola Village.


      5/15/2020 Update:

      Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29,2020.

      USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      Work to complete roofing, application of exterior skin, installation of windows & Tyvek continues.

      The application of exterior plaster on the east building continues. Work on east and west building interiors is ongoing, including painting, installation of sheetrock throughout.

      Deliveries of the sheetrock and another materiel to finish interior units will be ongoing.

      War Memorial Gym

      May 18 - Begin placement of form panels for above ground structure

      May 20 (estimate) - 1st concrete pours for above-ground walls.

      Lone Mountain Dining Project

      Closure of pedestrian access between Lone Mountain North and Lone Mountain Main has been extended to May 27. The bridge between Lone Mtn North and Lone Mtn Main and the covered passageway within the Dining site is closed to allow for the application of topping slab in interior space in Lone Mountain Main. The application of the topping slab will involve three concrete pours and saw cutting control joints into the new slab. Sawcutting will be noisy to adjacent areas within

      Lone Mountain:

      May 20 - 1st pour

      May 21 - Sawcut 1st pour

      May 22 - 2nd pour

      May 23 - Sawcut 2nd pour area

      3rd pour TBD

      Pavilion:

      May 15 - Completing concrete pour today for Pavilion decking.

      May 16 - Saw cut for control joints of the Pavilion slab.

      • 9 am workers set up.
      • 10 am saw cutting starts. Sawcutting may be noisy to adjacent areas within Lone Mountain,

      Lone Mtn Main, Rossi, and Loyola House.

      May 18-23 - Complete roof decking.

      May 21 - Metal framing of Pavilion. Includes deliveries of framing materials.

      May 21 - Painting activities will also continue. Adjacent offices in LMMain may notice paint odors.

      Lone Mountain Power upgrade

      Work to install upgraded power to Lone Mtn Main is underway.

      May 15 - Installation of the electrical vault on Turk.

      May 18-21 - Trenching and backfilling to vault


      5/8/2020 Update:

      Construction at USF’s project sites ramped up beginning Monday 5/4/20 in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020, which allows all construction to proceed throughout the City beginning May 4, 2020,

      USF continues to require all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers maintain social distance.

      All dates are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

      Work to complete roofing, application of exterior skin, installation of windows & Tyvek, and plumbing and electrical work that pierces roofing and exterior walls continues. The application of exterior plaster on the east building is beginning.

      Work on east and west building interiors is ongoing, including installation of sheetrock in interior units. Deliveries of the sheetrock and another materiel to finish interior units will be ongoing.

      War Memorial Gym

      The replacement of temporary shoring of the west facade continues with installation steel framing.

      May 8- Concrete pour of 1st portion of the sheer wall. 2 -3 trucks.

      May 12 - Concrete pour of 2nd portion of the sheer wall. 2 -3 trucks.

      Lone Mountain Dining Project

      May 6 - 20: There will be no pedestrian access between Lone Mountain North and Lone Mountain Main between May 6 and May 20. The bridge between Lone Mtn North and Lone Mtn Main and the covered passageway within the Dining site will be closed for two weeks to allow for the application of topping slab in interior space in Lone Mountain Main.

      May 1 - May 19 (estimate): Lone Mountain Power upgrade - Work to install upgraded power to Lone Mtn Main is underway.

      Trenching continues along the west side of Pacific Wing down to Turk Blvd. The portion crossing the Lone Mtn Driveway has been temporarily covered. Please proceed with caution when in that area.


      5/1/2020 Update:

      Construction at USF’s project sites will ramp up beginning Monday in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020, which allows all construction to proceed throughout the City beginning May 4, 2020,

      USF continues to require all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers maintain social distance.

      Lone Mountain Residence Hall

      Work to complete roofing, application of exterior skin, installation of windows & Tyvek, and plumbing and electrical work that pierces roofing and exterior walls continue. Work on east and west building interiors will restart on Monday, May 4.

      War Memorial Gym

      The replacement of temporary shoring of the west facade continues with installation steel framing.

      May 11- estimated date for the concrete pour of the sheer wall.

      Lone Mountain Dining Project

      May 4 - Demo of topping slab in the southern section of interior space. This activity will involve jackhammering and will be noisy and disruptive to adjacent areas in Lone Mountain Main.

      May 6 - 20: There will be no pedestrian access between Lone Mountain North and Lone Mountain Main between May 6 and May 20. The bridge between Lone Mtn North and Lone Mtn Main and the covered passageway within the Dining site will be closed for two weeks.

      May 1 - May 8: Lone Mountain Power upgrade - Work to install upgraded power to Lone Mtn Main is underway.

      A utility trench will extend from the west side of Pacific Wing down to Turk Blvd. A section of the trench will cross the Lone Mtn Driveway at the top of the western loop. The Contractor will trench half the driveway, plate the open excavation, and then flip to the other side and continue trenching. This will allow for continuous traffic flow. Please proceed with caution when in that area.


      4/17/2020 Update:

      Construction activity at campus projects is curtailed except for activity that will ensure that each site is safe, habitable, and watertight as permitted by the Health Safety Officer of the City & County of San Francisco.

      USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020. Superintendents at each site are tasked with making sure workers maintain social distance.

      Lone Mountain Residence Hall

      Work to ensure that the buildings are watertight continues, including roofing, application of exterior skin, installation of windows & tyvek, and plumbing and electrical work that pierces roofing and exterior walls.

      War Memorial Gym

      Work to make the site safe and secure includes removing temporary shoring of the west facade by erection of iron work, estimated to begin April 21.

      Lone Mountain Dining Project

      A 100’ x 16 ft concrete temporarily supported wall is required to be secured. Steelworkers on-site will fabricate a permanent framework to secure that structure.


      4/3/2020 Update:

      Construction activity on campus projects has been curtailed except for activity that will ensure that each site is safe, habitable, and watertight as permitted by the Health Safety Officer of the City & County of San Francisco.


      3/27/2020 Update:

      Several campus construction projects, as essential infrastructure, are exempt from the SF DPH Shelter In Place Order.

      Construction is continuing although some schedules and work volume have been affected.

      All dates below are best estimates and may change without notice.

      Lone Mountain Residence Hall

      ** Thursday April 2: Tower Crane is scheduled to be deconstructed and taken down. **

      On-going:

      Construction fans will run 24/7 to dry interior portions of both building. The fans are powered by a generator which will also run throughout this period. The activity will continue through March.

      East & West Bldgs: work on exterior skin.

      Preparations are underway to start stucco at East Bldg.

      Framing on the West Buildings continues.

      Roofing continues on the East and West Bldgs.

      Periodic deliveries of framing, roof trusses, lumber, windows.

      Installation of storm drains and other site work.

      Installation of windows nearing completion.

      Dining Hall Project at Lone Mountain Main

      ** March 30 - April 12 ** The pedestrian bridge between Lone Mountain Main and Lone Mountain North will be closed.

      Exterior Work:

      April 1 - 3: Specific date TBD. Concrete pour of remaining two sections of south Pavilion wall. Equipment involves pumps and related equipment which may involve noise affecting adjacent areas. Removal of generator in LMMain west lot. This activity will be noisy and may affect adjacent areas including LM Chapel and the Pacific Wing.

      Interior work:

      Mar 30 - Apr 3: Chipping/breaking up concrete slab on grade. This activity will be noisy and may affect adjacent areas including LM Chapel and LMM lower levels.

      March 30 - April 12: demolition and installation of new concrete slab in passageway between LMNorth and LMMain. The pedestrian bridge between Lone Mountain Main and Lone Mountain North will be closed during this period. The north door to Lone Mountain North will be available for access to LMNorth. This activity will be noisy and may affect adjacent areas including LM Chapel and LMM lower levels.

      LMM lower levels.Work on plumbing systems on main and in Public Safety may continue periodically: Noise may affect adjacent areas including LM Chapel and LMM lower levels.

      Periodic deliveries of materiel: steel, rebar, concrete are on-going.

      War Memorial Gym/Sobrato Center

      Continuing work on subgrade slab: plumbing final connections, slab on grade waterproofing.

      Continuing work on the interior.

      Continuing exterior work on drain lines, waterproofing, and plumbing.


      3/22/2020 Update:

      USF, in accordance with the San Francisco Department of Public Health Order and the California State Public Health Order, is deemed an essential business and remains in operation. Management is developing measures to limit access to the campus and university buildings. Essential functions will continue to operate including Emergency Services, Educational Operations, Food Services, Residences, Essential Services Providers, Professional Services, Minimum Basic Operations, and Research.

      These measures are subject to change if additional restrictions are enacted by the City and County of San Francisco, or pending any additional state or federal restrictions.

      Additionally, the Public Health Order exempts essential infrastructure which includes housing construction and utilities. Several campus construction projects fall within those categories including the Lone Mountain Residence Hall project. Work will continue at certain sites on campus.

      3/17/2020 Update:

      In accordance to Mayor London Breed’s Shelter in Place Order issued earlier today, the USF Residence Hall, USF Dining and USF Gym projects will cease operations for 3 weeks. Crews will be onsite today and periodically thereafter to ensure the sites are safe and secure along with security oversight 24/7.

      The Lone Mountain water shut-off scheduled for March 18, 9am -1pm will proceed as planned.


      3/16/2020 Update:

      The water shut off for Lone Mountain will be Wed 3/18 9am-1p and will affect Rossi Wing, LMMain, Loyola House, and portions of Pacific Wing.


      3/13/2020 Update:

      Lone Mountain Residence Hall Project

      Lone Mountain Water Shut Off: Estimated date Wed 3/18 8am-Noon. Will affect Rossi Wing, LMMain, Loyola House, and portions of Pacific Wing. The date will be confirmed by email to the Lone Mtn community.

      On-going:

      Roofing continues on the East and West Bldgs.

      Stocking roof tile will continue on Saturday 3/14

      Construction fans will run 24/7 to dry interior portions of both buildings. The fans are powered by a generator which will also run throughout this period. The activity will continue through March.

      East & West Bldgs: work on exterior skin

      Framing on the East Building and West Buildings continues.

      Periodic deliveries of framing, roof trusses, lumber, windows.

      Installation of windows continues.

      Installation of storm drains and other site work.

      Upcoming: Tower crane removal anticipated April 3

      Dining Hall Project at Lone Mountain Main

      Exterior Work:

      March 18 -20 : Concrete pour of 2nd two sections of south Pavilion wall. Equipment involves pumps and related equipment which may involve noise affecting adjacent areas.

      March 16 - 20: Preparation for steel framing of Pavilion: steel delivery, etc.

      March 20: delivery of switchgear, a large piece of equipment, near Pacific Wing.

      March 20: Possible temporary closure of LMNorth/LMMain bridge. Details, when final, will be sent to Housing and campus staff in a separate notice.

      March 23 - 27: Estimated installation of steel framing of the Pavilion structure

      Interior work:

      Completion of fireproof paint on structural systems. Fans will be installed to facilitate drying and air circulation however odors from paint may affect adjacent areas including LM Chapel.

      Infill of openings of the west wall/kitchen area.

      Ongoing work on plumbing systems on main and in Public Safety: Noise may affect adjacent areas including LM Chapel and LMM lower levels.

      Periodic deliveries of materiel: steel, rebar, concrete.

      War Memorial Gym/Sobrato Center

      March 6-18: Subgrade plumbing final connections, sublease gravel, slab on grade waterproofing.

      Concrete pour: specific date TBD; 6 - 10 trucks.

      Continuing work on interior.

      Continuing exterior work on drain lines, waterproofing, and plumbing.


      3/12/2020 Update:

      Since late January, the University of San Francisco administration has been closely monitoring the COVID-19 outbreak. USF is analyzing new information daily from public health officials and civic leaders and is developing mitigating actions in accordance with that guidance.

      At this date, there are no known cases of the coronavirus on the USF campus.

      Please note these updates:

      Effective Wednesday, March 11, 2020 USF is suspending face-to-face instruction at all USF campus locations at least through Sunday, March 29. All classes will be conducted online beginning March 18.

      Although face-to-face instruction is suspended, the University remains open. Some staff and faculty will continue to report to work on campus while others have made temporarily-approved, remote work arrangements.

      Some students will remain on campus during this period of online instruction: the residence halls, library, recreational facilities, and dining services will remain open. All in-person, non-essential on-campus events at the Hilltop and Downtown (101 Howard) campuses are canceled through March 21.

      University buildings will be locked and accessible by One Card during this period.

      The University is making decisions in a rapidly evolving situation and may need to adjust this plan as necessary.


      3/06/2020 Update:

      Lone Mountain Residence Hall

      On-going:

      Construction fans will run 24/7 to dry interior portions of both building. The fans are powered by a generator which will also run throughout this period. The activity will continue through March.

      East & West Bldgs: work on exterior skin

      Shotcrete around north stairs and hammerhead, west site walls.

      Framing on the East Building and West Buildings continues.

      Roofing continues on the East and West Bldgs.

      Periodic deliveries of framing, roof trusses, lumber, windows.

      Installation of windows continues.

      Installation of storm drains and other site work.

      Upcoming: Tower crane removal anticipated in early April

      Dining Hall Project at Lone Mountain Main

      Exterior Work:

      March 7: completion of forms for south Pavilion wall. May involve some noise affecting adjacent areas.

      March 11: Concrete pour of 1st two sections of south Pavilion wall. Equipment involves pumps and related equipment which may involve noise affecting adjacent areas.

      March 18: Concrete pour of 2nd two sections of south Pavilion wall. Equipment involves pumps and related equipment which may involve noise affecting adjacent areas.

      March 20: delivery of switchgear, a large piece of equipment, near Pacific Wing. (Date change from Mar 13)

      Interior work:

      Thru March 13: Application of fireproof paint on structural systems. Fans will be installed to facilitate drying and air circulation however odors from paint may affect adjacent areas including LM Chapel

      LMM lower levels.

      Ongoing work on plumbing systems on main and in Public Safety: Noise may affect adjacent areas including LM Chapel and LMM lower levels.

      Periodic deliveries of materiel: steel, rebar, concrete.

      War Memorial Gym/Sobrato Center

      March 6-13: Subgrade plumbing final connections, sublease gravel, slab on grade waterproofing.

      Week of March 16: specific date TBD; concrete pour, 6 - 10 trucks.

      Continuing work on the interior.

      Continuing exterior work on drain lines, waterproofing, and plumbing.


      2/28/2020 Update:

      Lone Mountain Residence Hall

      Feb 21 - March 6: Waterproofing and sealing of all outside areas (rooftops, courtyards, paseo, and walkways) will involve the application of sealant and rubberized material. Depending on conditions, odors may affect adjacent areas including Loyola House.

      On-going:

      Construction fans will run 24/7 in the first phase of drying interior portions of East Building. The fans are powered by a generator which will also run throughout this period. There will be additional active drying periods in late February and early March.

      Shotcrete around north stairs and hammerhead, west site walls.

      Framing on the East Building and West Buildings continues.

      Roofing continues on the East and West Bldgs.

      Periodic deliveries of framing, roof trusses, lumber, windows.

      The installation of windows continues.

      Installation of storm drains and other site work.

      Dining Hall Project at Lone Mountain Main

      Exterior Work:

      Feb 24 - March 13: Continued work on foundation slab on grade and preparation for Pavilion’s exterior walls: installation of rebar, MEP connections, build forms for 16ft exterior south wall, pour wall sections.

      Mar 2: small concrete pour at SW corner of Pacific Wing for new transformer and switchgear; estimate 10 am

      Mar 13 (estimate): delivery of switchgear, a large piece of equipment, near Pacific Wing.

      Interior work:

      Feb 24 - March 13: Application of fireproof paint on structural systems. Fans will be installed to facilitate drying and air circulation however odors from paint may affect adjacent areas including LM Chapel

      Mar 12 (estimate): Concrete pour, topping slab

      LMM lower levels.

      Ongoing work on plumbing systems on main and in Public Safety: Noise may affect adjacent areas including LM Chapel and LMM lower levels.

      Periodic deliveries of materiel: steel, rebar, concrete.

      War Memorial Gym/Sobrato Center

      Feb 24 - March 13: Continued work on foundation slab: installation of rebar, deliver gravel, connect plumbing for drainage systems, pour footings.

      March 5: concrete pour, about 6 trucks.

      Continuing work on the interior.

      Continuing exterior work on drain lines, waterproofing, and plumbing.


      2/21/2020 Update:

      Lone Mountain Residence Hall

      Feb 21 - March 6: Waterproofing and sealing of all outside areas (rooftops, courtyards, paseo, and walkways) will involve the application of sealant and rubberized material. Depending on conditions, odors may affect adjacent areas including Loyola House.

      Feb 25: Concrete pour at north stairs

      Feb 26: PG&E work on Turk Blvd on power systems 8 pm - after midnight.

      On-going:

      Construction fans will run 24/7 in the first phase of drying interior portions of the East Building. The fans are powered by a generator which will also run throughout this period. There will be additional active drying periods in late February and early March.

      Shotcrete around east side wall, north stairs, and hammerhead, west side walls.

      Framing on the East Building and West Buildings continues.

      Roofing continues on the East and West Bldgs.

      Periodic deliveries of framing, roof trusses, lumber, windows.

      The installation of windows continues.

      Installation of storm drains and other site work.

      Dining Hall Project at Lone Mountain Main

      Exterior Work:

      Feb 24 - March 13: Continued work on foundation slab on grade and preparation for Pavilion’s exterior walls: installation of rebar, MEP connections, build forms for 16ft exterior south wall, pour wall sections.

      Feb 26: small concrete pours at SW corner of Pacific Wing for new transformer and switchgear.

      Interior work:

      Feb 24 - March 13: Application of fireproof paint on structural systems. Fans will be installed to facilitate drying and air circulation however odors from paint may affect adjacent areas including LM Chapel and LMM lower levels.

      Ongoing work on plumbing systems on main and in Public Safety: Noise may affect adjacent areas including LM Chapel and LMM lower levels.

      Periodic deliveries of materiel: steel, rebar, concrete.

      War Memorial Gym/Sobrato Center

      Feb 24 - March 13: Continued work on foundation slab: installation of rebar, deliver gravel, connect plumbing for drainage systems, pour footings.

      Continuing work on the interior. Continuing exterior work on drain lines, waterproofing, and plumbing.


      2/13/2020 Update:

      President’s Day is expected to be fairly quiet at all three sites. Most Trades have President’s Day off (2/17), but those who do not will be at work on site.

      Lone Mountain Residence Hall

      Waterproofing and sealing of all outside areas (rooftops, courtyards, paseo, and walkways) will involve the application of sealant and rubberized material that has begun and will continue periodically through early March. Depending on conditions, there may be odors associated with the process.

      Feb 18-25: Shotcrete around the East Building, exterior walls, hammerhead.

      Construction fans will run 24/7 in the first phase of drying interior portions of East Building. The fans are powered by a generator which will also run throughout this period. There will be additional active drying periods in late February and early March.

      On-going:

      Framing on the East Building and West Buildings continues.

      Roofing continues on the East and West Bldgs.

      Periodic deliveries of framing, roof trusses, lumber, windows.

      Installation of windows continues.

      Installation of storm drains and other site work.

      Small concrete pours continue at the northwest corner of the site.

      Dining Hall Project at Lone Mountain Main

      Exterior Work:

      Continued work on foundation slab on grad and preparations for Pavilion’s exterior walls.

      Interior work:

      Feb 18-21: Continued gravel delivery, backfill, then concrete pour for plumbing trenches in the main interior. Noise may affect adjacent areas including LM Chapel and LMM lower levels.

      Feb 18-21: Ongoing installation of plumbing systems.

      Interior work on the 2nd floor of LMMain is complete.

      Plumbing work is the area behind Public Safety/Dispatch continues.

      Periodic deliveries of materiel: steel, rebar, concrete.

      War Memorial Gym/Sobrato Center

      February 20, Thursday: small concrete pour involving up to 5 trucks. The date of pour could change depending on external factors.

      Continuing work on the interior. Continuing exterior work on drain lines, waterproofing, and plumbing.

      1/31/2020 Update:

      Lone Mountain Residence Hall

      February 12 - 21: Construction fans will run 24/7 in the first phase of drying interior portions of East Building. The fans are powered by a generator which will also run throughout this period. There will be additional active drying periods in late February and early March dates to be finalized.

      On-going:

      Framing on the East Building and West Buildings continues.

      Roofing continues on the East and West Bldgs.

      Periodic deliveries of framing, roof trusses, lumber, windows.

      The installation of windows continues.

      Installation of storm drains and other site work.

      Small concrete pours continue at the northwest corner of the site.

      Dining Hall Project at Lone Mountain Main

      Exterior Work:

      Saturday, Feb 8: Exterior concrete pour of Pavilion foundation. It will involve 10-20 trucks. Start time at 8am. Expected duration 12-14 hours; once started the pour must continue until complete to insure the concrete pad cures evenly.

      LMNorth residences and Loyola House may be affected by noise, dust, and exhaust from the equipment.

      Update: the foundation slab requires control joints cut into it, a process requiring saw-cutting expected to last 4 hours. The saw-cutting will occur either on Sunday 2/9 or Monday 2/10, depending on the condition of the concrete slab. The process will be noisy and disruptive to adjacent buildings, classrooms, and offices.

      Feb 11: A contractor will move wall panels to the Pavilion. There will be some periodic disruption to access through the passage between LMMain and LMNorth.

      Interior work:

      Feb 10 -12: Gravel delivery, backfill, then concrete pour for plumbing trenches in the main interior. Noise may affect adjacent areas including LM Chapel and LMM lower levels.

      Fireproofing steel columns and beams on the main level continue.

      Interior work on the 2nd floor, east of the main chapel area continues. Expected completion date Feb 10.

      Continued coring work for plumbing etc which will involve saw cutting & jackhammering. It will be noisy in adjacent areas.

      Plumbing work is the area behind Public Safety/Dispatch continues.

      Ongoing:

      Periodic deliveries of materiel: steel, rebar, concrete.

      War Memorial Gym/Sobrato Center

      Continuing work on the interior. Continuing exterior work on drain lines, waterproofing, and plumbing.


      1/31/2020 Update:

      Lone Mountain Residence Hall

      Tuesday, Feb 4: Small concrete pour at the northwest corner of the site; 2-4 concrete trucks, some noise from pumps.

      On-going:

      Framing on the East Building and West Buildings continues.

      Roofing continues on the East and West Bldgs.

      Periodic deliveries of framing, roof trusses, lumber, windows.

      The installation of windows continues.

      Installation of storm drains and other site work.

      Dining Hall Project at Lone Mountain Main

      Exterior Work:

      Saturday, Feb 1: Installation of the trench for utilities across the driveway at the southwest corner of Pacific Wing, while will involve, saw cutting and backhoe work. Start at 9 am.

      Student residences in Pacific Wing may be affected by noise, dust, and exhaust from the work.

      Saturday, Feb 8: Exterior concrete pour of Pavilion foundation. It will involve 10-20 trucks. Start time at 8 am. Expected duration 12-14 hours; once started the pour must continue until complete to insure the concrete pad cures evenly.

      LMNorth residences and Loyola House may be affected by noise, dust, and exhaust from the equipment.

      Feb 3-7: Preparatory work for the foundation pour includes grading, delivery and placement of gravel substrate, and installation of rebar throughout next week. This work may be noisy and may also affect nearby spaces.

      Interior work:

      Monday, Feb 3 - 6: foundation work on the interior slab in the main interior area. Will involve drilling resulting in noise and vibration affecting adjacent areas including LM Chapel and LMM lower levels.

      Plumbing work affecting lower-level offices at the east end of LMM is complete.

      Fireproofing steel columns and beams on the main level continue.

      Interior work on the 2nd floor, east of the main chapel area continues. Expected completion date Feb 10.

      Continued coring work for plumbing etc which will involve saw cutting & jackhammering. It will be noisy in adjacent areas.

      Sawcutting openings in selected interior and exterior walls continues. This work will be noisy and disruptive to areas above and adjacent to the interior site such as the Chapel area and Dispatch.

      Plumbing work is the area behind Public Safety/Dispatch continues.

      Ongoing:

      Periodic deliveries of materiel: steel, rebar, concrete.


      1/24/2020 Update:

      Recent Power Outages

      The power outages you may have experienced are not USF induced. It appears they extend to a larger area surrounding Lone Mountain.

      Please refer to this PGE link for information:,/br> https://m.pge.com/#outages

      Lone Mountain Residence Hall

      Work at the infiltration basin should be completed this week.

      On-going:

      The installation of windows continues.

      Periodic deliveries of framing, roof trusses, lumber, windows.

      Installation of storm drains and other site work.

      Framing on the East Building and West Buildings continues.

      Roofing continues on the East Bldg.

      North stair, West Bldg: waterproofing and shotcrete continues

      War Memorial Gym/Sobrato Center

      Continuing work on the interior. Continuing exterior work on drain lines, waterproofing, and plumbing.

      Dining Hall Project at Lone Mountain Main

      Ongoing:

      deliveries of materiel: steel, rebar, gravel, concrete.

      Interior work:

      Jan 31: interior concrete pour of slab on grade; will involve about 5-8 concrete trucks and associated activities in the rear lot.

      Plumbing work affecting lower-level offices at the east end of LMM is nearing completion. The estimated completion is Monday, Jan 27.

      Fireproofing steel columns and beams on the main level continue.

      Interior work on the 2nd floor, east of the main chapel area continues. Expected completion date Feb 10.

      Continued coring work for plumbing etc which will involve saw cutting & jackhammering. It will be noisy in adjacent areas.

      Sawcutting openings in selected interior and exterior walls continues. This work will be noisy and disruptive to areas above and adjacent to the interior site such as the Chapel area and Dispatch.

      Plumbing work is the area behind Public Safety/Dispatch continues.

      Exterior Work:

      Installation of pan decking continues over cantilever beams nearing completion. Cutting and placing pan decking is noisy and may affect nearby interior spaces.

      Continued work on the foundation includes grading, delivery, and placement of gravel substrate, nearing completion. This work may be noisy and may also affect nearby spaces.

      Feb 5 - Exterior concrete pour of slab on grade. Will involve 10-20 trucks, The work may extend beyond 5 pm.

      Offices and classrooms adjacent to the outside area may be affected by noise, dust, and exhaust from the equipment.

      Ongoing work:

      installation of power for Dining Project; Trenching is in the driveway area west of Pacific Wing and in the Cahill lot behind LMMain. There will be saw cutting and digging at various times. This work will be noisy sometimes and disruptive to areas above and adjacent to the Pacific Wing and Chapel area.


      1/18/2020 Update:

      Lone Mountain Residence Hall

      Work at the infiltration basin continues. Subject to other work on-site and the weather, the work may push into next week. Trench across the interior driveway nearing completion.

      On-going:

      Installation of windows continues.

      Periodic deliveries of framing, roof trusses, lumber, windows.

      Installation of storm drains and other site work.

      Framing on the East Building and West Buildings continues.

      Roofing continues on the East Bldg.

      Paseo concrete pour complete.

      North stair, West Bldg: waterproofing and cast-in-place concrete continues

      War Memorial Gym/Sobrato Center

      Continuing work on interior. Continuing exterior work on drain lines, waterproofing, and plumbing.

      Dining Hall Project at Lone Mountain Main

      Interior work:

      Plumbing work affecting lower-level offices at the east end of LMM is nearing completion.

      Estimated completion is Monday Jan 27.

      Fireproofing steel columns and beams on the main level continues.

      Continued coring work for plumbing etc which will involve saw cutting & jackhammering. It will be noisy to adjacent areas.

      Sawcutting openings in selected interior and exterior walls continues. This work will be noisy and disruptive to areas above and adjacent to the interior site such as the Chapel area and Dispatch.

      Exterior Work:

      Installation of pan decking continues over cantilever beams continues. Cutting and placing pan decking is noisy and may affect nearby interior spaces.

      Continued work on the foundation includes grading, delivery and placement of gravel substrate, which may be noisy and may also affect nearby spaces.

      Offices and classrooms adjacent to the outside area may be affected by noise, dust, and exhaust from the equipment.

      Jan 13-24: preparation for PGE power for Dining Project; the first phase is pot-holing then trenching is driveway area west of Pacific Wing and in the Cahill lot behind LMMain. There will be saw cutting and digging at various times. This work will be noisy sometimes and disruptive to areas above and adjacent to the Pacific Wing and Chapel area.


      1/10/2020 Update:

      Lone Mountain Residence Hall

      January 11: Completion of removal of two trees at southeast quadrant of Res Hall site. Works starts 8am.

      January 13 - 17: Related to work at the infiltration basin and subject to other work on site which may push the work to the following week, a trench is to be dug on the interior driveway. A mobile crane is scheduled for delivery Thursday Jan 16. Dates may change without notice.

      On-going:

      Periodic deliveries of framing, roof trusses, lumber, windows Nearing completion on installation of windows in the east building.

      Framing on the East Building and West Buildings

      Installation of storm drains and other site work

      Roofing continues on the East Bldg

      Grading the Paseo complete: concrete pour estimated for Jan 13/14, subject to rain delays. Approximately 10 trucks.

      North stair, West Bldg: water proofing and cast-in-place concrete after Jan 14.

      War Memorial Gym/Sobrato Center

      Continuing work on utilities, interior work, and exterior work in the excavated pit, west side.

      Dining Hall Project at Lone Mountain Main

      Interior work:

      Plumbing work, lower level LMM, east end. Offices at the east end will be inaccessible through Jan 27, estimate.

      Fireproofing steel columns and beams continues.

      Continued coring work for plumbing etc which will involve saw cutting & jack hammering. It will be noisy to adjacent areas.

      Sawcutting openings in selected interior and exterior walls continues.

      This work will be noisy and disruptive to areas above and adjacent to the interior site such as the Chapel area and Dispatch.

      Exterior Work:

      Continued work on the foundation structures of the Pavilion including installation of grade beams, rebar work, and excavation.

      Offices and classrooms adjacent to the outside area may be affected by noise, dust, and exhaust from the equipment.

      Jan 13-24: preparation for PGE power for Dining Project; first phase is pot-holing then trenching in driveway area west of Pacific Wing and in the Cahill lot behind LMMain.

      There will be sawcutting and digging at various times. This work will be noisy sometimes and disruptive to areas above and adjacent to the Pacific Wing and Chapel area.


      1/2/2020 Update:

      Lone Mountain Residence Hall

      January 4: Removal of two trees at southeast quadrant of Res Hall site. Works starts 8am.

      On-going:

      Periodic deliveries of framing, roof trusses, lumber, and windows Framing on the East Building and West Buildings

      Installation of storm drains and other site work

      Roofing on the East Bldg

      Grading the Paseo through 12/30, subject to rain delays.

      North stair, West Bldg: waterproofing and cast-in-place concrete

      War Memorial Gym/Sobrato Center

      Continuing work on utilities and other interior work.

      Dining Hall Project at Lone Mountain Main

      Interior work:

      12/16 - early January

      Plumbing work, lower level LMM, east end. Offices at the east end will be inaccessible.

      Fireproofing steel columns and beams continues.

      Monday Jan 6: Coring work for plumbing etc will involve saw cutting & jackhammering. It will be noisy in adjacent areas.

      Sawcutting openings in selected interior walls continue.

      This work will be noisy and disruptive to areas above and adjacent to the interior site such as the Chapel area and Dispatch.

      Exterior Work:

      Continued work on the foundation structures of the Pavilion including installation of grade beams, rebar work, and excavation.

      Offices and classrooms adjacent to the outside area may be affected by noise, dust, and exhaust from the equipment.


      12/20/2019 Update:

      Lone Mountain Residence Hall

      Framing, roofing, deliveries of materiel continue on the East Building and West Buildings continues.

      Installation of storm drains on the West Building continues.

      Holiday work schedule:

      There will be no work at the Res Hall site on Christmas Day nor on New Year’s Day.

      War Memorial Gym/Sobrato Center

      Continuing work on waterproofing, plumbing and other interior work. Small concrete pour today. No significant noise is anticipated.

      Dining Hall Project at Lone Mountain Main

      Interior work:

      Excavation for below-grade plumbing continues,

      Saw cutting interior walls and foundation slab will start today and continue through next week. This work will be disruptive to adjoining areas.

      2nd floor LMM - Installation of venting begins, continues through mid-January.

      Exterior Work:

      Installation of grade beams finishing up.

      Continuing to dig for MEPs at the same time - laterals through to sinks etc

      Concrete pour next Friday 12/27, pump from backlot.

      Steel delivery 12/30.

      Offices and classrooms adjacent to the outdoor site may be affected by dust and exhaust from the equipment.

      Holiday work schedule:

      There will be no work at the Res Hall site on Christmas Day nor on New Year’s Day.


      12/13/2019 Update:

      New Item: Kalmanovitz Hall, Fulton Street

      LARGE RIG, Tuesday Dec 17

      We are replacing equipment on the Kalmanovitz roof. A large rig will be delivered in the early morning and will occupy the quad between K hall and Gleeson Library.

      The K-Hall equipment is expected to be back on line on Friday 12/20. The contractor will have another rig delivered to the quad by 7am to take material down off K Hall.

      Lone Mountain Residence Hall

      Tues-Thurs Dec 17-19: Excavation and fill of line at Turk, gate east construction gate. Will involve up to 45 trucks over the 3 day period.

      Saturday 12/14: Removal of shoring at west bin wall, near Loyola House. 8am start. Date may change due to weather.

      On-going:

      Infiltration basin at Turk frontage restoration continues.

      Periodic deliveries of framing, roof trusses, lumber, and windows

      Framing on the East Building and West Buildings Roofing on east building continues.

      Installation of storm drains and other site work Grading the Paseo through 12/30, subject to rain delays.

      North stair, West Bldg: water proofing and cast-in-place concrete

      Holiday work schedule: No work on Christmas Day or New Year’s Day.

      War Memorial Gym/Sobrato Center

      12/14: Exterior excavation 8am-3pm

      Continuing work on waterproofing, utilities, and other interior work.

      Dining Hall Project at Lone Mountain Main

      Interior work:

      12/16 - January 27

      Plumbing work, lower level LMM, east end. Offices at the east end will be inaccessible. Fireproofing steel columns and beams in the main dining area.

      Interior sawcutting and concrete work will continue periodically into January. This work will be noisy and disruptive to areas above and adjacent to the interior site such as the Chapel area and Dispatch.

      Cahill’s work in LM265, east side of the chapel, will begin 12/16 including finishing venting from the dining area. Once complete, electrical work, carpet, and installation of furniture will be approximately Jan 13-27.

      Exterior Work:

      December 27: Steel delivery

      Continued work on the foundation structures of the Pavilion including installation of grade beams, rebar work, and excavation continues.

      Offices and classrooms adjacent to the outside area may be affected by noise, dust, and exhaust from the equipment.

      Work schedule:

      Interior work 7am start time.

      Dining: exterior work start time Dec 23,24,26,27 will be 8am.

      Gym exterior start time 8am

      There will be no work at the Gym or Dining sites on Christmas Day or New Year’s Day.

      Other Announcements

      San Francisco Fire Department on Campus: Monday, Tuesday, Wednesday Dec 16,17,18 The University will host three San Francisco Fire Battalions to familiarize fire crews and captains with the layout of buildings and facilities on Lone Mountain. One fire battalion will be on the upper campus each day, Monday through Wednesday next week. In a circumstance when a full battalion is away from its respective station, it is required to travel with its fleet in case of emergency. Accordingly, you will see up to five fire trucks and support vehicles parked on the Lone Mtn Drive on each of those days.


      12/5/2019 Update:

      Lone Mountain Residence Hall

      Fri/Sat 12/6-7 work begins to restore infiltration basin at Turk frontage; will involve trucks off hauling

      Saturday 12/7: Removal of shoring at west bin wall, near Loyola House. 8am start.

      Mon/Tues 12/9-10: cutting micro piles at north landing to grade.

      On-going:

      Periodic deliveries of framing, roof trusses, lumber, and windows Framing on the East Building and West Buildings

      Installation of storm drains and other site work

      Roofing on the East Bldg

      Grading the Paseo through 12/30, subject to rain delays.

      North stair, West Bldg: water proofing and cast-in-place concrete

      Holiday work schedule: No work on Christmas Day or New Year’s Day.

      War Memorial Gym/Sobrato Center

      Continuing work on waterproofing, utilities, and other interior work.

      Dining Hall Project at Lone Mountain Main

      Interior work:

      12/16 - early January,
      Plumbing work, lower level LMM, east end. Offices at the east end will be inaccessible. I will contact units affected with details as they become known.

      Fireproofing steel columns and beams.

      On-going

      Remove wall forms for interior walls.

      Next step on interior walls will be sawcutting select openings, expected to start 12/13

      This work will be noisy and disruptive to areas above and adjacent to the interior site such as the Chapel area and Dispatch.

      Exterior Work:

      Continued work on the foundation structures of the Pavilion including installation of grade beams, rebar work, and excavation.

      Offices and classrooms adjacent to the outside area may be affected by noise, dust, and exhaust from the equipment.

      Holiday work schedule: There will be no work at the Gym or Dining sites on Christmas Day or New Year’s Day.


      11/20/2019 Update:

      Lone Mountain Residence Hall

      Water Shut Off: November 26,10am-Noon estimate. Shut off will affect Lone Mountain Main, Rossi, and Loyola House.

      Installation of scaffolding at various locations around the east building continues.

      Periodic deliveries of framing, roof trusses, and windows will continue.

      tallation of storm drains and other site work continues.

      Roofing on the East Bldg is scheduled to start 12/9.

      Thanksgiving work schedule: There will be no work at the Res Hall site on Thanksgiving Day. Regular work will continue on Friday and Saturday 11/29 & 11/30.

      War Memorial Gym/Sobrato Center

      Installing underground plumbing in the excavation area.

      Continuing work on waterproofing and other interior work. No significant noise is anticipated.

      Dining Hall Project at Lone Mountain Main

      Interior work:

      Work will continue on installation of rebar and placement of concrete forms to reinforce existing structural walls.

      Concrete pour Thursday 11/21, pump from back lot. One day. 3 trucks.

      Sawcutting, jack hammering, and then excavation of concrete foundation in the interior area will continue.

      This work will be noisy and disruptive to areas above and adjacent to the interior site such as the Chapel area and Dispatch.

      Exterior Work:

      Continued work on the foundation area of the Pavilion will continue. There will be outside work at the Pavilion site on Saturday 11/23, 9am-5pm

      Deliveries of large grade beams will begin the week of 11/25, specific dates to be coordinated with other construction activity nearby. These deliveries may occasionally impact traffic on Lone Mtn Drive.

      Noise from these activities may affect nearby classrooms and offices. Offices and classrooms adjacent to the lawn may also be affected by dust and exhaust from the equipment.

      Thanksgiving work schedule: There will be no work at the Gym or Dining sites 11/28-11/30.


      11/15/2019 Update:

      Lone Mountain Residence Hall

      Water Shut Off: November 26,10am-Noon estimate. Shut off will affect Lone Mountain Main, Rossi, and Loyola House.

      Concrete Mat Pours - November 16 and 20. Start at 7am. 20-25 trucks per day. We are working with the contractor to have the pumps delivered the day before each pour to avoid early morning delivery.

      Periodic deliveries of framing, roof trusses, and windows will continue. Framing on the East Building and West Buildings continues.

      The installation of storm drains on the West Building continues.

      Thanksgiving work schedule: There will be no work at the Res Hall site on Thanksgiving Day. Regular work will continue on Friday and Saturday 11/29 & 11/30.

      War Memorial Gym/Sobrato Center

      Completing excavation and off-haul through today. Continuing work on waterproofing, plumbing, and other interior work. No significant noise is anticipated.

      Dining Hall Project at Lone Mountain Main

      Interior work:

      Work will continue on the installation of rebar and placement of concrete forms to reinforce existing structural walls. Concrete pour next Thursday 11/21, pump from backlot. One day. 3 trucks. Sawcutting, jackhammering, and then excavation of concrete foundation in the interior area will continue. This work will be noisy and disruptive to areas above and adjacent to the interior site such as the Chapel area and Dispatch.

      Exterior Work:

      Earthwork Saturday 11/16: Grading and digging in the outside area. 9am-5pm Excavation for preparation for grade beams will continue through Wed 11/20. Saw cutting the retaining wall should be completed by 11/20..

      Deliveries of large grade beams will begin on 11/27 which may occasionally impact traffic on Lone Mtn Drive.

      Noise from these activities may affect nearby classrooms and offices. Offices and classrooms adjacent to the lawn may also be affected by dust and exhaust from the equipment.

      Thanksgiving work schedule: There will be no work at the Gym or Dining sites 11/28-11/30.


      11/6/2019 Update:

      Lone Mountain Residence Hall

      Water Shut Off: November 26,10am-Noon estimate. Shut off will affect Lone Mountain Main, Rossi, and Loyola House.

      Concrete Mat Pours: November 16 and 20. Start at 7am. 20-25 trucks per day. We are working with the contractor to have the pumps delivered the day before each pour to avoid early morning delivery.

      Periodic deliveries of roof trusses and windows will occur throughout the week.

      Framing on the East Building and West Buildings continues.

      Installation of storm drains on the West Building continues.

      War Memorial Gym/Sobrato Center

      Prep work for the removal of the concrete light well wall will continue through tomorrow. The wall will be removed with a concrete saw on Friday and Monday 11/8 and 11/11, which will be noisy. About 3 trucks will be used to take the concrete away.

      Dining Hall Project at Lone Mountain Main

      Interior work

      Installation of mechanical, electrical, and plumbing infrastructure into the existing concrete foundation requires saw-cutting and limited excavation. Work will continue for installation of rebar to reinforce existing structural walls. Cahill will begin to pour structural concrete for reinforced walls and footings.

      Friday November 8. Sawcutting, jack hammering, and then excavation of concrete foundation in the interior area is scheduled to begin Nov 8 and will continue through the week of November 11 at least. This work will be noisy and disruptive to areas above and adjacent to the interior site such as the Chapel area and Dispatch.

      Exterior Work

      Earthwork

      November 11: Excavation for new grade beams begins. Preparation of the Pavilion site for grade beams & foundation involves saw-cutting the existing retaining wall to grade, digging for new footings, and excavation of about 1 foot of soil. Noise from this activity will affect nearby classrooms and offices. Offices and classrooms adjacent to the lawn may also be affected by dust and exhaust from the equipment.

      The schedule for work is: Monday through Saturday 8am - 7pm.


      11/1/2019 Update:

      Lone Mountain Residence Hall

      Water Shut Off: November 26, 10am-12pm, will affect parts of Lone Mtn. Details to follow.

      Concrete Mat Pours: November 16 and November 20. Start at 7am. 20 -25 trucks per day.

      Scaffolding is in place along the length of the east side and up to two to three stories. Framing on the East Building and West Building is on-going. Roof trusses are being installed at portions of the East Building.

      War Memorial Gym/Sobrato Center

      Excavation along the west side is continuing. Contractors are completing lagging and below-grade waterproofing.

      Interior work is ongoing.

      Dining Hall Project at Lone Mountain Main

      Micropiles

      Drilling micro piles in the Pavilion/Lawn area is complete.

      Earthwork

      Contractors are working to finish the drainage system on the hillside between the Lone Mtn Lawn and Lone Mtn North. They will work on the hillside on Saturday, Nov 2 starting at 9 am. Some of the work will be noisy.

      Earthwork is expected to begin after Nov 6. Preparation of the Pavilion site for grade beams & foundation involves saw-cutting the existing retaining wall to grade, digging for new footings, and excavation of about 1 foot of soil. Noise from this activity will periodically affect nearby classrooms and offices. Offices and classrooms adjacent to the lawn may also be affected by dust and exhaust from the equipment.

      Interior work

      Installation of mechanical, electrical, and plumbing infrastructure into the existing concrete foundation requires saw-cutting and limited excavation. Work will continue for the installation of rebar to reinforce existing structural walls.

      Saturday, Nov 2: Excavation of shear wall footings in the interior area. There will be some saw-cutting in the interior on Saturday.

      November 6: More extensive saw cutting of the concrete foundation is scheduled to begin after Wednesday, Nov 6 . This work will be noisy and disruptive to areas adjacent to the interior site such as the Chapel area and Dispatch.

      This work will be noisy within the immediate area

      Water Shutoff at Lone Mtn Main- canceled. The contractor found a less disruptive alternative.


      10/25/2019 Update:

      Lone Mountain Residence Hall

      Scaffolding is being erected along the east side of the East Building (west of Ewing Terrace property lines). The scaffolding will be in place along the length of the east side and up to two to three stories. The work will involve some noise. Framing on the East Building and West Buildings continues. Installation of storm drains on the West Building continues.

      War Memorial Gym/Sobrato Center

      Excavation along the west side is continuing. There will be minor truck traffic for off haul; 3-4 trucks per day, including Saturday Oct 26. The noise level is expected to be moderate. Interior work is continuing.

      Dining Hall Project at Lone Mountain Main

      Micropiles

      Drilling micro piles in the Pavilion/Lawn area is complete. The piles will be tested early next week, after which the site will be prepared for excavation and saw cutting.

      Earthwork

      Preparation of the Pavilion site for grade beams & foundation involves saw-cutting the existing retaining wall to grade, digging for new footings, and excavation of about 1 foot of soil. Noise from this activity will periodically affect nearby classrooms and offices. Offices and classrooms adjacent to the lawn may also be affected by dust and exhaust from the equipment.

      The schedule for exterior work is: Monday through Saturday 8am - 7pm.

      Interior work

      Installation of mechanical, electrical, and plumbing infrastructure into the existing concrete foundation requires saw-cutting and limited excavation. Work will continue for installation of rebar to reinforce existing structural walls.

      Saturday Oct 26: Sawcutting and then excavation of shear wall footings in the interior area. Monday November 4: More extensive saw cutting of the concrete foundation is scheduled to begin Monday Nov 4 . This work will be noisy and disruptive to areas adjacent to the interior site such as the Chapel area and Dispatch.

      This work will be noisy within the immediate area

      Water Shutoff - postponed. Looking at less intrusive alternatives. Details to follow when they’re set.

      10/21/2019 Update:

      Early Morning Equipment Pickup

      A large piece of equipment is scheduled to be picked up on Tuesday October 22 at approximately 5:00 a.m. As with other larger equipment, the size of the truck required for hauling the equipment triggers travels time restrictions required by the City of San Francisco. Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise. We apologize for the disruption and inconvenience.

      10/17/2019 Update:

      Lone Mountain Residence Hall

      Scaffolding is being erected along the east side of the East Building (west of Ewing Terrace property lines). The scaffolding will be in place along the length of the east side. The work will take several weeks and will involve some noise.

      Installation of micro piles at the north stair landing continues through Oct 19. Testing of the micro piles will be between Oct 28 - Oct 31.

      East Building: Rough framing of the upper floors continues. Second floor roof scheduled to be in place by Oct 31.

      West Building: Rough framing on the first level is underway. Shotcrete work in the garage level is to be completed 10/16.

      Trenching for the installation of storm drains will begin on the West Building continues.

      War Memorial Gym/Sobrato Center

      Demo of concrete at the southwest corner of WMG is complete.

      Excavation along the west side continues There will be minor truck traffic for off haul; 3-4 trucks per day. The noise level is expected to be moderate.

      Dining Hall Project at Lone Mountain Main

      Water Shutoff

      a 2-3 hour water shut off is being planned that will affect LMMain Chapel area and Loyola House. The date and time have not yet been set, but I will send a notice email as soon as I know.

      Exterior Work

      Drilling of micro piles is expected to be complete by October 19.

      Preparation of the Pavilion site for grade beams & foundation will involve saw-cutting the existing retaining wall to grade, currently scheduled for Oct 21-29. This work will be loud.

      Grading the site is currently scheduled for Oct 30 - Nov 5.

      These activities may periodically affect nearby classrooms and offices. Offices and classrooms adjacent to the lawn may also be affected by dust and exhaust from the equipment.

      The schedule exterior work is: Monday through Saturday 8am - 7pm.

      Interior Work

      Installation of mechanical, electrical, and plumbing infrastructure into the existing concrete foundation requires saw-cutting and limited excavation. Work will continue for installation of rebar to reinforce existing structural walls.

      Sawcutting and then excavation of shear wall footings in various sections of the site began Oct 17. This work will be occur periodically and be noisy and disruptive. I will share specific dates as they become known.

      Chapel Roof (over LMM 265)

      New openings in the roof for venting requirements have been completed. Temporary water proofing for those openings is in place. Final water proofing work will occur over the winter break. The roofers identified some spots on the west side of the chapel roof that may require minor repairs. Scope and dates to be determined.


      10/11/2019 Update:

      Lone Mountain Residence Hall

      Evacuation Drill: There will be a required evacuation drill at the site on Tuesday Oct 15 between 8 and 9am. All construction personnel are required to leave the construction site and gather in a pre-determined location which, in this case, will be the USF parking lot on the west side of the School of Ed/Presentation Hall building. The process should take less than an hour.

      The contractor will apply shotcrete to the West Building stair through early next week, including work on Saturday Oct 12, starting about 8am. Shotcrete is sprayed concrete conveyed through a hose at a high velocity onto a surface. The process can be noisy.

      Auger cast piles will be drilled in the west building on Oct 15. The use of an air compressor will cause some noise.

      Scaffolding is being erected along the east side of the East Building (west of Ewing Terrace property lines). The scaffolding will be in place along the length of the east side and up to two to three stories. The work will take several weeks and will involve some noise.

      Framing on the East Building continues.

      Trenching for the installation of storm drains will begin on the West Building continues.

      War Memorial Gym/Sobrato Center

      Drilling for micropiles is complete.

      Portions of concrete at the southwest corner of WMG need to be demolished. Work will involved a hydraulic hammer and then saw cutting. The work will be noisy and will occur Oct 14 - 18.

      Excavation along the west side is expected to begin this week and will last about a week. There will be minor truck traffic for off haul; 3-4 trucks per day. The noise level is expected to be moderate.

      Installation of temporary water proofing along the west border of the gym roof will occur Saturday Oct 12, after 8am. The noise level is expected to be minor.

      Dining Hall Project at Lone Mountain Main

      Micropiles

      Drilling micro piles in the Pavilion/Lawn area continues and is expected to be complete by the end of next week. Saw cutting and shallow excavation at the site for installation of grade beams and other foundation work will begin after the micro piles are completed.

      Earthwork

      Preparation of the Pavilion site for grade beams & foundation will involve saw-cutting the existing retaining wall to grade, digging for new footings, and excavation of about 1 foot of soil. Noise from this activity will periodically affect nearby classrooms and offices. Offices and classrooms adjacent to the lawn may also be affected by dust and exhaust from the equipment.

      The schedule exterior work is: Monday through Saturday 8am - 7pm.

      Interior work

      Installation of mechanical, electrical, and plumbing infrastructure into the existing concrete foundation requires saw-cutting and limited excavation. Work will continue for installation of rebar to reinforce existing structural walls.

      Sawcutting and then excavation of shear wall footings is expected to begin after Oct 16. This work will be noisy and disruptive. I will send a notice of specific dates when known.

      Roof

      New openings in the roof for venting requirements have been completed. Temporary water proofing for those openings is in place. The roofers identified some spots on the west side of the chapel roof that may require minor repairs. Scope and dates to be determined.

      Water Shutoff - postponed. Looking at less intrusive alternatives. Details to follow when they’re set.


      10/04/2019 Update:

      Lone Mountain Residence Hall

      Scaffolding is being erected along the east side of the East Building (west of Ewing Terrace property lines). The scaffolding will be in place along the length of the east side and up to two to three stories.

      The work will take several weeks and will involve some noise.

      Framing on the East Building continues, with the third story of the East Building now visible from Turk.

      Trenching for the installation of storm drains will begin on the West Building on Saturday Oct 5, starting about 8am.

      Contractor will apply shotcrete to the West Building stair. Shotcrete is sprayed concrete conveyed through a hose at a high velocity onto a surface. The process can be noisy. Projected for Friday Oct 4 through Friday Oct 11.

      War Memorial Gym/Sobrato Center

      Drilling for micropiles is underway and is expected continue through next week followed by excavation and shoring. Excavation is expected to begin next week and will last about a week. There will be minor truck traffic for off haul; 1 -2 trucks per day. The noise level is expected to be moderate.

      A "shrink-wrap” barrier is installed on the exposed west side of the Gym building next week.

      Dining Hall Project at Lone Mountain Main

      Micropiles

      Drilling micro piles in the Pavilion/Lawn area continues and is expected to be completed by Oct 16. The process has been delayed due to equipment issues. The schedule for micro pile drilling through Oct 16 is: Monday through Saturday 8am - 7pm. Noise from the drilling may periodically affect nearby classrooms and offices. Offices and classrooms adjacent to the lawn may also be affected by dust and exhaust from the equipment.

      Interior work

      Reinforcing the existing concrete walls and foundations continues. Coring to install dowels for reinforcing structural wall should by complete by Oct 4 and will be followed by installation of rebar, which is moderately noisy work to those adjacent to the site.

      Roof

      New opening were made in the roof for venting requirements. Sealing and water proofing those openings is complete today, Oct 4.


      Mid October - Mid November

      Starting in about 2 weeks, activity at the interior site as well as the Pavilion area will be noisy and disruptive to adjacent offices, classrooms, and buildings

      Pavilion:

      Once micro piles are completed, the site will be prepared for grade beams & foundation which will involve saw-cutting the existing retaining wall to grade, digging for new footings, and excavation of about 1 foot of soil.

      Interior:

      Installation of mechanical, electrical, and plumbing infrastructure into the existing concrete foundation will require saw-cutting and limited excavation. Work will continue to reinforce existing structural walls.

      It will be noisy.

      Future updates will have more specific dates, when known.


      9/27/2019 Update:

      Lone Mountain Residence Hall

      Framing on the East Building continues, with the third story of the east building now visible from Turk. At the same time, the installation of wet and dry utilities is also underway.

      Concrete mat pours

      Mat pours are currently scheduled for Saturday Saturday, Sept 28. The mat pours will be a large pour and will start at 7 am. The truck volume will be high throughout the day.

      Scaffolding

      Scaffolding will be erected along the east side of the east building (west of Ewing Terrace property lines) starting approximately October 4.

      War Memorial Gym/Sobrato Center

      Earthwork & Shoring, Micropiles

      Drilling for micropiles is expected to begin on Wednesday of next week followed by excavation and shoring. The noise level is expected to be moderate.

      A "shrink-wrap” barrier will be installed on the exposed west side of the Gym building next week.

      Equipment Delivery

      Video boards have been delivered and installed.

      Dining Hall Project at Lone Mountain Main

      Interior work

      Reinforcing the existing concrete walls and foundations continues. Coring is expected to be completed by Oct 4.

      Micropiles

      Drilling micro piles in the Pavilion/Lawn area continues and is expected to be completed by Oct 5. The schedule for micropile drilling for this week is: Monday through Saturday 8am - 7pm. Noise from the drilling may periodically affect nearby classrooms and offices. Offices and classrooms adjacent to the lawn may also be affected by dust and exhaust from the equipment.

      All dates are best estimates and may change without notice.


      9/18/2019 Update:

      Dining Hall Project at Lone Mountain Main

      The installation of micro piles in the Pavilion/Lawn area is on-going. Earlier this week, the contractor found that their standard equipment cannot penetrate the bedrock, approximately 30ft below grade.

      Starting tomorrow morning Thursday, Sept 19, the contractor will be using a drill hammer at depth to break into bedrock. Noise from the drill hammer may periodically affect nearby classrooms, offices and residence rooms. Offices, classrooms, and residence rooms near the lawn may also be affected by dust and exhaust from the equipment.

      The schedule for micropile drilling for this week is Monday through Saturday 8am - 7pm.

      Lone Mountain Residence Hall

      Concrete mat pours

      Mat pours are currently scheduled for Saturday, Sept 21, Tuesday, Sept 24 and Saturday, Sept 28.

      The September 21 and September 28 mat pours will be large pours and will start at 6am. The truck volume will be high throughout the day.

      The contractor will be working this Saturday, Sept 21 near Turk and Tamalpais trenching and backfilling the sidewalk near the east entrance to the worksite.


      9/16/2019 Update:

      Lone Mountain Residence Hall

      Framing on the East Building continues, with the second story of the east building visible from Turk. At the same time, installation of wet and dry utilities is also underway.

      Concrete mat pours

      Mat pours are currently scheduled for Saturday, Sept 21, Tuesday, Sept 24 and Saturday, Sept 28. The September 21 and September 28 mat pours will be large pours and will start at 6am. Truck volume will be high throughout the day.

      War Memorial Gym/Sobrato Center

      Demolition

      Demolition of the west wall is War Memorial gym is complete.

      Earthwork & Shoring, Micropiles

      Drilling for micropiles is expected to begin on Wednesday of next week followed by excavation and shoring. The noise level is expected to be moderate.

      Equipment Delivery

      Video boards for the gymnasium interior are expected to be delivered by tractor trailer on Monday morning at 8am. The truck will occupy the loading zone in front of the gym. The process is expected to take less than a day.

      Dining Hall Project at Lone Mountain Main

      Interior work

      Work is underway to reinforce the existing concrete walls and foundations in preparation for the new design. The first step is to prepare the walls for additional reinforcement by using ‘coring’ equipment, which can be noisy for spaces adjacent to the work site. The process is expected to continue for several weeks.

      Carpentry

      Part of the process for reinforcing the walls will be to fabricate wooden forms for the concrete reinforcement. The forms are being built in the LMM back lot and involves general carpentry; hammer guns, power saws, etc.

      Micropiles

      Drilling micro piles in the Pavilion/Lawn area is continuing. The schedule for micro pile drilling for this week is: Monday through Saturday 8am - 7pm. Noise from the drilling may periodically affect nearby classrooms and offices. Offices and classrooms adjacent to the lawn may also be affected by dust and exhaust from the equipment.

      Lower Campus

      Crane Delivery: a crane is scheduled to be delivered to the lower campus during the morning of Saturday September 21.

      All dates are best estimates and may change without notice.


      9/11/2019 Update:

      Lone Mountain Residence Hall

      Interior work

      Coring is underway in the former Wolf & Kettle area. This is the first step preparing the walls for additional rebar & reinforcement. The equipment used can be heard in some areas adjacent to the project but is significantly quieter than the prior jackhammering. This process will continue for several weeks.


      9/6/2019 Update:

      Lone Mountain Residence Hall

      Early Morning Equipment Pick Up

      A large piece of equipment is scheduled to be picked up Monday, September 9 at approximately 4:30 a.m.  As with other larger equipment, the size of the truck required for hauling the equipment triggers travel time restrictions required by the City of San Francisco.  Contractors will make every effort to minimize noise associated with the pickup . We apologize for the disruption and inconvenience.


      9/5/2019 Update:

      Please find our construction update below.

      Given the volume of activity on campus, this and future updates will include information for the Res Hall project along with War Memorial Gym and the Lone Mountain Dining Hall.

      Lone Mountain Residence Hall

      Framing is underway, with the second story of the east building visible from Turk. At the same time, installation of wet and dry utilities is also underway.

      Mat pours

      Concrete map pours are currently scheduled for Saturday, Sept 21, Tuesday, Sept 24 and Saturday, Sept 28.

      The September 21 mat pour is a major pour and will start at 6am. Truck volume will be high throughout the day.

      Laydown Area

      The area at the southwest corner of the site, near the current temporary trash facility, is being converted to a construction lay down area and temp parking for workers and subcontractors.

      War Memorial Gym/Sobrato Center

      Demolition

      Demolition of the west wall is War Memorial gym is complete except for a small section at the building’s southwest corner.

      Earthwork & Shoring

      Excavation and shoring on the west side of the building is ongoing.

      Micropiles

      Drilling for micropiles is expected to begin next week. The noise level is expected to be moderate.

      Equipment Delivery

      Video boards for the gymnasium interior are expected to be delivered by tractor trailer next week. The truck will occupy the loading zone in front of the gym. The process is expected to take less than a day.

      Work hours

      In general, work hours for this project are 8am - 4pm Monday- Friday. Workers may be onsite before 8am but no noisy work is allowed.

      We will send advance notice for extended hours or work on Saturdays on the occasions when it is required.

      Dining Hall Project at Lone Mountain Main

      Interior work

      The next phase in the interior portion of the project is to reinforce the existing concrete walls and foundations in preparation for the new design.

      The first step will be preparing the walls for additional reinforcement by using ‘coring’ equipment. The process is expected to start the week of 9/919, pending delivery of equipment, and will continue for several weeks.

      Carpentry

      Part of the process for reinforcing the walls will be to fabricate wooden forms for the concrete reinforcement. The forms will be built in the LMM back lot and will involve general carpentry; hammer guns, power saws, etc.

      Micropiles

      Drilling micro piles in the Pavilion/Lawn area will begin Tuesday 9/4.

      Noise from the drilling may periodically affect nearby classrooms and offices. Offices and classrooms adjacent to the lawn may also be affected by dust and exhaust from the equipment.

      The process will take about 4 weeks.

      Roof curbs

      Workers will curb and seal off the roof openings above LMM265 and should be complete by Wednesday. The noise level is relatively minor.

      Work hours

      In general, work hours for this project are 8am - 4pm Monday- Friday. Workers may be onsite before 8am but no noisy work is allowed.

      We will send advance notice for extended hours or work on Saturdays on the occasions when it is required.

      All dates are best estimates and may change without notice.


      8/9/2019 Update:

      This update includes information for two projects on campus: Upper Campus Res Hall and War Memorial Gym/Sobrato Center

      RES HALL, UPPER CAMPUS

      CONCRETE MAT POUR DATES

      A concrete pour is scheduled for Tuesday August 20. Work is expected to begin at 7am and should be completed by the afternoon.

      FRAMING

      As a general note, the project has progressed to the framing stage, starting with the east building. Wood framing sections are fabricated in northern California, delivered to campus, and erected on site.

      WAR MEMORIAL GYM/SOBRATO CENTER

      This is the first update on this project through this email/web distribution. A project description is outlined further below.

      PROJECT DESCRIPTION

      Alterations to War Memorial Gym/Sobrato include improvements to the lobbies and reconfiguration of the west side/upper lobby at the southwest corner of the building. The building’s main

      The alterations will reduce seating capacity by about 650 seats. The existing entrance on Golden Gate will be converted to emergency egress only.

      DEMOLITION

      The project has been underway since May 2020. The perimeter fence has been installed and recent activity has included interior demolition and exterior drilling for shoring beams.

      Demolition of the exterior west wall will be on Monday, August 20 and continue through the week, during regular working hours.

      This work will be loud. We apologize for any disruption and inconvenience.


      7/17/2019 Update:

      CONCRETE MAT POUR DATES

      Concrete mat pours are scheduled for Friday, July 19 and Saturday, July 20. Work is expected to occur between 6am & 9pm.

      TOWER CRANE DELIVERY

      The tower crane delivery date has been changed from Wednesday, July 17 to Tuesday, July 23. The size of the equipment and the extent of the installation process require an early delivery time, approximately 6am. The work to assemble the crane will continue throughout the day.

      TURK TRENCHING

      Trenching work on Turk to connect utilities to the residence hall site is expected to be substantially complete by 7/29.

      Please note: Dates in the schedule are contingent on a variety of variables and are subject to change.


      6/30/2019 Update:

      CONCRETE MAT POUR DATES: UPDATES & CHANGES

      The next concrete mat pours are scheduled for Tuesday, July 9; Friday, July 19; and Saturday, July 20. All are expected to occur between 6am & 9pm.

      The mat pour scheduled on Saturday July 13 is cancelled.

      TOWER CRANE DELIVERY

      A tower crane is scheduled to be delivered to the site on Wednesday, July 17.

      TURK TRENCHING

      Work on connecting utilities to the residence hall site will require trenching on Turk, near the east construction gate. The work is currently scheduled 7/8 - 7/18

      Please note: Dates in the schedule are contingent on a variety of variables and are subject to change.


      6/14/2019 Update:

      CONCRETE MAT POUR DATES CHANGED

      The concrete mat pours scheduled for Saturday, June 15, 6 am - 9 pm and Thursday, June 27 6 am - 8 pm has been changed. The anticipated reschedule dates are Tuesday, July 9, 7 am - 8 pm and Saturday, July 13, 6 am - 9 pm.


      5/17/2019 Update:

      CONCRETE MAT POUR POSTPONED

      The concrete mat pours scheduled for Saturday, May 18, 6 am - 9 pm is postponed. The anticipated reschedule date is Saturday, June 1, 6 am - 9 pm.

      EARLY MORNING EQUIPMENT PICKUP

      Two large rigs are scheduled for removal next Friday, May 24 at 4 am. As with other larger equipment, the size of the trucks required for hauling such equipment triggers travel time restrictions required by the City of San Francisco. Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be noise and back-up safety beacons. We apologize for the disruption and inconvenience.


      5/13/2019 Update:

      Concrete Mat Pour

      Construction at the USF Res Hall site is entering a new phase: Mass excavation for the Lone Mountain residence hall is nearly complete. The next major activity will be the installation of the mat slab foundations and podiums for the east and west structures.

      The mat pour process is lengthy, involving equipment set up, delivery of concrete by trucks throughout the day, pumping, delivery, finishing, curing, and break-down. Separate pour dates are required to allow each slab section to cure before further work is done. We estimate the most impactful part of this phases will occur over 11 days scheduled over the next few months.

      Concrete mat pours are an unavoidably disruptive and noisy process. The size of a foundation slab requires continuous delivery of concrete to ensure the integrity of the structure. Once started, the pour for each slab must continue until completion. The time required for each slab will vary between 9 and 15 hours in a given day, depending on the volume of concrete required.

      Devcon and USF have been working together for several months to seek ways to minimize disruption to our neighbors. On Tuesday, April 16, we met with neighbors from University Terrace and Ewing Terrace Associations to look at alternatives:  should we schedule fewer days and longer hours or plan for many more days and shorter hours?  We also asked for input on whether or not the pours should happen on weekdays or on Saturdays. The consensus from the neighborhood representatives was to schedule fewer days for longer hours, on Saturdays when possible.

      Please see the chart below for the proposed pour dates. Devcon has submitted an application to the City for a permit to work beyond the City’s normal construction hours (7 am - 8 pm).

      The first pour date is this Saturday, May 18, starting at 6 am. All dates are subject to change depending on conditions; for example, there is a prediction for rain this Saturday, May 18 which may affect the schedule.

      We will make every effort to minimize the impact of this process, however, we realize that it will be challenging. Devcon will retain professional traffic control crews to manage traffic, pedestrians, and the concrete truck activity. We will do our best to minimize further disruption. If you have any questions, please contact us at neighbor@usfca.edu.

      Pour Date Start time Estimated Completion
      18-May Saturday 6 am 9 pm
      25-May Saturday 6 am 9 pm
      15-Jun Saturday 6 am 9 pm
      27-Jun Thursday 7 am 8 pm
      17-Jul Wednesday 7 am 8 pm
      20-Jul Saturday 7 am 8 pm
      27-Jul Saturday 7 am 5 pm
      3-Aug Saturday 7 am 4 pm
      13-Aug Tuesday 7 am 5 pm
      19-Aug Monday 7 am 4 pm
      29-Aug Thursday 7 am 4 pm

      5/7/2019 Update:

      Early Morning Equipment Pickup

      A crane broke down on Monday and could not be repaired onsite. A replacement crane will be delivered on Wednesday 5/8/2019 at approximately 4am. As with other larger equipment, the size of the truck required for hauling the equipment triggers travel time restrictions required by the City of San Francisco. Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise. We apologize for the disruption and inconvenience.


      4/8/2019 Update:

      Dynamic Load Testing of Auger Cast Piles

      A series of dynamic tests are scheduled to be applied to the auger cast piles of the west building on Thursday and possibly Friday this week April 11 and 12. Dynamic load testing is a method to assess a pile's bearing capacity by applying a dynamic load, i.e. a falling weight, to the pile head and testing the effects on the pile.

      Five piles will be tested. Each pile will be hit 3 times. It is possible that the impact from a hit might be felt at some distance from the location of the test pile.

      Testing on Thursday is expected to go from 9am-6pm. If needed, Friday testing will start at 9 am and could go until 6 pm.


      4/2/2019 Update:

      Early Morning Equipment Pickup

      A large piece of equipment is scheduled to be delivered on Tuesday, April 2 at approximately 4:00 a.m. As with other larger equipment, the size of the truck required for hauling the equipment triggers travels time restrictions required by the City of San Francisco. Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise. We apologize for the disruption and inconvenience.

      Work on Water Lines

      Work on campus water lines and connections to City services on Turk will continues. The work on Turk will at times be noisy and will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving.

      Excavation & Off-Hauling

      Excavation at site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues periodically. Flagmen are positioned at the job site gates and at the middle spur of Lone Mountain. Truck bosses manage truck traffic to ensure truckers follow prescribed routes.  Please use caution at the perimeter of the job site. The mass excavation phase is anticipated to be complete by mid April.

      Storm Water Infiltration Basin

      Excavation and installation of a storm water infiltration basin is underway. The infiltration basin is to be located on the east end of the Lone Mountain law within the construction fence. Work will involve excavation, shoring, and grading and at times may be noisy.
      The infiltration basin is an element of the USF Storm Water Control Plan required by the San Francisco Public Utilities Commission. Once the residence hall project is complete, the lawn area will be returned to its original condition.


      3/14/2019 Update:

      Early Morning Equipment Pickup

      A large piece of equipment is scheduled to be delivered on Saturday, March 16 at approximately 4:00 a.m. As with other larger equipment, the size of the truck required for hauling the equipment triggers travels time restrictions required by the City of San Francisco. Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise. We apologize for the disruption and inconvenience.

      Work on Water Lines

      Work on campus water lines and connections to City services on Turk will continue into next week. The work on Turk will at times be noisy and will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving.

      Excavation & Off-Hauling

      Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues periodically. Flagmen are positioned at the job site gates and at the middle spur of Lone Mountain. Truck bosses manage truck traffic to ensure truckers follow prescribed routes. Please use caution at the perimeter of the job site. The mass excavation phase is anticipated to be complete by mid-April.

      Storm Water Infiltration Basin

      Excavation and installation of a stormwater infiltration basin will begin the week of March 18. The infiltration basin is to be located on the east end of the Lone Mountain law within the construction fence. Work will involve excavation, shoring, and grading and at times may be noisy.

      The infiltration basin is an element of the USF Storm Water Control Plan required by the San Francisco Public Utilities Commission. Once the residence hall project is complete, the lawn area will be returned to its original condition.


      3/5/2019 Update:

      Early Morning Equipment Pickup

      A large piece of equipment is scheduled to be picked up on Friday, March 8 at approximately 4:00 a.m. As with other larger equipment, the size of the truck required for hauling the equipment triggers travels time restrictions required by the City of San Francisco. Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise. We apologize for the disruption and inconvenience.


      2/19/2019 Update:

      Early Morning Equipment Pickup

      The equipment delivery scheduled for early morning on Tuesday, February 19 has been changed to Thursday, February 21 at 4:30 am.


      2/14/2019 Update:

      Early Morning Equipment Pickup

      A large piece of equipment is scheduled to be delivered on Tuesday, February 19 at approximately 4:00 a.m.  As with other larger equipment, the size of the truck required for hauling the equipment triggers travels time restrictions required by the City of San Francisco.  Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise. We apologize for the disruption and inconvenience.

      Work on Water Lines

      Work on campus water lines and connections to City services on Turk is scheduled to begin this week, weather allowing. The work on Turk will at times be noisy and will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. We will post the work dates when they are finalized.

      Excavation & Off-Hauling

      Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues. Flagmen are positioned at the job site gates and at the middle spur of Lone Mountain. Truck bosses manage truck traffic to ensure truckers follow prescribed routes.  Please use caution at the perimeter of the job site.


    • Kaiser Vaccine Clinic at USF Koret Rec Center

      • Kaiser continues to host a vaccine clinic at the Swig Pavilion in Koret

      Covid-19Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance


      4/12/2021 Updates:

      All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

      Lone Mountain Residence Hall

  • July 19- July 23: Office/Classroom/Study room furniture; 2 trucks/day. ETA 8:30am
  • July 26 - July 30 Furniture for res hall lounges.  8:30- 4:30pm. Duration: 2-3 days. 3 trucks (# of trucks per day TBD)
  • Landscaping work for area east of Drive on-going. There will be some truck activity next week involving delivery of soil and plants.
  • On-going interior punch list
  • On-going interior work to prepare for opening.

2/14/2019 Update:

Early Morning Equipment Pickup

A large piece of equipment is scheduled to be delivered on Tuesday, February 19 at approximately 4:00 a.m. As with other larger equipment, the size of the truck required for hauling the equipment triggers travels time restrictions required by the City of San Francisco. Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise. We apologize for the disruption and inconvenience.

Work on Water Lines

Work on campus water lines and connections to City services on Turk is scheduled to begin this week, weather allowing. The work on Turk will at times be noisy and will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. We will post the work dates when they are finalized.

Excavation & Off-Hauling

Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues. Flagmen are positioned at the job site gates and at the middle spur of Lone Mountain. Truck bosses manage truck traffic to ensure truckers follow prescribed routes. Please use caution at the perimeter of the job site. Early Morning Equipment Pickup a large piece of equipment is scheduled to be picked up Thursday, February 7 at approximately 4:00 a.m. As with other larger equipment, the size of the truck required for hauling the equipment triggers travels time restrictions required by the City of San Francisco. Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise. We apologize for the disruption and inconvenience.

Work on Water Lines

The start date for work on campus water lines and connections to City services on Turk has been pushed to February. The work on Turk will at times be noisy and will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. We will post the work dates when they are finalized.


2/6/2019 Update:

Excavation & Off-Hauling

Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues. Flagmen are positioned at the job site gates. In particular, Thursday and Friday (2/7&8/19) @ 7:00 am off haul soil out of the construction site’s west gate will begin, the middle spur of Lone Mountain Drive will begin. Additional flaggers will be provided.


1/30/2019 Update:

Early Morning Equipment Pickup

A large piece of equipment is scheduled to be picked up Thursday, January 31 at approximately 4:00 a.m.  As with other larger equipment, the size of the truck required for hauling the equipment triggers travels time restrictions required by the City of San Francisco.  Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise.  We apologize for the disruption and inconvenience.

Work on Water Lines

The start date for work on campus water lines and connections to City services on Turk has been pushed to February. The work on Turk will at times be noisy and will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. We will post the work dates when they are finalized. 

Excavation & Off-Hauling

Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues. Flagmen are positioned at the job site gates. Two truck bosses will manage truck traffic to ensure truckers follow prescribed routes. 


1/17/2019 Update:

Work on Water Lines

The work on campus water lines and connections to City services on Turk will start January 19. The work on Turk will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. Expected end date is January  31.

Excavation & Off-Hauling

Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues. Flagmen are positioned at the job site gates. Two truck bosses will manage truck traffic to ensure truckers follow prescribed routes.

Holiday Schedule

January 18, MLK Holiday - Contractors will be working at the site.

February 18, President’s Day - No work at the site is planned.


12/19/2018 Update:

Work on Water Lines

The work on campus water lines and connections to City services on Turk, originally scheduled to start this week, has been postponed until January. The work on Turk will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. We will share the work dates with you when they are finalized. 

Schedule

USF recently made the decision to change the construction start time to 7 am, M-F, and 8 am Saturdays to allow more trucks to work to be performed on a daily basis and to meet the overall schedule. Currently, trucks off haul excavated earth to a site two to three hours away from campus. The expanded timeframe will allow significantly more loads to be removed from the site on a daily basis. For example, a truck will be able to make three trips daily instead of two; multiply that by 30 or more trucks daily and the progress is significant. Ultimately, this should reduce the total number of days required to complete the excavation phase.  While we understand and regret the disruption, our intent is to potentially shorten the overall duration of the project. 

Holiday Schedule

Dec 23, 24, 25 - No work on site

Dec 26-29  - Regular work hours

Dec 30,31/Jan 1 - No work on site

Jan 2 - 5 - Regular work hours


12/07/2018 Update:

Excavation & Off-Hauling

Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues. Flagmen are positioned at the job site gates. Two truck bosses will manage truck traffic to ensure truckers follow prescribed routes. Overall excavation work is expected to last about 5 months.

Work on Water Lines

Starting on Monday, December 10, contractors will work on campus water lines and connections to City services. Work on the campus water lines will be on December 10 and 11.   The work will move out to connections on Turk after the campus work is complete, specific start date TBD. The work on Turk will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. This work will be noisy, including the use of jackhammers. We apologize in advance for any disruption. 

We encourage everyone to use extra caution at all times when walking or driving near the job site.


11/21/18 Update: 

There will be no construction activity over Thanksgiving weekend,  11/22 -25.


11/09/2018 Update:

Excavation & Shoring

Excavation at the site continues including soil stabilization, shoring, leveling, grading and off hauling. During off-hauling flagmen will be positioned at the job site gates. Two truck bosses manage truck traffic to ensure truckers follow prescribed routes.  Overall excavation work is expected to last about 5 months. 

There will be some drilling and shoring work on the site on Saturday, November 10, no off hauling is expected. 

We encourage everyone to use extra caution at all times when walking or driving near the job site gates.

Tree placement, Northeast corner

Seven Deodar Cedars (60inch boxes) were put in place on the slope on the northeast corner of the site. The landscape contractor is completing the planting process. 

East Slope grubbing 

The clusters of dead trees in the middle of the slope between the construction site and the Ewing Terrace property line have not yet been removed. The dead trees must be removed in anticipation of future landscaping. The contractor plans to start removing the dead trees as soon as shoring work in that area is complete. We have asked them to leave as much greenery on the slope as possible. Any open ground left after removal will be covered by wattles and other material to prevent erosion. 


10/31/2018 Update:

Excavation & Shoring

Excavation at the site continues including soil stabilization, shoring, leveling, grading and off hauling. During off-hauling flagmen will be positioned at the job site gates. Two truck bosses manage truck traffic to ensure truckers follow prescribed routes and do not stack in line on Turk. Overall excavation work is expected to last about 5 months. There will be off hauling on Saturday, November 2. 

East Slope grubbing 

There are a couple of clusters of dead trees in the middle of the slope between the construction site and the Ewing Terrace property line. The dead trees must be removed in anticipation of future landscaping. Because access to that area with large equipment won’t be possible after excavation, the contractor plans to start removing the dead trees starting Thursday, Nov 1. We have asked them to leave as much greenery in place as possible. Any open ground left after removal will be covered by wattles and other material to prevent erosion. 

Tree placement, Northeast corner

For the same reason as above, we plan to plant seven Deodar Cedars (60inch boxes) downhill from the northeast corner of the site. The contractor will start digging the holes for the trees tomorrow, the process will take several days and will involve some noise. Because of the size of the boxes, a crane is scheduled for Wed Nov 7 to put them in place. 


10/25/18 Update:

Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling will begin Friday, October 26 which will result in an increase in truck traffic in and out of the site. Flagmen will be positioned at the job site gates. Two truck bosses will manage truck traffic to ensure truckers follow prescribed routes. Overall excavation work is expected to last about 5 months.

We encourage everyone to use extra caution at all times when walking or driving near the job site gates.


10/22/18 Update:

An excavator is scheduled for delivery Tuesday, October 23 at approximately 4:30 a.m.  As with other larger equipment, the size of the job trailer triggers travel time restrictions required by the City of San Francisco.  Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise.  We apologize for the disruption and inconvenience.


10/18/18 Update:

One trailer is scheduled for pick up Monday, October 22 at approximately 6:30 a.m. As with some larger equipment, the size of the job trailer triggers travel time restrictions required by the City of San Francisco.  Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise.  We apologize for any disruption and inconvenience.


10/16/18 Update:

One of the large rigs scheduled for delivery on Tuesday, October 16 was not delivered. Delivery has been rescheduled for Thursday, Oct 18 at approximately 4:00 a.m.

As with the other large equipment, the size of the equipment triggers travel time restrictions required by the City of San Francisco. The contractors will make every effort to minimize the noise associated with this delivery however it is likely to be noisy. We apologize in advance for any disruption and inconvenience. 


10/15/18 Update:

Two large rigs are scheduled to be delivered to the Lone Mountain Residence Hall construction site on Tuesday October 16. The size of the equipment requires hauling by oversize trucks which trigger travel time restrictions imposed by the City of San Francisco.  Accordingly, the trucks will arrive at the construction site entrance on Turk at approximately 4:00 a.m.  The contractors will make every effort to minimize the noise associated with this delivery however it is likely to be noisy and apologize in advance for any disruption and inconvenience. 


10/4/18 Update:

  • Thursday, Oct 5: Paving of temporary road on lawn area through Oct 6. Work will involve the application of asphalt on the temporary roadway. 
  • Monday, Oct 8: Excavation at the site is scheduled to begin on Monday, Oct 8.  Early phases of the process involve soil stabilization, shoring, leveling, and grading.  Some of the shoring work will be noisy. Continued delivery of shoring beams to the site. As the work proceeds, truck traffic in and out of the site will increase. A flagman will be in place at the job site gate but we encourage everyone to use extra caution at all times around the site. A ‘truck boss’ is assigned to the site to manage truck traffic and ensure truckers follow prescribed routes. Overall excavation work is expected to last about 5 months.
  • Wednesday, Oct 11: Deliver & install Devcon construction trailers. 

All dates are schedule estimates and may change without notice. 


9/25/18 Update: 

  • Sept 27 - 28: The temporary access road is scheduled to be completed and paved on. 
  • The construction site is cleared and prepared for excavation and shoring. The next phase at the site will involve preparation for earthwork and shoring.  
  • October 1: Construction activities will pick up significantly beginning the week of.
  • Delivery of two trailers (for construction management) is scheduled for early October. 
  • 10/1 - 10/19: Leveling and rough grading at the site is scheduled for.
  • 10/8 -10/19: Delivery of shoring beams is scheduled between.
  • Mass excavation is scheduled to begin in late October and is expected to take about five months. We will share details about these activities as the schedule develops. 
  • All of this work will involve increased truck activity both for deliveries and for off-hauling. Flagmen will be in place at the job site gate but we encourage everyone to use extra caution at all times around the site.

All dates are schedule estimates and may change without notice. 


9/13/18 Update:

work will begin on building a temporary roadway from Turk to the construction site, roughly near the Roselyn Terrace/Turk intersection. This temporary road will be used primarily by trucks off-hauling soils from the site. As with other construction activities impacting the eastern portion of the Lone Mountain lawn, the changes are temporary. The lawn will be returned to its original condition when the project is completed.  


8/31/18 Update:

Two drill rigs are scheduled to be delivered to the Lone Mtn Residence Hall construction site during the week of September 3. The first drill rig, the smaller of the two, will be delivered around noon on Tuesday, Sept 4. The Contractor will manage vehicle and pedestrian traffic around the immediate area. 

The second delivery is a large drill rig, scheduled for delivery to the site on Wednesday, Sept 5. The size of the drill rig requires hauling by an oversize truck, the dimensions of which trigger travel time restrictions imposed by the City of San Francisco. Specifically, this truck may only travel on City streets before 6 am.  Accordingly, the truck and drill rig will arrive at the construction site entrance on Turk at approximately 4:00 a.m.  The crew will take approximately 1/2 hour to unload the rig and then will drive away.  The contractors will make every effort to minimize the noise associated with this delivery however we acknowledge that it is likely to be noisy and apologize in advance for any disruption and inconvenience. 


8/21/18 Update:

Tree removal will begin on 8/21 at the Res Hall site. The work will involve some heavy equipment and chainsaw noise.


8/4/18 Update:

There will be some work at the Lone Mountain lawn site on Saturday, August 4. A team of carpenters will be building forms for a concrete pour. The work is scheduled to start at 9am


8/3/18 Update:

Site preparation and demolition activities will continue during the week of Aug 6. The schedule includes constructing a perimeter fence around the restricted construction area which borders the sidewalk along Turk, the demolition of Underhill which will involve heavy equipment, and continued site grubbing and tree removal.  


8/1/18 Update:

We are expecting to start tree removal & site “grubbing” at the Residence Hall site late this week or early next. The tree work will be noisy.


7/16/18 Update:

On Wednesday, July 18, the general contractor will fly a drone over the proposed Res Hall construction site during business hours in order to photo document current conditions. The process will take about a half hour.


6/20/18 Update: Construction Site Closure

Beginning Monday, June 25, the following parking lots, rampways, and pedestrian pathways will close in preparation for construction of the new Sobrato Residential Complex:

  • Loyola Parking Lot 
  • Lone Mountain Drive, east of Loyola House driveway entrance 
  • Pedestrian Path from Loyola Village to Turk Blvd 
  • Underhill Tennis Courts 
  • In preparation for construction, the north-west and west Lone Mountain parking lots will be closed beginning May 21, 2018. We anticipate the Lone Mountain east parking lot and driveway to close this summer.
  • Informational signage will be posted within Lone Mountain main to direct individuals to the new locations of displaced staff. 
  • The Outtakes Cafe kitchen facility will be closed beginning May 21, 2018. The dining area will remain open as a gathering space/lounge.
  • Beginning May 21, the Lone Mountain east parking lot and east driveway will be closed.