Capital Projects Updates

UPDATE 11/23/2022:

 
All dates below are best estimates, subject to weather and other external impacts, and may change without notice.

Toler Hall/Malloy Hall 

Replacement of Malloy heating system piping to repair leak.  Duration of project through Dec 30.  Aspects of this work will be noisy, including drilling and anchoring process. This repair does not affect Toler's or McLaren's heating system. 
  • Nov 28- Dec 2  Install piping Toler wall
  • Dec 5 - 8  Begin underground digging

Lower Campus Steamline Project

No work on site Thursday 11/24/22
Saturday work begins on 10/29 through December. Workers may arrive on site early; noisy work may begin after 8am; work stops 1:30pm.
  • Area 1:  Path by SW Kalmanovitz Hall door                      
    • Late November (2-3 days) - Install pipe                                  
  • Area 2: The main path between Welch Field and Gleeson Lawn
    • Late November - Backfill
  • Area 3:  Main east/west path in front of McLaren steps
    • Work delayed until Christmas break
  • Area 4:  Main path going north/south between Gleeson Library and Harney
    • Late November - Backfill
  • Excavation activities will involve trenching and jackhammering, which will sometimes be noisy.
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas intersecting foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.
  • Please use caution in the area. Please respect all signs and instructions.
  • Expected completion: mid November

Malloy Basketball Practice Facility/War Memorial Gym

No work on site Thursday - Friday 11/24, 11/25
  • Late October - December: Ongoing delivery of steel, 3-4 trucks/day , structural steel installation using crane. 
  • Installation of decking and roofing follows steel framing in sequence.
  • Hayes Healy Parking Lot Closed - All levels of the HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Viaduct, 330 Parker Ave

No work on site Thursday - Friday 11/24, 11/25
Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • OngoingPiers: bearing repairs, prep hydraulic hoistsinstallation of structural lock-up devices

Events etc:

  • Nov 30:  Basketball 7pm: 2pm Men vs Little Rock
  • Dec 7. Men’s Basketball 7:30 pm,vs Merrimack
  • Dec 19. Men’s Basketball 7:30 pm,vs UT Arlington
  • Dec 21. Men’s Basketball 7:00 pm vs Arizona State, TV trucks will be on site 
  • Jan 2.  Electrical Shutdown - all buildings on the Lower Campus. 7am - 3pm

Covid-19 

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing.

 


UPDATE 11/17/2022:

All dates below are best estimates, subject to weather and other external impacts, and may change without notice.

Toler Hall/Malloy Hall 

Week of November 21: Replacement of Malloy heating system piping to repair leak. Work is expected to begin Monday morning at 9AM. Duration of project TBD.  Aspects of this work will be noisy, including drilling and anchoring process. This repair does not affect Toler's or McLaren's heating system. 
 

Lower Campus Steamline Project

Saturday work begins on 10/29 through December. Workers may arrive on site early; noisy work may begin after 8am; work stops 1:30pm.
Week of November 21 (estimate) Saw cutting at walkway near NE corner of St Ignatius Church. Loud noise at times. 
  • Area 1:  Path by SW Kalmanovitz Hall door                      
    • Late November (2-3 days) - Install pipe                                  
  • Area 2: The main path between Welch Field and Gleeson Lawn
    • Late November - Backfill
  • Area 3:  Main east/west path in front of McLaren steps
    • Work delayed until Christmas break
  • Area 4:  Main path going north/south between Gleeson Library and Harney
    • Late November - Backfill
  • Excavation activities will involve trenching and jackhammering, which will sometimes be noisy.
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas intersecting foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.
  • Please use caution in the area. Please respect all signs and instructions.
  • Expected completion: mid November
Malloy Basketball Practice Facility/War Memorial Gym
  • Late October - December: Ongoing delivery of steel, 3-4 trucks/day , structural steel installation using crane. 
  • Installation of decking and roofing follows steel framing in sequence.
  • Hayes Healy Parking Lot Closed - All levels of the HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • OngoingPiers: bearing repairs, prep hydraulic hoistsinstallation of structural lock-up devices

Events etc:

  • Nov 30:  Basketball 7pm: 2pm Men vs Little Rock
  • Dec 7. Men’s Basketball 7:30 pm,vs Merrimack
  • Dec 19. Men’s Basketball 7:30 pm,vs UT Arlington
  • Dec 21. Men’s Basketball 7:00 pm vs Arizona State, TV trucks will be on site 
  • Jan 2.  Electrical Shutdown - all buildings on the Lower Campus. 7am - 3pm

Covid-19 

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing.
 

UPDATE 11/11/2022:

All dates below are best estimates, subject to weather and other external impacts, and may change without notice.

Lower Campus Steamline Project

Saturday work begins on 10/29 through December. Workers may arrive on site early; noisy work may begin after 8am; work stops 1:30pm.
November 16 or 17 (estimate) Saw cutting at walkway near NE corner of St Ignatius Church. Loud noise at times. 
  • Area 1:  Path by SW Kalmanovitz Hall door                      
    • Late November (2-3 days) - Install pipe                                  
  • Area 2: The main path between Welch Field and Gleeson Lawn
    • Late November - Backfill
  • Area 3:  Main east/west path in front of McLaren steps
    • Work delayed until Christmas break
  • Area 4:  Main path going north/south between Gleeson Library and Harney
    • Late November - Backfill     
  • Excavation activities will involve trenching and jackhammering, which will sometimes be noisy.
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas intersecting foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.
  • Please use caution in the area. Please respect all signs and instructions.
  • Expected completion: mid November

Malloy Basketball Practice Facility/War Memorial Gym

  • Late October - December: Ongoing delivery of steel, 3-4 trucks/day , structural steel installation using crane. 
  • Installation of decking and roofing follows steel framing in sequence
  • Hayes Healy Parking Lot Closed - All levels of the HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • OngoingPiers: bearing repairs, prep hydraulic hoistsinstallation of structural lock-up devices

Events etc:

  • Nov 13:  Basketball 4pm: 2pm Men vs UC Merced
  • Nov 30:  Basketball 7pm: 2pm Men vs Little Rock
  • Dec 7. Men’s Basketball 7:30 pm,vs Merrimack
  • Dec 19. Men’s Basketball 7:30 pm,vs UT Arlington
  • Dec 21. Men’s Basketball 7:00 pm vs Arizona State, TV trucks will be on site 
  • Jan 2.  Electrical Shutdown - all buildings on the Lower Campus. 7am - 3pm

Covid-19 

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing.

UPDATE 11/04/2022:

All dates below are best estimates, subject to weather and other external impacts, and may change without notice.

Lower Campus Steamline Project

Saturday work begins on 10/29 through December. Workers may arrive on site early; noisy work may begin after 8am; work stops 1:30pm. 

November 10-11 (estimate) Saw cutting at walkway near NE corner of St Ignatius Church. Loud noise at times. 

  • Area 1:  Path by SW Kalmanovitz Hall door                      
    • Late November (2-3 days) - Install pipe                                  
  • Area 2: The main path between Welch Field and Gleeson Lawn
    • Late Nov - Backfill
  • Area 3:  Main east/west path in front of McLaren steps
    • Work delayed until Christmas break
  • Area 4:  Main path going north/south between Gleeson Library and Harney
    • Early November - Test Seams
    • Late November - Backfill                             
  • Excavation activities will involve trenching and jackhammering, which will sometimes be noisy.
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas intersecting foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.
  • Please use caution in the area. Please respect all signs and instructions.
  • Expected completion: mid November

Malloy Basketball Practice Facility/War Memorial Gym

  • Late October - December: Delivery of steel, structural steel installation using crane. 
  • Thru Nov 30 (estimate) Steel deliveries up to 4 per day.  
  • Installation of decking and roofing follows steel framing in sequence
  • Hayes Healy Parking Lot Closed - All levels of the HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • OngoingPiers: bearing repairs, prep hydraulic hoistsinstallation of structural lock-up devices

Events etc:

  • Nov 7:  Basketball Double Header. 4pm: WM vs CSU East Bay; 7pm Men vs TX Southern 
  • Dec 21Men’s Basketball vs Arizona State, TV trucks will be on site 
  • Jan 2.  Electrical Shutdown - all buildings on the Lower Campus. 7am - 3pm

Covid-19 

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing.

UPDATE 10/28/2022:

All dates below are best estimates, subject to weather and other external impacts, and may change without notice.

Lower Campus Steamline Project

Saturday work begins on 10/29 through December. Workers may arrive on site early; noisy work may begin after 8am; work stops 1:30pm
  • Area 1:  Path by SW Kalmanovitz Hall door                      
    • Late November (2-3 days) - Install pipe                                  
  • Area 2: The main path between Welch Field and Gleeson Lawn
    • Late Nov - Backfill
  • Area 3:  Main east/west path in front of McLaren steps
    • Work delayed until Christmas break
  • Area 4:  Main path going north/south between Gleeson Library and Harney
    • Early November - Test Seams
    • Mid November - Backfill
  • Excavation activities will involve trenching and jackhammering, which will sometimes be noisy.
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas intersecting foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.
  • Please use caution in the area. Please respect all signs and instructions.
  • Expected completion: mid November

Malloy Basketball Practice Facility/War Memorial Gym

  • Late October - December: Delivery of steel, crane places steel onto site
  • Thru Nov 30 (estimate) Steel deliveries up to 4 per day.  
  • Foundation work complete 
  • Hayes Healy Parking Lot Closed - All levels of the HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • OngoingPiers: bearing repairs, prep hydraulic hoistsinstallation of structural lock-up devices

Covid-19 

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing.

UPDATE 10/17/2022:

All dates below are best estimates, subject to weather and other external impacts, and may change without notice.

Lower Campus Steamline Project

  • Area 1:  Path by SW Kalmanovitz Hall door     
    • Late Oct or early Nov (2-3 days) - Install pipe
  • Area 2: The main path between Welch Field and Gleeson Lawn
    • Early Nov - Backfill
  • Area 3:  Main east/west path in front of McLaren steps
    • Work delayed until Christmas break
  • Area 4:  Main path going north/south between Gleeson Library and Harney
    • 11/1-11/15 - Test Seams
  • Excavation activities will involve trenching and jackhammering, which will sometimes be noisy.
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas intersecting foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.
  • Please use caution in the area. Please respect all signs and instructions.
  • Expected completion: mid November

Malloy Basketball Practice Facility/War Memorial Gym

  • October 17.  Concrete pour 8-10 trucks;
  • Oct 24 - Crane delivery to site
  • Oct 25 - Concrete pour 2-3 trucks
  • Oct 26 - Crane starts moving steel
  • Hayes Healy Parking Lot Closed - All levels of the HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • OngoingPiers: bearing repairs, prep hydraulic hoistsinstallation of structural lock-up devices

Campus Events

  • Oct 21-23 - Celebrate USF, Alumni & USF Community event
    • Friday October 21.  Family campus tours
    • Saturday Oct 22 12-3pm - Food & Music Festival, Ulrich Field.  This event will generate noise. 

Covid-19 

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing.

UPDATE 10/7/2022:

All dates below are best estimates, subject to weather and other external impacts, and may change without notice.

Lower Campus Steamline Project

  • Area 1:  Path by SW Kalmanovitz Hall door
    • 10/17 - 10/21 - Pipe layout/prep
    • late Oct or early Nov (2-3 days) - Install pipe                   
  • Area 2: The main path between Welch Field and Gleeson Lawn
    • early Nov - Backfill
  • Area 3:  Main east/west path in front of McLaren steps
    • Work delayed until Christmas break
  • Area 4:  Main path going north/south between Gleeson Library and Harney
    • 8/31 - 9/2 - Cut and demo existing pipe
    • 9/6 - 10/7 - Install pipe
    • 10/10 - 10/14 - Test Seams
  • Excavation activities will involve trenching and jackhammering, which will sometimes be noisy.
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas intersecting foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.
  • Please use caution in the area. Please respect all signs and instructions.
  • Expected completion: Late October/early November

Malloy Basketball Practice Facility/War Memorial Gym

  • Saturdays Oct 8 & 15: limited work on-site 9am-5pm
  • October 14 & 17.  Concrete pour 4-5 trucks each
  • Oct 24 - Crane delivery to site
  • Oct 25 - Concrete pour 2-3 trucks
  • Oct 26 - Crane starts moving steel
  • Hayes Healy Parking Lot Closed - All levels of the HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.
  • Ongoing- Clearing & grubbing work; selected tree removal
  • Ongoing- installation of structural lock-up devices

SFPUC Sewer Upgrade - courtesy notice

SFPUC will conduct street work to implement a sewer upgrade on Schrader between Grove and Fulton. 
-Week of October 10: Repaving 
-Access to both levels of Kendrick garage will remain, although expect delays. 
-No access to the garage from Grove -- access from Fulton only
-Work will be noisy
This is a SFPUC project and not associated with USF.
 

Campus Events

  • Oct 21-23 - Celebrate USF, Alumni & USF Community event  - Details TBD

Covid-19 

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing.

UPDATE 9/23/2022:

Lower Campus Steamline Project 

Sept 26  8am Pipe delivery by truck via Parker St entrance
  • Area 1:  Path by SW Kalmanovitz Hall door 
    • 10/17 - 10/21 - Pipe layout/prep
    • late Oct or early Nov (2-3 days) - Install pipe
  • Area 2:  Main path between Welch Field and Gleeson Lawn
    • 9/26 - 9/30 - Pipe layout/prep
    • early - mid October (2-3 days) - Install pipe
  • ​​​​Area 3:  Main east/west path in front of McLaren steps
    • Work delayed until Christmas break   
  • Area 4:  Main path going north/south between Gleeson Library and Harney
    • 8/31 - 9/2 - Cut and demo existing pipe
    • 9/6 - 9/30 - Install pipe
    • 10/3 - 10/7 - Cut concrete vault for tie-in
  • Excavation activities will involve trenching and jackhammering, which will sometimes be noisy.
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas intersecting foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.
  • Please use caution in the area. Please respect all signs and instructions.
  • Expected completion: Late October/early November

Malloy Basketball Practice Facility/War Memorial Gym

  • Micro piles drilling restarted
  • Pouring foundation piers onion.  Small pours (1 truck each) on Monday, 9/26 & Wednesday, 9/28
  • Oct 24   Crane delivery to site. 
  • Hayes Healy Parking Lot Closed - All levels of HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.  
  • Sept 27 - Equipment Delivery about 8a: large truck will park on LoSchiavo drive at the Parker entrance for off-loading. The drive entrance will be closed from 8am-12pm except in case of emergency. 
  • Ongoing- Clearing & grubbing work; selected tree removal  (estimate 4-6 weeks)

Lone Mountain Trash & Recycling Facility

Construction activities complete.
 

SFPUC Sewer Upgrade - courtesy notice

SFPUC will conduct street work to implement a sewer upgrade on Schrader between Grove and Fulton. 
  • Starts Monday 9/26
  • Should last 2-3 weeks; M-F; Hours 7:30am-5pm 
  • Access to both levels of Kendrick's garage will remain, although expect delays. 
  • No access to the garage from Grove -- access from Fulton only
  • Work will be noisy
  • The street will be re-paved in October. This will take 2 days - access will be similar (can still use the garage, Muni line still operating)
This is a SFPUC project and not associated with USF.
 

Campus Events

  • Oct 21-23 - Celebrate USF, Alumni & USF Community event  - Details TB

Covid-19 

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing.

UPDATE 9/16/2022:

All dates below are best estimates, subject to weather and other external impacts, and may change without notice. 

Lower Campus Steamline Project 

Sept 26, 8 am Pipe delivery by truck via Parker St entrance

  • Area 1:  Path by SW Kalmanovitz Hall door 
    • 10/17 - 10/21 - Pipe layout/prep
    • Late Oct/early Nov (2,3 days) - Install pipe
  • Area 2: The main path between Welch Field and Gleeson Lawn
    • 9/26 -9/30 - Pipe layout/prep 
    • Early - mid-Oct (2,3 days) - Install pipe
  • Area 3:  Main east/west path in front of McLaren steps
    • Work delayed until Christmas break
  • Area 4:  Main path going north/south between Gleeson Library and Harney
    • 9/6 - 9/30 - Install pipe
    • 10/3 - 10/7 - Cut concrete vault for ti-in 
  • Excavation activities will involve trenching and jackhammering, which will sometimes be noisy.
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas intersecting foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.
  • Please use caution in the area. Please respect all signs and instructions.
  • Expected completion: Late October/early November

Malloy Basketball Practice Facility/War Memorial Gym

  • Drilling certain micro piles paused.  Restart TBD
  • Pour foundation piers.  Rebar work continues
  • Hayes Healy Parking Lot Closed - All levels of HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.  

  • Sept 26 - Equipment Delivery 8a, -12pm: large truck will park on LoSchiavo drive at the Parker entrance for off-loading. The drive entrance will be closed from 8 am-12 pm except in case of emergency. 
  • Ongoing- Clearing & grubbing work; selected tree removal  (estimate 4-6 weeks)

Fromm Hall roof repair

  • Sept 21 - Demobilize

Lone Mountain Trash & Recycling Facility

  • Construction activities complete.

Koret Garage Stair resurfacing

  • Resurfacing is complete.

SFPUC Sewer Upgrade - courtesy notice

  • SFPUC will conduct street work to implement a sewer upgrade on Schrader between Grove and Fulton. Estimated start Sept 26. 
  • Traffic lanes will be re-routed and sometimes closed. 
  • This is an SFPUC project and not related to USF.

Campus Events

  • Oct 21-23 - Celebrate USF, Alumni & USF Community event  - Details TBD

Covid-19 

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing.

 


UPDATE 9/10/2022:

All dates below are best estimates, subject to weather and other external impacts, and may change without notice. 

Harney Science Roof fans

  • Saturday, Sept 10 - Crane to offload materials from roof.  8am-12pm. Please use caution in the area. One day only.

Fromm Hall roof repair

  • Sept 12 - Crane returns to allow off-load.  Crane will be placed on Parker, just south of Golden Gate intersection, to lift materiel from the Fromm roof. Crane in place one day
  • Sept 16 - Demobilize

Koret Garage Stair resurfacing

Resurface and retread the stairs leading from the upper deck of the Koret garage to the lower deck. The stairs will remain closed to foot traffic for the project's duration. Expected completion 9/23. Please use caution in the area. 

Lower Campus Steamline Project 

Expected completion: early October
  • Area 1:  Path by SW Kalmanovitz Hall door 
    • Saturday 9/10 8:30am - 6pm:  Possible concrete demo at KHall stairs. If so, this work will be noisy.
    • 9/17 - 10/1 - Install pipe
    • Mid-September (2 days TBD) -  Pipe layout/prep 
    • Mid-late September (4 days TBD) - Install pipe
  • Area 2: The main path between Welch Field and Gleeson Lawn
    • Mid-September (2 days TBD) - Pipe layout/prep - 
    • Mid-late September (2 days TBD) - Install pipe - 
  • Area 3:  Main east/west path in front of McLaren steps
    • Work delayed until Christmas break
  • Area 4:  Main path going north/south between Gleeson Library and Harney
    • 8/31 - 9/6 - Cut and demo existing pipe - 
    • 9/6 - 9/23 - Install pipe
Scope
  • Steamline maintenance/replacement project that will involve closing off Welch Field.  Impact areas on the lower campus include Welch Field, the lower portion of the Gleason lawn, the north-south footpath between Gleason and CSI, and one vault in the paver section of the drive between UC and McLaren.
  • Excavation activities will involve trenching and jackhammering, which will sometimes be noisy.
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas intersecting foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.
Please use caution in the area. Please respect all signs and instructions.

Malloy Basketball Practice Facility/War Memorial Gym

  • Drilling micro piles paused.  Restart TBD
  • Sept 5 - Sept 23 - Pour foundation piers.  Rebar work continues.
  • Sept 13  Fire Alarm Testing 9am - audible alarms will last about 5 minutes
  • Hayes Healy Parking Lot Closed - All levels of HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Trash & Recycling Facility

  • Sept 6-15 - Delivery & install of door, previously delayed
  • Sept 16 - Estimated completion date

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).
  • Sept 12-14 - Erosion control setup
  • Sept 12 (estimate) - Clearing & grubbing work; selected tree removal  (estimate 4-6 weeks)
Most work will take place under the roadbed. There will be substantial concrete demo work periodically which will be noisy.  

Campus Events

  • Sept 10 - Student Concert at Ulrich Field 1p-4 pm. Golden Gate gate will be used due to construction.
  • Oct 21-23 - Celebrate USF, Alumni & USF Community event  - Details TBD

Covid-19 

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c, April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing.

UPDATE 9/2/2022:

All dates below are best estimates, subject to weather and other external impacts, and may change without notice. 

Harney Science Roof fans

  • Saturday, Sept 10 - Crane to place roof exhaust fans will be placed on Golden Gate near NE corner of Harney. Sidewalks in front of Harney between Kittridge & Chabot will be temporarily barricaded during the pick process. Please use caution in the area. One day only.

Fromm Hall roof repair

  • Aug 29 - Sept 2 - Demo rooftop materials
  • Aug 30 - Sept 13 - Install roof
  • Sept 7 - Crane returns to allow off-load.  Crane will be placed on Parker, just south of Golden Gate intersection, to lift materiel from the Fromm roof. Crane in place one day
  • Sept 14 - Demobilize

Koret Garage Stair resurfacing

Resurface and retread the stairs leading from the upper deck of the Koret garage to the lower deck. The stairs will remain closed to foot traffic for the project's duration. A work crew will be on-site for about a month. Please use caution in the area. 
 

Lower Campus Steamline Project 

  • Area 1:  Path by SW Kalmanovitz Hall door 
    • 9/17 - 10/1 - Install pipe
    • Mid-September (2 days TBD) -  Pipe layout/prep 
    • Mid-late September (4 days TBD) - Install pipe
  • Area 2: The main path between Welch Field and Gleeson Lawn
    • Mid-September (2 days TBD) - Pipe layout/prep - 
    • Mid-late September (2 days TBD) - Install pipe - 
  • Area 3:  Main east/west path in front of McLaren steps
    • Work delayed until Christmas break
  • Area 4:  Main path going north/south between Gleeson Library and Harney
    • 8/31 - 9/6 - Cut and demo existing pipe - 
    • 9/6 - 9/23 - Install pipe
    • 9/23 - 9/30Test and backfill
Scope
  • Steamline maintenance/replacement project that will involve closing off Welch Field.  Impact areas on the lower campus include Welch Field, the lower portion of the Gleason lawn, the north-south footpath between Gleason and CSI, and one vault in the paver section of the drive between UC and McLaren.
  • Excavation activities will involve trenching and jackhammering, which will sometimes be noisy.
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas intersecting foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.

Please use caution in the area. Please respect all signs and instructions.

Malloy Basketball Practice Facility/War Memorial Gym

  • Aug 30 - Concrete pour at lower levels of HH parking lot. Trucks will stage (3-4) on the upper deck of HH garage within fenced.
  • Sept 3 - Drilling micro piles paused.  Restart TBD
  • Sept 5 - Sept 23 - Pour foundation piers.  Rebar work continues.
  • Hayes Healy Parking Lot Closed - All levels of HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Trash & Recycling Facility

  • Sept 6-15 - Delivery & installation of door, previously delayed
  • Sept 16 - Estimated completion date

Lone Mountain Viaduct, 330 Parker Ave

  • Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).
  • Thru Aug 31 - Goats clearing hillside brush
  • Sept 6 - Demo of small
  • Sept 12 (estimate) - Site clearing and selected tree removal 

Most work will take place under the roadbed. There will be substantial concrete demo work periodically, which will be noisy.  


Campus Events

  • Sept 10 - Student Concert at Ulrich Field 1p-4 pm. Golden Gate gate will be used due to construction.
  • Oct 21-23 - Celebrate USF, Alumni & USF Community event  - Details TBD

Covid-19 

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020.
USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing


 

UPDATE 8/25/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice. 

University Center roof repair

Saturday, Aug 28 - Crane at UC lot for the day to assist roof repair on UC 3rd floor roof. Please use caution in the area. 

Harney Science Roof fans

Saturday Sept 10 Crane to place roof exhaust fans will be placed on Golden Gate near NE corner of Harney. Sidewalk in front of Harney between Kittridge & Chabot will be temporarily barricaded during the pick process. Please use caution in the area. One day only.

Fromm Hall roof repair 

  • Aug 29, Monday: Crane will be placed on Parker, just south of Golden Gate intersection, to lift materiel onto the Fromm roof. Crane in place one day
  • Aug 29 - Sept 2: Demo roof top materials
  • Aug 30- Sept 13:  Install roofSept 7: Crane returns to allow off-load from roof
  • Sept 14: Demobilize

Koret Garage Stair resurfacing 

Resurface and retread the stairs leading from the upper deck of the Koret garage to the lower deck. The stairs will remain closed to foot traffic for the project's duration. A work crew will be on-site for about a month. Please use caution in the area. 

Lower Campus Steamline Project 

Friday 8/26 - Crane delivery.  The crane will be staged inside a fenced area between Library and Harney

Monday 8/29 - Pipe delivery will be Monday 8/29, 7 am ( 1 truck)

  • truck will enter from Parker Ave and will stage pipe inside fenced area on Gleeson lawn

Area 1:  Path by SW Kalmanovitz Hall door 

  • Install pipe - 9/17 - 10/1   

Area 2:  Main path between Welch Field and Gleeson Lawn

  • Install pipe - mid-late September

Area 3:  Main east/west path in front of McLaren steps

  • Work delayed until Christmas break   

Area 4:  Main path going north/south between Gleeson Library and Harney

  • Remove pavers and excavate - 8/22 - 8/29 
  • Cut and demo existing pipe - 8/29 - 8/31
  • Install pipe - 8/31 - 9/14

Scope:

  • Steamline maintenance/replacement project that will involve closing off Welch Field.  Impact areas on lower campus include: Welch Field, lower portion of Gleason lawn, north-south footpath between Gleason and CSI, and one vault in the paver section of the drive between UC and McLaren
  • Excavation activities will involve trenching and jackhammering, which will at times be noisy
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas intersecting foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.  
  • Please use caution in the area. Please respect the signs and instructions. 

Malloy Basketball Practice Facility/War Memorial Gym

  • Aug 30: Concrete pour at lower levels of HH parking lot. Trucks will stage (3-4) on the upper deck of HH garage within fenced site, off the street. 
  • Aug 1 - Sept 2: Ongoing: drilling micro piles and placing rebar. Estimated duration 5 weeks 
  • Sept 5 - Sept 23: Pour foundation piers
  • Hayes Healy Parking Lot Closed: All levels of HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.  

Lone Mountain Trash & Recycling Facility

Aug 26 - Delivery of compactors. 

Aug 29 - Minor concrete pour

Sept 2 - Estimated completion date


Loyola Village - exterior paint refresh, new gutters, awnings, etc

  • Aug 26 - Touch up painting, finish awnings installation
  • Aug 26 - Completion date

Lone Mountain Viaduct, 330 Parker Ave

  • Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  
  • Thru Aug 31: Goats clearing hillside brush
  • Sept 6  (estimate): Demo of small part of the wall along the north side of viaduct which will involve saw-cutting and will sometimes be loud. 
  • Sept 12 (estimate): Site clearing and selected tree removal 
  • Most work will take place under the road bed. There will be substantial concrete demo work periodically which will be noisy.  

Campus Events

  • Sept 10 - Student Concert at Ulrich Field 2p-4pm 
  • Oct 21-23 - Celebrate USF, Alumni & USF Community event  Details TBD

Covid-19

Construction at USF’s project sites continue in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing


UPDATE 8/19/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice. 

Student Move-In Day - mostly Lone Mtn residence halls. 

August 20 Saturday    

  • 9am - 6pm Orientation Desk opens
  • 10am- 5pm New Student Check in and Residence Hall Move In
  • New students & families will have received an assigned check-in/move-in time before arrival. 
  • Student "Go Team” reps will help guide arrivals through process

The following city street no-parking areas will be in effect :.

  • Friday, Aug. 19 to Tuesday, Aug. 23 – The following city street no parking areas will be in effect from Friday, Aug. 19 at 7 a.m.
    • Golden Gate Ave. (South side of Golden Gate Ave., 2325 to 2381 Golden Gate Ave.
    • Turk Blvd. (South side of Turk Blvd., 2930 to 2975 Turk, from the top of the bus stop going East to the entrance of the Koret parking lot.)
  • Saturday, Aug. 20 – The following city street no parking areas will be in effect on Saturday, Aug. 20 from 7 a.m.–4 p.m
    • Anza St. (south side of Anza St. in front of Loyola Village, 305 to 341 Anza St.)
    • Anza St. (north side of Anza St. adjacent to Pedro Arrupe Residence Hall, 1400 to 1448 Anza St. between 6th and 5th Avenues)

Fromm Hall roof repair 

  • Aug 22, Monday:  Crane will be placed on Parker, just south of Golden Gate intersection, to lift materiel onto the Fromm Roof. 
  • Aug 22 - Aug 26:  Demo roof top materials'
  • Aug 23- Sept 6:  Install roof
  • Aug 31:    Crane returns to allow off-load from roof
  • Sept 7:    Demobilize

Koret Garage Stair resurfacing 

Resurface and retread the stairs leading from the upper deck of the Koret garage garage to the lower deck. The stairs will remain closed to foot traffic for the duration of the project.   A work crew will be on-site for about a month.  Please use caution in the area. 

Lower Campus Steamline Project 

Steamline maintenance/replacement project that will involve closing off Welch Field.

  • Impact areas on lower campus include: Welch Field, lower portion of Gleason lawn, north south footpath between Gleason and CSI, and one vault in the paver section of the drive between UC and McLaren
  • Excavation activities will involve trenching and jack hammering, which will at times be noisy
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas that intersect foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.
    • Area 1:  Path by SW Kalmanovitz Hall door 
      • Install pipe - 9/17 - 10/1   
    • Area 2:  Main path between Welch Field and Gleeson Lawn
      • Install pipe - mid-late September          
    • Area 3:  Main east/west path in front of McLaren steps
      • Work delayed until Christmas break   
    • Area 4:  Main path going north/south between Gleeson Library and Harney
      • Remove pavers and excavate     8/22 - 8/29 
      • Cut and demo existing pipe        8/29 - 8/31
      • Install pipe                                    8/31 - 9/14

Malloy Basketball Practice Facility/War Memorial Gym

  • Aug 22, Monday:  Off-haul drilling spoils. 8-10 trucks
  • Aug 1 - Sept 2:  Ongoing: drilling micro piles and placing rebar. Estimated duration 5 weeks 
  • Sept 5 - Sept 23:   Pour foundation piers
  • Hayes Healy Parking Lot Closed: All levels of HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.  

Lone Mountain Trash & Recycling Facility

  • Thru Aug 23 - finish paint, install downspouts, finish concrete drains. 
  • Aug 23  Minor concrete pour
  • Sept 2    Estimated completion date

Loyola Village - exterior paint refresh, new gutters, awnings, etc

  • Aug 23   install awnings
  • Aug 24:   finish new planters at Anza entrance
  • Aug 26 :   Estimated completion date

Lone Mountain Viaduct, 330 Parker Ave

  • Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).  
  • Thru Aug 31   Goats, clearing hillside brush
  • Sept 6  (estimate):  Demo of small part of the wall along the north side of viaduct which will involve saw-cutting and will sometimes be loud. 
  • Sept 12 (estimate):  Site clearing and selected tree removal 
  • Most work will take place under the road bed. There will be substantial concrete demo work periodically which will be noisy.  

Campus Events

  • Sept 9 Wms Volleyball match Sobrato Center/WMG
  • Sept 10 Student Concert at Ulrich Field 2p-4pm 
  • Oct 21-23  Celebrate USF, Alumni & USF Community event  Details TBD

Covid-19

Construction at USF’s project sites continue in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing



UPDATE 8/12/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice. 

Student Move-In Day - mostly Lone Mtn residence halls. 

  • August 20 Saturday
    • 9am - 6pm Orientation Desk opens
    • 10am- 5pm New Student Check in and Residence Hall Move In
    • New students & families will have received an assigned check-in/move-in time before arrival. 
    • Student "Go Team” reps will help guide arrivals through process

The following city street no-parking areas will be in effect :.

  • Friday, Aug. 19 to Tuesday, Aug. 23 – The following city street no parking areas will be in effect from Friday, Aug. 19 at 7 a.m.
    • Golden Gate Ave. (South side of Golden Gate Ave., 2325 to 2381 Golden Gate Ave.
    • Turk Blvd. (South side of Turk Blvd., 2930 to 2975 Turk, from the top of the bus stop going East to the entrance of the Koret parking lot.)
  • Saturday, Aug. 20 – The following city street no parking areas will be in effect on Saturday, Aug. 20 from 7 a.m.–4 p.m
    • Anza St. (south side of Anza St. in front of Loyola Village, 305 to 341 Anza St.)
    • Anza St. (north side of Anza St. adjacent to Pedro Arrupe Residence Hall, 1400 to 1448 Anza St. between 6th and 5th Avenues)

Fromm Hall roof repair 

  • Aug 22, Monday:  Crane will be placed on Parker, just south of Golden Gate intersection, to lift materiel onto the Fromm Roof. 
  • Aug 22 - Aug 26: Demo roof top materials
  • Aug 23- Sept 6: Install roof
  • Aug 31: Crane returns to allow off-load from roof
  • Sept 7: Demobilize

Koret Garage Stair resurfacing 

Resurface and retread the stairs leading from the upper deck of the Koret garage garage to the lower deck. The stairs will remain closed to foot traffic for the duration of the project.   A work crew will be on-site for about a month.  Please use caution in the area. 

Lower Campus Steamline Project 

  • Steamline maintenance/replacement project that will involve closing off Welch Field.  
  • Impact areas on lower campus include: Welch Field, lower portion of Gleason lawn, north south footpath between Gleason and CSI, and one vault in the paver section of the drive between UC and McLaren
  • Excavation activities will involve trenching and jack hammering, which will at times be noisy
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas that intersect foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.
  • Area 1:  Path by SW Kalmanovitz Hall door 
    • Install pipe - 9/17 - 10/1
  • Area 2:  Main path between Welch Field and Gleeson La
    • Install pipe - mid-late Septenber
  • Area 3:  Main east/west path in front of McLaren steps
    • Work delayed until Christmas break
  • Area 4:  Main path going north/south between Gleeson Library and Harney
    • Remove pavers and excavate     8/22 - 8/29 
    • Cut and demo existing pipe         8/29 - 8/31
    • Install pipe                                    8/31 - 9/14

Malloy Basketball Practice Facility/War Memorial Gym

Aug 22, Monday: 

  • Off-haul drilling spoils. 8-10 trucks
  • Aug 1 - Sept 2:  Ongoing: drilling micro piles and placing rebar. Estimated duration 5 weeks 
  • Sept 5 - Sept 23:   Pour foundation piers
  • Hayes Healy Parking Lot Closed: All levels of HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.  

Lone Mountain Trash & Recycling Facility

  • Thru Aug 23 - finish paint, install downspouts, finish concrete drains. 
  • Aug 23  Minor concrete pour
  • Sept 2    Estimated completion date

Loyola Village - exterior paint refresh, new gutters, awnings, etc

  • Aug 23   install awnings
  • Aug 24:   finish new planters at Anza entrance
  • Aug 26 :   Estimated completion date

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus). 

  • Thru Aug 31   Goats, clearing hillside brush
  • Sept 6  (estimate):  Demo of small part of the wall along the north side of viaduct which will involve saw-cutting and will sometimes be loud. 
  • Sept 12 (estimate):  Site clearing and selected tree removal 

Most work will take place under the road bed. There will be substantial concrete demo work periodically which will be noisy.  


Campus Events

  • Sept 9 Wms Volleyball match Sobrato Center/WMG
  • Sept 10 Student Concert at Ulrich Field 2p-4pm 
  • Oct 21-23  Celebrate USF, Alumni & USF Community event  Details TBD

Covid-19

Construction at USF’s project sites continue in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing


UPDATE 8/5/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Campus Maintenance Project

Tuesday 8/9/22 7:30AM - 4PM. Back flow valve replacement near Gleeson Library loading dock. The north/south pathway between Gleeson Library and Fromm Hall will be closed. The Fromm Hall student entrance will remain accessible from the south end of the path.

Disability Services will be accessible from the loading dock.

Please use caution when traveling in this area, watch for large equipment, and follow instructions from the construction crew.

Turk Boulevard Street Improvement project

Infrastructure project to refurbish the sidewalk, ramps, and driveways on the USF (north) side of Turk Boulevard, roughly between Tamalpais and Roselyn Terraces.  The project is expected to be completed by mid-to-late August.

Work crews will arrive approximately 7:30 a.m. with work commencing at 8am. Framing molds and concrete pours of sidewalks, driveway entrances and ramps. Please follow traffic control directions and use caution in the area.

Koret Garage Stair resurfacing

Resurface and retreading the stairs leading from the upper deck of the garage to the lower deck. Loud work will continue through next week. The stairs will remain closed to foot traffic for the duration of the project.  Placement of treads in late August. Please use caution in the area.

Lower Campus Steamline Project

Steamline maintenance/replacement project that will involve closing off Welch Field.  The project has an estimated 2-3 month duration. To meet that schedule, the contractor will work 2 weekday shifts (8am - 8:30pm)  and a single shift on Saturdays starting at 9am (possible earlier starts depending on events scheduled at St Ignatius Church)

General scope:

  • impact areas on lower campus include: Welch Field, lower portion of Gleason lawn, north south footpath between Gleason and CSI, and one vault in the paver section of the drive between UC and McLaren
  • Excavation activities will involve trenching and jack hammering, which will at times be noisy
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas that intersect foot or vehicle traffic in paved areas will be covered with metal trench plates rated for pedestrian and vehicular traffic.

Malloy Basketball Practice Facility/War Memorial Gym

  • Week of Aug 8:  Drilling micro piles in garage structure through Tues Aug 9; Aug 10 drilling begins outside at south end of site. This work will be noisy.
  • Saturday Aug 6, Saturday August 13:  Drilling micro piles. Work start @ 9am. Some of this work will be noisy.
  • Hayes Healy Parking Lot Closed: All levels of HH parking garage are closed.  Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Trash & Recycling Facility

  • August 8: Delivery of compactor rails on site. Noisy
  • August 9:  Delivery and placement of compactors
  • Aug 15: Delivery of garage door system
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking.  Alternative parking is available to USF permit holders in the garages beneath the new Lone Mtn Residence Hall; visitors may park at Koret Lot.

Loyola Village, Anza Street

Schedule:  May 31 - August 19 approximately.

Continued progression through the Complex with painting of the center walkway and scaffolding of the courtyards.

  • Some sheet metal work will be fabrication (cutting & soldering) to be located in the LV garage in an effort to contain noise.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).

  • Date TBD: Demo of small part of the wall along the north side of viaduct which will involve saw-cutting and will sometimes be loud.
  • Aug 15(estimate):  Site clearing and selected tree removal
    • Most work will take place under the road bed. There will be substantial concrete demo work periodically which will be noisy.  

Campus Events

  • August 13 - Saturday - Student Move-In Day.
  • 9am - 6pm - Orientation Desk opens
  • 10am- 5pm - New Student Check in and Residence Hall Move In
  • New students & families will have received an assigned check-in/move-in time before arrival.
  • Student "Go Team” reps will help guide arrivals through process.
  • USF Public Safety will work with SFMTA to create queuing lanes and to block off parking spots in select areas.
  • September 10 Saturday - Back to School Concert  2-4 pm  Ulrich Field    (this event was postponed, now back to original date)

Covid-19

Construction at USF’s project sites continue in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020.   Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distancing


 

UPDATE 7/29/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Turk Boulevard Street Improvement project

Infrastructure project to refurbish the sidewalk, ramps, and driveways on the USF (north) side of Turk Boulevard,roughly between Tamalpais and Roselyn Terraces. The project is expected to be completed by mid-to-late August

Week of August 1:work crews will begin arrivingapproximately 7:30 a.m. with work commencing at 8am. Framing molds and concrete pours of sidewalks, driveway entrances and ramps

Please follow traffic control directionsand use caution in the area.

Koret Garage Stair resurfacing

August 1 (estimate): work will begin work to resurface and retread the stairs leading from the upper deck of the garage to the lower deck. The stairs will remain closed to foot traffic for theduration of the project. A work crew will be on-site for about a month. Most of the noisy/disruptive work will happen in the first two weeks of August. Please use caution in the area.

Lower Campus Steamline Project

Steamline maintenance/replacement project that will involve closing off Welch Field. The project has an estimated 2-3 month duration. To meet that schedule, the contractor will work 2 weekday shifts(8am - 8:30pm) and a single shift on Saturdays starting at 9am (possible earlier starts depending on events scheduled at St Ignatius Church)

Closure dates for paver removal and excavation.

Please use caution in the area and follow directional signage.

  • 8/4 - 8/5 - Path by SW Kalmanovitz Hall door
  • 8/8 - 8/10- Main path between Welch Field and Gleeson Lawn
  • 8/15 - 8/26 - Main path going north/south between Gleeson Library and Harney

General scope:

  • Impact areas on lower campus include: Welch Field, lower portion of Gleason lawn, north south footpath between Gleason and CSI, and one vault in the paver section of the drive between UC andMcLaren
  • Excavation activities will involve trenching and jack hammering, which will at times be noisy
  • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas that intersect foot or vehicle traffic in paved areas will be covered with metal trench platesrated for pedestrian and vehicular traffic.

Malloy Basketball Practice Facility/War Memorial Gym

  • Aug 1:Drilling micro piles commences. Estimated duration 5 weeks
  • Aug 5:Power shutdown:Gillson/Memorial only.Estimate timeframe: 8am - 5:30pm.

Underground electrical work ongoing.

  • Hayes Healy Parking Lot Closed: All levels of HH parking garage are closed. Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Trash & Recycling Facility

  • Aug 1 & 2:Prep and delivery of new compactors
  • Aug 15:Delivery of garage door system
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available to USF permit holders in the garagesbeneath the new Lone Mtn Residence Hall; visitors may park at Koret Lot.

Loyola Village, Anza Street

Schedule: May 31 - August 19 approximately.

Continued progression through the Complex with painting of the center walkway and scaffolding of the courtyards.

Some sheet metal work will be fabrication (cutting & soldering) to be located in the LV garage in an effort to contain noise.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).

  • Aug 8 (estimate):Demo of small part of the wall along the north side of viaduct which will involve saw-cutting and will sometimes be loud.
  • Aug 15(estimate):Site clearing and selected tree removal
  • Most work will take place under the road bed. There will be substantial concrete demo work periodically which will be noisy

Campus Events

  • August 13 - Saturday - StudentMove-In Day.
    • 9am - 6pm - Orientation Desk opens
    • 10am- 5pm - New Student Check in and Residence Hall Move In
    • New students & families will havereceived an assigned check-in/move-in time before arrival.
    • Student "Go Team” reps will help guide arrivals through process.
    • USF Public Safety will work with SFMTA to create queuing lanes and to block off parking spots in select areas.

Covid-19

Construction at USF’s project sites continue in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “SanFrancisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents ateach site are tasked with making sure workers follow those guidelines and maintain social distancing


UPDATE 7/22/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Turk Boulevard Street Improvement project

infrastructure project to refurbish the sidewalk, ramps, and driveways on the USF (north) side of Turk Boulevard,roughly between Tamalpais and Roselyn Terraces. The project is expected to be completed by mid-to-late August.

Monday, July 25:work crews will begin arrivingapproximately 7:30 a.m. with work commencing at 8am. Demolition activities will occur first, including jack hammering and saw cutting.

Please follow traffic control directionsand use caution in the area.

Koret Garage Stair resurfacing

August 1 (estimate): work will begin work to resurface and retread the stairs leading from the upper deck of the garage to the lower deck. The stairs will remain closed to foot traffic for theduration of the project. A work crew will be on-site for about a month. Most of the noisy/disruptive work will happen in the first two weeks of August. Please use caution in the area.

Lower Campus Steamline Project

Steamline maintenance/replacement project that will involve closing off Welch Field. The project has an estimated 2-3 month duration. To meet that schedule, the contractor will work 2 weekday shifts(8am - 8:30pm) and a single shift on Saturdays starting at 9am (possible earlier starts depending on events scheduled at St Ignatius Church)

July schedule (estimate

  • 7/21 - 22 -- mobilization of excavation equipment on site. Concrete saw-cutting (Welch Field)
  • 7/25 -- begin excavation of Welch Field (~7-10 days)
    • Impact areas on lower campus include: Welch Field, lower portion of Gleason lawn, north south footpath between Gleason and CSI, and one vault in the paver section of the drive between UC andMcLaren
    • Excavation activities will involve trenching and jackhammering, which will at times be noisy
    • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas that intersect foot or vehicle traffic in paved areas will be covered with metal trench platesrated for pedestrian and vehicular traffic.

Malloy Basketball Practice Facility/War Memorial Gym

  • Aug 1:Estimated start date for drilling micro piles. Estimated duration 3 weeks
  • Power shutdown: Gillson/Memorial only. Date TBD
  • Underground electrical work ongoing.
  • Hayes Healy Parking Lot Closed: All levels of HH parking garage are closed. Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Trash & Recycling Facility

  • July 25:Electrical tie-in. Power will remain on.
  • July 25:Interior painting begins
  • July 27:Exterior painting begins

Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available to USF permit holders in the garagesbeneath the new Lone Mtn Residence Hall; visitors may park at Koret Lot.

Loyola Village, Anza Street

Schedule: May 31 - August 19 approximately.

  • Continued progression through the Complex with painting of the center walkway and scaffolding of the courtyards.
  • Some sheet metal work will be fabrication (cutting & soldering) to be located in the LV garage in an effort to contain noise
  • July 25 week: remove and transplant palm trees at Anza entrance.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).

  • Aug 8 (estimate):Demo of small part of the wall along the north side of viaduct which will involve saw-cutting and will sometimes be loud.
  • Aug 15(estimate): Site clearing and selected tree removal
  • Most work will take place under the road bed. There will be substantial concrete demo work periodically which will be noisy.

Campus Events

  • August 13 - Saturday - Move-In Day. Details to follow
  • September 10 - Saturday - Back to School concertTo be rescheduled/probably re-located

Covid-19

Construction at USF’s project sites continue in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “SanFrancisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents ateach site are tasked with making sure workers follow those guidelines and maintain social distancing


UPDATE 7/15/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lower Campus SteamlineProject

Steamline maintenance/replacement project that will involve closing off Welch Field. The project has an estimated 2-3 month duration. To meet that schedule, the contractor will work 2 weekday shifts (8am - 8:30pm) and a single shift on Saturdays starting at 9am (possible earlier starts depending on events scheduled at St Ignatius Church)

July schedule (estimate)

  • 7/15 -- Fence delivery and installation around Welch Field
  • 7/19 - 20 -- site prep
  • 7/21 - 22 -- mobilization of excavation equipment on site (Welch Field)
  • 7/25 -- begin excavation of Welch Field (~7-10 days)
    • Impact areas on lower campus include: Welch Field, lower portion of Gleason lawn, north south footpath between Gleason and CSI, and one vault in the paver section of the drivebetween UC and McLaren
    • Excavation activities will involve trenching and jack hammering, which will at times be noisy
    • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas that intersect foot or vehicle traffic in paved areas will be covered withmetal trench plates rated for pedestrian and vehicular traffic.

Malloy Basketball Practice Facility/War Memorial Gym

  • July 25:Estimated start date for drilling micro piles.Estimated duration 3 weeks
  • July 25(estimate) Power shutdown: Gillson/Memorial. Details TBD
  • Underground electrical work ongoing.
  • Hayes Healy Parking Lot Closed:All levels of HH parking garage are closed. Faculty, staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Trash & Recycling Facility

  • July 11 - 19 Finish interior taping
  • July 18:Painting begins
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available to USF permit holders in the garagesbeneath the new Lone Mtn Residence Hall; visitors may park at Koret Lot.

Loyola Village, Anza Street

  • Schedule: May 31 - August 19 approximately.
  • Continued progression through the Complex with painting of the center walkway and scaffolding of the courtyards.
  • Some sheet metal work will be fabrication (cutting & soldering) to be located in the LV garage in an effort to contain noise.
  • July 25 week: remove and transplant palm trees at Anza entrance.

Lone Mountain Viaduct, 330 Parker Ave

  • Structural remedial workof the Lone Mountain viaduct (north side of Lone Mountain campus).
  • Estimated to start August 2022. Details TBD
  • Most work will take place under the road bed. There will be substantial concrete demo work periodically which will be noisy.

Campus Events

  • August 13 - Saturday - Move-In Day. Details to follow
  • September 10- Saturday- Back to School concertTo be rescheduled/probably re-located

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “SanFrancisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents ateach site are tasked with making sure workers follow those guidelines and maintain social distancing


UPDATE 7/8/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lower Campus SteamlineProject

Facilities Mgt will initiate a streamline maintenance/replacement project that will involve closing off Welch Field (See the map below) as well as require excavation and a fair amount ofnoise (jackhammering).

The project is scheduled to start on July 11, estimated 2-3 month duration. To meet that schedule, the contractor will work 2 weekday shifts (8am - 8:30pm) and possibly on a Saturday start time 9am.

July schedule (estimate)

  • 7/11 - 7/12: site preparation
  • 7/13 - 7/15: trucks deliver fencing and equipment; set up fencing around Welch Field
  • 7/18 - 7/26 (~7-10 days): excavation begins at Welch field
    • Impact areas on lower campus include: Welch Field, lower portion of Gleason lawn, north south footpath between Gleason and CSI, and one vault in the paver section of the drivebetween UC and McLaren
    • Excavation activities will involve trenching and jack hammering.
    • Fence placement for the steamline project is scheduled to begin on Monday and Tuesday, July 11th and 12th.
    • All areas within the work zone will be fenced off and covered when work is not in progress. Trenched areas that intersect foot or vehicle traffic in paved areas will be covered withmetal trench plates rated for pedestrian and vehicular traffic.

Malloy Basketball Practice Facility/War Memorial Gym

  • July 11:3:30pm - 7:30pmPower shutdown: Gillson Hall & War Memorial Gym only
  • July 18:Estimated start date for drilling micro piles.Estimated duration 3 weeks
  • Hayes Healy Parking Lot Closed:All levels of HH parking garage are closed. Faculty, Staff, and visitors are encouraged to park at the Koret Lot.

Lone Mountain Trash & Recycling Facility

  • July 11 - 19 - Drywall installation
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available to USF permit holders in the garagesbeneath the new Lone Mtn Residence Hall; visitors may park at Koret Lot.

Loyola Village, Anza Street

  • Exterior Painting & Refresh Project:painting, landscaping, planter box rebuild, repair exterior lighting, gutter replacement, clay roof tile removal/reinstallation.
  • Contractors will move scaffolding as needed to work through exterior sections of the buildings. Some aspects of erecting scaffolding will be noisy at times.
  • Some sheet metal work will be fabrication (cutting & soldering) to be located in the LV garage in an effort to contain noise.
  • Schedule: May 31 - August 19 approximately.

Lone Mountain Viaduct, 330 Parker Ave

  • Structural remedial workof the Lone Mountain viaduct (north side of Lone Mountain campus).
  • Estimated to start August 2022. Details TBD
  • Most work will take place under the road bed. There will be substantial concrete demo work periodically which will be noisy.

Campus Events

  • August 13 - Saturday - Move-In Day. Details to follow
  • September 10 - Saturday - Back to School concert, Ulrich Field, 2-4pm

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “SanFrancisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents ateach site are tasked with making sure workers follow those guidelines and maintain social distancing


Update 06/17/2022

All dates below are best estimates, subject to impacts of weather, and other external impacts, and may change without notice.

War Memorial Gym/Basketball Practice Facility

  • WMG North Lobby -Please note the area remains a construction site and is closed. Please do not enter the area.
  • Malloy Basketball Practice Facility
  • June:ongoing site preparation: soil removal, site fence install, equipment deployment
  • Hayes Healy Parking Lot Closed:All levels ofHH parking garage are closed. Faculty, Staff, and visitors are encouraged to park at the two garages underneath Lone Mountain East Residence Hall.

Lone Mountain Trash & Recycling Facility

  • Week of June 20 -Completeerection of roof trusses. Installation of exterior sheathing.
  • Electrical tie-in - date TBD: install electrical conduit inside LMNorth. No expected interruption of power.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn Residence Hall.

Loyola Village, Anza Street

  • Exterior Painting & Refresh Project:painting, landscaping, planter box rebuild, repair exterior lighting, gutter replacement, clay roof tile removal/reinstallation.
  • Contractors will move scaffolding as needed to work through exterior sections of the buildings. Some aspects of erecting scaffolding will be noisy at times.
  • Some sheet metal work willbe fabricated (cutting & soldering) to be located in the LV garage tocontain noise.
  • Scheule:
    • May 31 - August 19 approximately.
    • Saturday June 18: Scaffolding installation. Central and south sides of the building Saturday work starts at 9am.
    • Saturday June 25: On the 25th, a crane will be placed on Anza Street to hoist scaffolding in to the courtyards. Parking in front of the buildings along Anza street will be blocked off.

Lone Mountain Viaduct, 330 Parker Ave

  • Structural remedial workof the Lone Mountain viaduct (north side of Lone Mountain campus).
  • Start date changed: estimated to start August 2022. Details TBD
  • Most work will take place under the roadbed. Therewill be substantial concrete demo workperiodically, which will be noisy.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distancing


UPDATE 06/2/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

War Memorial Gym/Basketball Practice Facility

  • WMG North Lobby -Punch walk completed.Please note the area remains a construction site and is closed. Please do not enter the area.
  • Malloy Basketball Practice Facility
  • June:ongoing site preparation: soil removal, site fence install, equipment deployment
  • Hayes Healy Parking Lot Closed:All levels ofHH parking garage are closed. Faculty, Staff, and visitors are encouraged to park at the two garages underneath Lone Mountain East Residence Hall.

Lone Mountain Trash & Recycling Facility

  • Thru June 8 (estimate) - erection of steel frame. Aspects of this work will be noisy.
  • June 6 -17Erection of roof trusses
    • Electrical tie-in - date TBD: install electrical conduit inside LMNorth. No expected interruption of power.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn Residence Hall.

Loyola Village, Anza Street

Exterior Painting & Refresh Project:painting, landscaping, planter box rebuild, repair exterior lighting, gutter replacement, clay roof tile removal/reinstallation.

  • Schedule: May 31 - August 19 approximately.
  • May 31Begin installation of scaffolding.Scaffolding will start on the south side of thebuilding Contractors will move scaffolding as needed to work through exterior sections of thebuildings. Some aspects of erecting scaffolding will be noisy at times. Some sheet metal work will be a fabrication (cutting & soldering) to be located in the LV garage in an effort tocontain noise.

Lone Mountain Viaduct, 330 Parker Ave

Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).

  • Estimated schedule June 1, 2022 - May 2023.
    • Most work will take place under the road bed. Therewill be substantial concrete demo workperiodically which will be noisy. Details will follow.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distancing


UPDATE 05/27/2022

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

War Memorial Gym/Basketball Practice Facility

  • WMG North Lobby-Punch walk completed.Please note the area remains a construction site and is closed. Please do not enter the area.
  • Malloy Basketball Practice Facility
    • May 31 Begin concrete demo & drilling for micropiles in lower levels of HH garage
    • May 31 Power Shut downto test aspe. cts of the electrical system that serves Gillson and War Memorial. Power to Gillson and WMG will be shut down for 8 hours starting at 7am.
    • Hayes Healy Parking Lot Closed:All levels of HH parking garage will close for the duration of the project starting May 23, 2022. Faculty, Staff, and visitors are encouraged to parkat the two garages underneath Lone Mountain East Residence Hall.
    • May 30 Memorial Day - No work at site.Light work on Friday May 27.

Lone Mountain Trash & Recycling Facility

  • May 31-Delivery of roof trusses
  • May 23-June 8 (estimate) - erection of steel frame. Aspects of this work will be noisy.
  • June 1-3. Delivery and erection of scaffolding.
  • June 2. Tie-in for the fire pump reroute. Power Outage in LMN and LMM estimated 2hours.
  • June 6-17Delivery & rrection of roof trusses
  • Electrical tie-in - date TBD: install electrical conduit inside LMNorth. Consideration underway of re-routing the original planned path to avoid excessive noise. No expectedinterruption of power.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available to USF permit holdersin the garages beneath the new Lone Mtn Residence Hall.
  • May 30 Memorial Day - No work at site.Light work on Friday May 27.

Loyola Village, Anza Street

  • Exterior Painting & Refresh Project:painting, landscaping, planter box rebuild, repair exterior lighting, gutter replacement, clay roof tile removal/reinstallation.
  • Schedule: May 31 - August 19 approximately.
  • May 31Begin installation of scaffolding.Scaffolding will start on the south side of thebuilding Contractors will move scaffolding as needed to work through exterior sections of thebuildings. Some aspects of erecting scaffolding will be noisy at times. Some sheet metal work will be fabrication (cutting & soldering) to be located in the LV garage in an effort tocontain noise.

Lone Mountain Viaduct, 330 Parker Ave

  • Structural remedial work of the Lone Mountain viaduct (north side of Lone Mountain campus).
  • Estimated schedule June 1, 2022 - May 2023.
  • Most work will take place under the road bed. Therewill be substantial concrete demo workperiodically which will be noisy. Details will follow.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create,adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field SafetyGuidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each siteare tasked with making sure workers follow those guidelines and maintain social distance.


UPDATE 05/23/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

War Memorial Gym/Basketball Practice Facility

  • WMG North Lobby
    • Punch walk completed.Please note the area remains a construction site and is closed. Please do not enter the area.
  • Malloy Basketball Practice Facility
    • May 20 - 26Installation of site's perimeterfencing
    • May 23 Surface excavation activities south end of site near Gillson & Cardiac Hill
    • May 31 Beginconcrete demo & drilling for micropiles in lower levels of HH garage
    • May 31 Power Shut downto test aspects of the electrical system that serves Gillson and War Memorial. Power to Gillson and WMG will be shut down for 8 hours starting at 7am.
    • Hayes Healy Parking Lot Closed:All levels ofHH parking garage will close for the duration of the project starting May 23, 2022. Faculty, Staff, and visitors are encouraged to park at the two garages underneath Lone Mountain East Residence Hall.
    • May 30 Memorial Day - No work at site.Light work on Friday May 27.

Lone Mountain Trash & Recycling Facility

  • May 24-Debris off-haul, one truck
  • May 31-Delivery of roof trusses
  • May 23-June 8 (estimate) - erection of steel frame. Aspects of this work will be noisy.
  • June 1-3.Delivery and erection of scaffolding.
  • June 6-17Erection of roof trusses
  • Electrical tie-in - date TBD: install electrical conduit inside LMNorth. Consideration underway of re-routing the original planned path to avoid excessive noise. No expected interruption of power.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn Residence Hall.
  • May 30 Memorial Day - No work at site.Light work on Friday May 27.

Loyola Village, Anza Street

  • Exterior Painting & Refresh Project
    • Scope: painting, landscaping, planter box rebuild, repair exterior lighting, gutter replacement, clay roof tile removal/reinstallation. May 31 - August 19 approximately.
  • May 31Begin installation of scaffolding.Scaffolding will start on the south side of thebuilding Contractors will move scaffolding as needed to work through exterior sections of the buildings. Some aspects oferecting scaffolding will be noisy at times. Some sheet metal work will be fabrication (cutting & soldering) to be located in the LV garage in an effort to contain noise.

Campus Events

  • May 26- Thursday - St Ignatius PreparatoryBaccalaureate Reception 8:30pm-10pm
  • May 28- Saturday. St Ignatius PreparatoryWar Memorial Gym 8am set up. 8:30pm-10pm

Upcoming Projects

  • Lone Mountain Viaduct, 330 Parker Ave
    • Seismic retrofit of Lone Mountain viaduct (north side of Lone Mountain campus). Estimated schedule June 1, 2022 - May 2023. Most work will take place underthe road bed. There will be substantial concrete demo workperiodically. Details will follow.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain soci


UPDATE 05/13/22:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

War Memorial Gym/Basketball Practice Facility

Noisy work including drilling & saw cutting will not occur May 13-19 inrecognitionof Final Exams.

  • WMG North Lobby -The construction of the USF Athletics Hall of Fame is nearing completion. Final painting through May 16; punch walk May 20.Please note the area remains a construction site and is closed. Please do not enter the area.
  • Malloy Basketball Practice Facility
    • May 15 - 20Site preparation activities continue
    • Hayes Healy Parking Lot:May 9th: lowest level of the garage will be closed.All levels ofHH parking garage will close for the duration of the project starting May 23, 2022. Faculty, Staff, and visitors are encouraged to park at the two garages underneath Lone Mountain East Residence Hall. No drilling or saw cutting will occur May 13-19 for Finals.
    • May 30 -Beginconcrete demo & drilling for micropiles in lower levels of HH garage

Lone Mountain Trash & Recycling Facility

Noisy work including drilling, saw cutting, & framing will not occur May 13-19 inrecognitionof Final Exams.

  • Electrical tie-in - date TBD: install electrical conduit inside LMNorth. Consideration underway of re-routing the original planned path to avoid excessive noise. No expected interruption of power.
  • May 20-Delivery, structural steel. One large truck, flagmen on site. Please use caution along the viaduct at that time.
  • May 23-June 8 (estimate) - erection of steel frame. Aspects of this work will be noisy.
  • Project competition estimated mid August.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn Residence Hall.

Campus Events

  • May 19 -Thursday - USFCommencement family & student reception, Sobrato Center 8p - 10pm
  • May 19-21 Thursday - Saturday. USFSpring Commencement ceremonies at various campus venues
  • May 26- Thursday - St Ignatius PreparatoryBaccalaureate Reception 8:30pm-10pm
  • May 28 -Saturday. St Ignatius PreparatoryWar Memorial Gym 8am set up starts. 8:30pm-10pm

Upcoming Projects

  • Lone Mountain Viaduct, 330 Parker Ave
    • Seismic retrofit of Lone Mountain viaduct (north side of Lone Mountain campus). Estimated schedule June 1, 2022 - May 2023. Most work will take place underthe road bed. There will be substantial concrete demo workperiodically. Details will follow.

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


UPDATE 05/06/22:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

War Memorial Gym/Basketball Practice Facility

Noisy work including drilling & saw cutting will not occur May 13-19 inrecognitionof Final Exams.

  • WMG North Lobby -The construction of the USF Athletics Hall of Fame is nearing completion. Final painting and punch list walks start May 9.Please note the area remains a construction site and is closed. Please do not enter the area.
  • Malloy Basketball Practice Facility -USF will construct an elevated one-story basketball practice facility(approximately 15,500 square feet) adjacent to the existing War Memorial Gymnasium (WMG) building. The new addition,to be built over an existing surface parking lot, would contain a new basketball practice facility and a newmezzanine level with restrooms, coaches’ offices, andathletic conference rooms. (PlanningCommission Motion 20942, July 22,2021). The work will be sometimes be noisy and disruptive over the next 12 or 14 months, particularly fo offices on the east side of WMG.
    • May 9Site preparation activities continue: soil removal, tree/stump removal, installation of site perimeter fencing, installation of temporary pedestrian paths. Please pay attention.
    • May 9-12Demo pony wall at pathway stair, will involve saw cutting and be noisy.
    • Reconfigure power: cutover & splicing: Date to be determined. Will involve an approximately 8 hour power shut down in area east of WMG.
    • Hayes Healy Parking Lot:May 9th: lowest level of the garage will be closed.All levels ofHH parking garage will close for the duration of the project starting May 23, 2022. Faculty, Staff, and visitors are encouraged to park at the two garages underneath Lone Mountain East Residence Hall. No drilling or saw cutting will occur May 13-19 for Finals. May 30 Drilling for micropiles in lower levels of HH garage

Lone Mountain Trash & Recycling Facility

Noisy work including drilling, saw cutting, & framing will not occur May 13-19 inrecognitionof Final Exams.

  • Electrical tie-in - date TBD: install electrical conduit inside LMNorth. Consideration underway of re-routing the original planned path to avoid excessive noise. No expected interruption of power.
  • May 10-shot crete building walls. Date is contingent upon completion of foundation concrete pour, above.
  • May 23-Delivery, structural steel. One large truck, flagmen on site. Please use caution along the viaduct at that time.
  • May 23-June 8 (estimate) - erection of steel frame. Aspects of this work will be noisy.
  • Project competition estimated mid August.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn

Campus Events

  • May 19 - Thursday - USFCommencement family & student reception, Sobrato Center 8p - 10pm
  • May 19-21 - Thursday - Saturday. USFSpring Commencement ceremonies at various campus venues
  • May 26- Thursday - St Ignatius PreparatoryBaccalaureate Reception 8:30pm-10pm
  • May 28- Saturday -St Ignatius PreparatoryWar Memorial Gym 8am set up starts. 8:30pm-10pm

Upcoming Projects

  • Lone Mountain Viaduct, 330 Parker Ave -
    • Seismic retrofit of Lone Mountain viaduct (north side of Lone Mountain campus). Estimated schedule June 1, 2022 - May 2023. Most work will take place underthe road bed. There will be substantial concrete demo workperiodically. Details will follow.

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


UPDATE 05/02/22:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • May 2-concrete pour for building foundation Approx 10-15 trucks. Trucks will be staged remotely and managed by flagmen and radio control. Please use caution near the construction area and on the viaduct.
  • Electrical tie-in - date TBD: install electrical conduit inside LMNorth. Consideration underway of re-routing the original planned path to avoid excessive noise. No expected interruption of power.
  • May 10-shot crete building walls. Date is contingent upon completion of foundation concrete pour, above.
  • May 11-Delivery, structural steel. One large truck, flagmen on site. Please use caution along the viaduct at that time.
  • May 13-27 (estimate) -framing activities. Work that will be noisy will begin after 9am during Exam Week.
  • Project competition estimated mid August.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn Residence Hall.

War Memorial Gym/Basketball Practice Facility preliminary work

  • Malloy Basketball Practice Facility
    • USF will construct an elevated one-story basketball practice facility(approximately 15,500 square feet) adjacent to the existing War Memorial Gymnasium (WMG) building. The new addition,to be built over an existing surface parking lot, would contain a new basketball practice facility and a newmezzanine level with restrooms, coaches’ offices, andathletic conference rooms. (PlanningCommission Motion 20942, July 22,2021). The work will be sometimes be noisy and disruptive over the next 12 or 14 months, particularly fo offices on the east side of WMG.
    • May 2 Site preparation activities begin: soil removal etc.
    • Reconfigure power: cutover & splicing: Date to be determined. Will involve an approximately 8 hour power shut down in area east of WMG.
    • Parking:Upper deck of Hayes Healy lot will remain closed.

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hall
    • planting replacement trees is continuing, depending upon supply chain. Planting scheme will be to place 8-10 New Zealand Christmas trees along the top of the birm. Plantings on the hillside will include Liquid Amber, Japanese Flowering Plums, and Magnolias. (Approx 8-10 each)

Campus Events

  • May 7 - Saturday - Student EventSchool of Education Parking10am - 2pm. Live music 12 - 1.
  • May 19 -Thursday USFCommencement family & student reception, Sobrato Center 8p - 10pm
  • May 19-21 - Thursday - Saturday. USFSpring Commencement ceremonies
  • May 26- Thursday - St Ignatius PreparatoryBaccalaureate Reception 8:30pm-10pm
  • May 28- Saturday. St Ignatius PreparatoryWar Memorial Gym 8am set up starts. 8:30pm-10pm

Upcoming Projects

  • Lone Mountain Viaduct, 330 Parker Ave
    • Seismic retrofit of Lone Mountain viaduct (north side of Lone Mountain campus). Estimated schedule June 1, 2022 - May 2023. Most work will take place underthe road bed. There will be substantial concrete demo workperiodically. Details will follow.

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


UPDATE 04/22/22:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Harney Science Center

  • SaturdayApril 23; Saturday April 28-Interior work on installing ventilation ducts from 1st floor to roof will require saw cutting through floor slabs on two Saturdays noted. Workers will arrive around 7:30 for set up. Saw cutting will start after 9am.

Lone Mountain Trash & Recycling Facility

  • April 28(date estimate)-concrete pour for building foundation Approx 10-15 trucks. Trucks will be staged remotely and managed by flagmen and radio control. Please use caution near the construction area and on the viaduct. (Note: the date for this pour has changed over the last few weeks due to supply line and other external contingencies.)
  • April 28 - 29(date estimate)-Electrical tie-in: install electrical conduit inside LMNorth. Electricians will run a line from LMN 2nd floor (near IST Help Desk entrance) to laundry room below and Conf room 116. Work on 2nd floor requires drilling a core through floor to lower level which will be noisy for a short time. No expected interruption of power.
  • May 2(date estimate)-shot crete building walls. Date is contingent upon completion of foundation concrete pour, above.
  • Project competition estimated early August.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn

War Memorial Gym/Basketball Practice Facility preliminary work

  • Hall of Fame/WMG:Tuesday 4/26: paint interior walls and ceiling. Work on interior space by general contractor expected to be completed by May 2.
  • Reconfigure power: cutover & splicing: Date to be determined. Will involve an approximately 8 hour power shut down in area east of WMG.
  • Site preparation activities: soil removal etc. Estimated start in about 1 week.
  • Parking:Upper deck of Hayes Healy lot will remain closed.

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized. The planting birm scheme will be to place 8-10 New Zealand Christmas trees along the top of the Z. Plantings on the hillside will include Liquid Amber, Japanese Flowering Plums, and Magnolias. (Approx 8-10 each)

Campus Events

  • April 29 Gleeson Plaza 11am -3pm Student Event with amplified sound (SF permit acquired)
  • April 29 School of Education parking lot. 3pm-7pmGleeson Plaza 3pm -7pm.Student Event with music and amplified sound (SF permit acquired)
  • May 19-21 Thursday - Saturday. Spring Commencement ceremonies

Upcoming Projects

  • Malloy Basketball Practice Facility
    • USF will construct an elevated one-story basketball practice facility(approximately 15,500 square feet) adjacent to the existing War Memorial Gymnasium (WMG) building. The new addition,to be built over an existing surface parking lot, would contain a new basketball practice facility and a newmezzanine level with restrooms, coaches’ offices, andathletic conference rooms. (PlanningCommission Motion 20942, July 22,2021).Project start date estimated May 2, 2022. Details will follow.
  • Lone Mountain Viaduct, 330 Parker Ave
    • Seismic retrofit of Lone Mountain viaduct (north side of Lone Mountain campus). Estimated schedule June 1, 2022 - May 2023. Most work will take place underthe road bed. There will be substantial concrete demo workperiodically. Details will follow.

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


UPDATE 04/15/22:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • April 20 or 21(date estimate)-concrete pour for building foundation Approx 10-15 trucks. Trucks will be staged remotely and managed by flagmen and radio control. Please use caution near the construction area and on the viaduct.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn

War Memorial Gym/Basketball Practice Facility preliminary work

  • April 19:Micropile strength test. Moderate percussive noise.
  • Reconfigure power: cutover & splicing: Date to be determined. Will involve an approximately 8 hour power shut down in area east of WMG.
  • Site preparation activities: soil removal etc. Estimated start in about 2 weeks.
  • Parking:Upper deck of Hayes Healy lot will remain closed.

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized. Planting scheme will be to place 8-10 New Zealand Christmas trees along the top of the birm. Plantings on the hillside will include Liquid Amber, Japanese Flowering Plums, and Magnolias. (Approx 8-10 each)

Events

  • Thursday - Saturday May 19-21 Spring Commencement ceremonies

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


UPDATE 04/08/22:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • MondayApril 11 -rebar inspection andconcrete pour. One truck. (April 5 pour canceled)
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn

War Memorial Gym/Basketball Practice Facility preliminary work

  • Reconfigure power: cutover & splicing: Date to be determined. Will involve an approximately 8 hour power shut down in area east of WMG.
  • Site preparation activities: soil removal etc. Estimated start in about 2 weeks.
  • Parking:Upper deck of Hayes Healy lot will remain closed.

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized. Planting scheme will be to place 8-10 New Zealand Christmas trees along the top of the birm. Plantings on the hillside will include Liquid Amber, Japanese Flowering Plums, and Magnolias. (Approx 8-10 each)

Campus Events

  • Saturday April 9 8:30 am- 3:45pm Campus Open House for newly admitted students
  • Thursday - Saturday May 19-21 Spring Commencement ceremonies

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


UPDATE 04/01/22:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • TuesdayApril 5 -viaduct pour back. One truck
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn

War Memorial Gym/Basketball Practice Facility

  • April 5 & 6, Drill two test piles: adjacent to east wall of WMG. Small rig; moderate noise
  • Parking:Upper deck of Hayes Healy lot will remain closed.

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized. Planting scheme will be to place 8-10 New Zealand Christmas trees along the top of the birm. Plantings on the hillside will include Liquid Amber, Japanese Flowering Plums, and Magnolias. (Approx 8-10 each)

Campus Events

  • Thursday May 26 8:30pm - 10pm - St Ignatius High SchoolGraduationReception at Sobrato Center/WMG
  • Saturday May 28 10:00 am- 12pm - St Ignatius High SchoolGraduationat Sobrato Center/WMG

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


Updates 03/25/22:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • March 28 - (estimate) April 1: Contractor will be drillingstructural piers at theTrashFacility site. Work starts after 8am each day. The work will involve large equipment and will be noisy.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn Residence Hall.

War Memorial Gym/Basketball Practice Facility

  • Week of March 28:continued installation of ceiling panels, finish flooring, MEP trim, install display cases

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized. Planting scheme will be to place 8-10 New Zealand Christmas trees along the top of the birm. Plantings on the hillside will include Liquid Amber, Japanese Flowering Plums, and Magnolias. (Approx 8-10 each)

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


Updates 03/21/22:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • March 22: Concrete pour at site. 8am start
  • March 25, 26, 28, 29:The contractorwill be drilling structural piers at the Trash Facility site. Work starts after 8am each day andafter 9am on Saturday 3/26.The work will involve large equipment and will be noisy. Also, largeequipment will be delivered on March 23, 24 which could also be noisy during set-up.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn Residence Hall.

War Memorial Gym/Basketball Practice Facility

  • Through March 25:Hayes Healy parking driveway and upper parking lot closed through Mar 25.
  • Week of March 21:installation of ceiling panels, finish flooring, MEP trim, install display cases

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized. Planting scheme will be to place 8-10 New Zealand Christmas trees along the top of the birm. Plantings on the hillside will include Liquid Amber, Japanese Flowering Plums, and Magnolias. (Approx 8-10 each)

University Calendar

  • Basketball practices: visiting teams Tues 3/22 4-6pm; Thurs 3/24 10:15 - noon.

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


Updates 03/11/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • March 13,Saturday: concrete demo workcontinues on the viaduct at the site. Work starts after 9am
  • Concrete Pour.EstimateMarch 16, to be confirmed.
  • Water Shut off at LMNorth -March 19, 8am - noon;Water service will be shut off forLone Mtn North 8am-12noon

Lone Mtn North 8am-12noon

  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn

War Memorial Gym/Basketball Practice Facility

  • Through March 18:Hayes Healy parking driveway and upper parking lot closed through Mar 18.Vehicle access/egress to the parking deck will not be available.The lot will be open on theweekend.
  • March 14:Delivery of flooring materials for Hall of Fame. One large truck is expected for delivery.
  • March 21:installation of ceiling panels

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized.

University Calendar

  • Women’s Basketball: possible invitation to host Women’s NIT Tournament; date TBD

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


Updates 03/04/2022

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • Mar 7:Shotcrete walls
  • Water Shut off at LMNorth -Change of Dateto either March 12 or March 19; to be confirmed asap.Water service will be shut off for Lone Mtn North 8am-12noon.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn.

War Memorial Gym/Basketball Practice Facility

  • Feb 28 - (approx) March 18:Hayes Healy parking driveway and upper parking lot deck east of WMG will be closed Feb 28-(approx) Mar 11. Vehicle access/egress to the parking deck will not be available.The lot will be open on theweekend.
  • March 14:Delivery of flooring materials for Hall of Fame. One large truck expected for delivery.
  • March 21:installation of ceiling panels
  • The Project Contractor has reserved ‘construction parking spaces’ on Golden Gate, along the frontage in front of the UC lot. The restriction hasn’t been enforced in recent weeks, but work at the site is going to pick up . Unauthorized cars using those spaces may be ticketed and/or towed.

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized.

University Calendar

  • March 5Donaroo Concertat War Memorial Gym 7pm - 10pm
    • load-in beginning at 12pm Friday, March 4th - onsite until 11/1130pm. “No park” zones reserved in front of the gym and on turk / stanyan for the trucks
    • load-in continues at 9am on Saturday, March 5th
    • doors at 630pm
    • concert is 7pm - 10:30pm
    • load out beginning at 9am Sunday, March 6th. Complete by about 3pm
    • generator in UC lot will be on/running 3/4 2pm - 11pm, 3/5 9am - 11pm
    • Student entrance will be at WMG south lobby entrance, interior to campus
    • Ticket sales are capped to about 25% capacity due to Covid

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


Updates 2/28/2022

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • Feb 28 - Mar 1finishrebar placement
  • Mar 2:Concrete pour of foundation. Several trucks.
  • Mar 7:Shotcrete walls
  • Mar 14: Water shut Lone Mtn North 5am - 5pm. Water service will be shut off for Lone Mtn North all day March 14
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn

War Memorial Gym/Basketball Practice Facility

  • Feb 28 - (approx) March 11:Hayes Healy parking driveway and upper parking lot deck east of WMG will be closed Feb 28-(approx) Mar 11. Vehicle access/egress to the parking deck will not be available.The lot will be open on theweekend.
  • March 14:Delivery of flooring materials for Hall of Fame. One large truck expected for delivery.
  • The Project Contractor has reserved ‘construction parking spaces’ on Golden Gate, along the frontage in front of the UC lot. The restriction hasn’t been enforced in recent weeks, but work at the site is going to pick up . Unauthorized cars using those spaces may be ticketed and/or towed.
  • Conversion of WMG North Lobby to USF Athletic Hall of Fame continues.
  • Periodic utility work/trenching in landscaped area between WMG, Hayes Healy & Glilson. Landscaped area will be fenced off. Walkways will be open; use caution in the area.

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized.

university calendar

  • March 5Donaroo Concertat War Memorial Gym 7pm - 10pm
    • load-in beginning at 12pm Friday, March 4th - onsite until 11/1130pm. “No park” zones reserved in front of the gym and on turk / stanyan for the trucksload-in continues at 9am on Saturday, March 5th.
    • doors at 630pm
    • concert is 7pm - 1030pm
    • load out beginning at 9am Sunday, March 6th. Complete by about 3pm
    • generator in UC lot will be on/running 3/4 2pm - 11pm, 3/5 9am - 11pm
    • Student entrance will be at WMG south lobby entrance, interior to campus
    • Ticket sales are capped to about 25% capacity due to Covid

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


Updates 2/28/2022

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • Feb 28 - Mar 1finishrebar placement
  • Mar 2:Concrete pour of foundation. Several trucks.
  • Mar 7:Shotcrete walls
  • Mar 14: Water shut Lone Mtn North 5am - 5pm. Water service will be shut off for Lone Mtn North all day March 14
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn

War Memorial Gym/Basketball Practice Facility

  • Feb 28 - (approx) March 11:Hayes Healy parking driveway and upper parking lot deck east of WMG will be closed Feb 28-(approx) Mar 11. Vehicle access/egress to the parking deck will not be available.The lot will be open on theweekend.
  • March 14:Delivery of flooring materials for Hall of Fame. One large truck expected for delivery.
  • The Project Contractor has reserved ‘construction parking spaces’ on Golden Gate, along the frontage in front of the UC lot. The restriction hasn’t been enforced in recent weeks, but work at the site is going to pick up . Unauthorized cars using those spaces may be ticketed and/or towed.
  • Conversion of WMG North Lobby to USF Athletic Hall of Fame continues.
  •  
  • Periodic utility work/trenching in landscaped area between WMG, Hayes Healy & Glilson. Landscaped area will be fenced off. Walkways will be open; use caution in the area.

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized.

university calendar=""

  • March 5Donaroo Concertat War Memorial Gym 7pm - 10pm
  • load-in beginning at 12pm Friday, March 4th - onsite until 11/1130pm. “No park” zones reserved in front of the gym and on turk / stanyan for the trucks
  • load-in continues at 9am on Saturday, March 5th.
  • doors at 630pm
  •  
  • concert is 7pm - 1030pm
  • load out beginning at 9am Sunday, March 6th. Complete by about 3pm
  • generator in UC lot will be on/running 3/4 2pm - 11pm, 3/5 9am - 11pm
  • Student entrance will be at WMG south lobby entrance, interior to campus
  • Ticket sales are capped to about 25% capacity due to Covid

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


Update 02/18/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • Feb 21: No work at site
  • Feb 22 - Mar 1 Framing and site preparation continue
  • Mar 2: Concrete pour of foundation. Several trucks, details tbd
  • Mar 7: Shotcrete walls.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available to USF permit holders in the garages beneath the new Lone Mtn Residence Hall.

War Memorial Gym/Basketball Practice Facility

  • Feb 21: No work at site
  • Feb 28 - March 4: Installation of new storm drain in along WMG drive, east side. The driveway and upper parking lot deck east of WMG will be closed and vehicle access/egress to the parking deck will not be available. (The parking lot will be open the week of Feb 18)
  • The Project Contractor has reserved ‘construction parking spaces’ on Golden Gate, along the frontage in front of the UC lot. The restriction hasn’t been enforced in recent weeks, but work at the site is going to pick up . Unauthorized cars using those spaces may be ticketed and/or towed.
  • Conversion of WMG North Lobby to USF Athletic Hall of Fame continues.
  • Periodic utility work/trenching in landscaped area between WMG, Hayes Healy & Glilson. Landscaped area will be fenced off. Walkways will be open; use caution in the area.

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hall plans for replacement trees are being finalized.

University Calendar

  • March 5 Donaroo campus concert - Either WMGym or Koret (TBD)
    • load-in beginning at 12pm Friday, March 4th - onsite until 11/1130pm.
    • “No park” zones reserved in front of the gym and on turk / stanyan for the trucks
    • load-in continues at 9am on Saturday, March 5th
    • doors at 630pm
    • concert is 7pm - 1030pm
    • load out beginning at 9am Sunday, March 6th. Complete by about 3pm
    • generator in UC lot will be on/running 3/4 2pm - 11pm, 3/5 9am - 11pm
    • If at WMG, student entrance will be at south lobby entrance, off Golden Gate
    • Ticket sales are capped to about 25% capacity due to Covid

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals owned by students, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. We appreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.


Update 2/11/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • Week of Feb 14-19: Debris removal from site. Please exercise caution in the area.
  • Form work for lower and upper levels continues. Plumbers on site for piping work. Will involve truck traffic and some noise. Please exercise caution when near the site.
  • Feb 18 or Feb 23 tbd: Concrete pour.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available to USF permit holders in the garages beneath the new Lone Mtn Residence Hall.

War Memorial Gym/Basketball Practice Facility

  • Week of Feb 14-19: Installation of new storm drain in along WMG drive, east side. The driveway and upper parking lot deck east of WMG will be closed and vehicle access/egress to the parking deck will not be available.
  • The Project Contractor has reserved ‘construction parking spaces’ on Golden Gate, along the frontage in front of the UC lot. The restriction hasn’t been enforced in recent weeks, but work at the site is going to pick up so, effective today 2/4/22, Cahill will start ticketing unauthorized cars using those spaces while also reserving the right to tow vehicles.
  • Conversion of WMG North Lobby to USF Athletic Hall of Fame continues.
  • Periodic utility work/trenching in landscaped area between WMG, Hayes Healy & Glilson. Landscaped area will be fenced off. Walkways will be open; use caution in the area.

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hall plans for replacement trees are being finalized.

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned by students, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. We appreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, and implement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by City Administrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workers follow those guidelines and maintain social distance.


Update 02/07/2022:

Lone Mountain Trash & Recycling Facility - addendum

  • Feb 9, possibly Feb 10: Rebar delivery to site. Will involve a large tractor-trailer entering Lo Schiavo Drive from Parker. Traffic on Parker and along the Drive may be briefly disrupted. Flagmen will be on site.

Update 2/4/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • Form work for lower and upper levels continues. Plumbers on site for piping work. Will involve truck traffic and some noise. Please exercise caution when near the site.
  • Feb 17: Concrete pour. Details such as number of trucks etc TBD.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn Residence Hall.

War Memorial Gym/Basketball Practice Facility

  • The Project Contractor has reserved ‘construction parking spaces’ on Golden Gate, along the frontage in front of the UC lot. The restriction hasn’t been enforced in recent weeks, but work at the site is going to pick up so, effective today 2/4/22, Cahill will start ticketing unauthorized cars using those spaces while also reserving the right to tow vehicles.
  • Conversion of WMG North Lobby to USF Athletic Hall of Fame continues.
  • Periodic utility work/trenching in landscaped area between WMG, Hayes Healy & Glilson. Landscaped area will be fenced off. Walkways will be open; use caution in the area.
  • Week of Feb 14-19: Installation of new storm drain in along WMG drive, east side. The driveway and upper parking lot deck east of WMG will be closed and vehicle access/egress to the parking deck will not be available.

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized.

University Calendar

  • Spring semester 1/24/22 -5/19/22
  • USF Athletics
    • Tuesday, Feb 8: Men’s Basketball Time 7pm
    • Saturday, Feb 5: Women’s Basketball Time 2pm

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

 

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


Update 1/28/2022:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Dining Commons

  • Back lot:fabrication of small concrete slab.
  • 1/24-1/28 build forms
  • Concrete pour – Tuesday Feb 1, 8a-12p; 2 trucks.

Lone Mountain Trash & Recycling Facility

  • Ongoing installation of grade beams and foundation walls . Will involve truck traffic and some noise. Please exercise caution when near the site.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn Residence Hall.

War Memorial Gym/Basketball Practice Facility

  • Conversion of WMG North Lobby to USF Athletic Hall of Fame continues.
  • Periodic utility work/trenching in landscaped area between WMG, Hayes Healy & Glilson. Landscaped area will be fenced off. Walkways will be open; use caution in the area.
  • Friday Jan 28: Utility work at sidewalk/driveway entrance to the parking deck east of WMGym, between the Gym and Hayes Healy. The lot will be closed from about midnight Jan 27 until noon January 28. The work is excepted to take about 4 hoursonFriday Jan 28, between 7am - 12pm; noisy work if any will start after 8am. Once work begins started, vehicle access/egress to the parking deck will not be available.
  • Week of Feb 14-19: Installation of new storm drain in along WMG drive, east side. The driveway and upper parking lot deck east of WMG will be closed and vehicle access/egress to the parking deck will not be available.

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized.

University Calendar

  • Spring semester 1/24/22 -5/19/22
  • USF Athletics
    • Monday Jan 29: Men's Basketball Time 4pm
    • Tuesday Feb 8: Men’s Basketball Time 7pm
    • Thursday Jan 22: Women’s Basketball Time 2pm
    • Thursday Feb 3: Women’s Basketball Time 6pm
    • Saturday Feb 5: Women’s Basketball Time 2pm

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals which owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c April 29,2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020 and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


1/21/2022 Updates:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Dining Commons

  • Back lot:fabrication of small concrete slab: 1/24-1/28 build forms. The concrete pour – soon after, date TBD

Lone Mountain Trash & Recycling Facility

  • Foundation Wall concrete pour – 1/24/22. Will involve truck traffic and some noise. Please exercise caution when near the site.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn Residence Hall.

War Memorial Gym/Basketball Practice Facility

  • Conversion of WMG North Lobby to USF Athletic Hall of Fame continues.
  • Tuesday, Jan 25: Utility work/trenching in the landscaped area between WMG, Hayes Healy & Gilson. Landscaped area will be fenced off. Walkways will be open; use caution in the area.
  • Friday, Jan 28: Utility work at sidewalk/driveway entrance to the parking deck east of WMGym, between the Gym and Hayes Healy. The lot will be closed from about midnight Jan 27 until noon January 28. The work is excepted to take about 4 hoursonFriday, Jan 28, between 7 am - 12 pm; noisy work if any will start after 8 am. Once work begins started, vehicle access/egress to the parking deck will not be available.

Lone Mountain Residence Hall (LME)

  • Eastside of LME Res Hallplans for replacement trees are being finalized.

University Calendar

  • Spring semester 1/24/22 -5/19/22
  • USF Athletics
    • Thursday, Jan 27: Men’s Basketball Time 7 pm
    • Monday, Jan 29: Men's Basketball Time 4 pm
    • Tuesday, Feb 8: Men’s Basketball Time 7 pm
    • Thursday, Jan 22: Women’s Basketball Time 2 pm
    • Thursday, Feb 3: Women’s Basketball Time 6 pm
    • Saturday, Feb 5: Women’s Basketball Time 2 pm

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


1/14/2022 Update:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • Concrete Pour – 1/18/22
  • Concrete Pour – 1/19/22
  • Foundation Wall concrete Pour – 1/24/22
  • Lumber Deliveries (will require off-loading on Parker Ave) – 1/18 & 1/20/22. Flagmen will be present

The above activities will involve truck traffic and some noise. Please exercise caution when near the site.

  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn Residence Hall.

War Memorial Gym

  • Conversion of WMG North Lobby to USF Athletic Hall of Fame continues.
  • Tree removal, east side: Jan 18 and Jan 21, 8:30a - 3pm

Lone Mountain Residence Hall (LME)

  • East side of LME Res Hallplans for replacement trees are being finalized.

University Events

  • USF Holiday schedule
  • Intersession 1/4/22 - 1/21/22
  • Spring semester 1/24/22 -5/19/22
  • USF Athletics
    • Saturday, Jan 15: Men’s Basketball Time 8pm TV trucks at campus
    • Monday, Jan 18: Women’s Basketball Time 5 pm
    • Thursday, Jan 20: Women’s Basketball Time 6 pm

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animals owned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29, 2020.USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


01/07/2021 Update:

All dates below are best estimates, subject to impacts of weather, other external impacts, and may change without notice.

Lone Mountain Trash & Recycling Facility

  • Thru Jan 14 (estimated). Recent rainstorms have occasionally delayed site work & excavation. Drilling & placement of soldier beams, installation of retaining wall continue. Trucks will use LoSchiavo Drive for off-hauling. One truck delivery of rebar is estimated at Jan 14. Some parts of this work are moderately noisy.
  • Parking on the Lo Schiavo Drive viaduct has been reduced. The west portion of the ramp is reserved for construction parking. Alternative parking is available toUSF permit holders in the garages beneath the new Lone Mtn Residence Hall.

War Memorial Gym

  • Conversion of WMG North Lobby to USF Athletic Hall of Fame continues.

Lone Mountain Residence Hall (LME)

  • Tree removal, east side of LME Res HallPlans for replacement trees are being finalized.

University Events

  • USF Holiday schedule
    • Intersession 1/4/22 - 1/21/22
    • Spring semester 1/24/22 -5/19/22
  • USF Athletics
    • Thursday Jan 13: Men’s Basketball Time 8pm, TV trucks at campus
    • Saturday Jan 15: Men’s Basketball Time 8pm TV trucks at campus.
    • Monday Jan 18: Women’s Basketball Time 5pm
    • Thursday Jan 20: Women’s Basketball Time 6pm

Dogs on USF Campus:

USF policy requires that all dogs on campus must be leashed at all times. Exceptions apply only to service animals and emotional support animalsowned bystudents, faculty, or staff and which are registered with USF Disability Services. All persons attending animals on campus are required to pick up after their animals. Weappreciate your cooperation.

Covid-19

Construction at USF’s project sites continues in accordance with San Francisco's Department of Public Health Order C19-07c on April 29, 2020. USF requires all contractors working on campus sites to adhere to Public Health guidelines on social distancing and safety guidelines. Each general contractor has been required to create, adopt, andimplement a written plan conforming with the recommendations of the “San Francisco Construction Industry Consensus - Best Practices COVID-19 / Construction Field Safety Guidelines” issued by CityAdministrator Naomi M. Kelly on April 1, 2020, and the San Francisco Department of Public Health Order C19-07c April 29, 2020. Superintendents at each site are tasked with making sure workersfollow those guidelines and maintain social distance.


2/14/2019 Update:

Early Morning Equipment Pickup

A large piece of equipment is scheduled to be delivered on Tuesday, February 19 at approximately 4:00 a.m. As with other larger equipment, the size of the truck required for hauling the equipment triggers travels time restrictions required by the City of San Francisco. Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise. We apologize for the disruption and inconvenience.

Work on Water Lines

Work on campus water lines and connections to City services on Turk is scheduled to begin this week, weather allowing. The work on Turk will at times be noisy and will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. We will post the work dates when they are finalized.

Excavation & Off-Hauling

Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues. Flagmen are positioned at the job site gates and at the middle spur of Lone Mountain. Truck bosses manage truck traffic to ensure truckers follow prescribed routes. Please use caution at the perimeter of the job site. Early Morning Equipment Pickup a large piece of equipment is scheduled to be picked up Thursday, February 7 at approximately 4:00 a.m. As with other larger equipment, the size of the truck required for hauling the equipment triggers travels time restrictions required by the City of San Francisco. Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise. We apologize for the disruption and inconvenience.

Work on Water Lines

The start date for work on campus water lines and connections to City services on Turk has been pushed to February. The work on Turk will at times be noisy and will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. We will post the work dates when they are finalized.


2/6/2019 Update:

Excavation & Off-Hauling

Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues. Flagmen are positioned at the job site gates. In particular, Thursday and Friday (2/7&8/19) @ 7:00 am off haul soil out of the construction site’s west gate will begin, the middle spur of Lone Mountain Drive will begin. Additional flaggers will be provided.


1/30/2019 Update:

Early Morning Equipment Pickup

A large piece of equipment is scheduled to be picked up Thursday, January 31 at approximately 4:00 a.m.  As with other larger equipment, the size of the truck required for hauling the equipment triggers travels time restrictions required by the City of San Francisco.  Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise.  We apologize for the disruption and inconvenience.

Work on Water Lines

The start date for work on campus water lines and connections to City services on Turk has been pushed to February. The work on Turk will at times be noisy and will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. We will post the work dates when they are finalized. 

Excavation & Off-Hauling

Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues. Flagmen are positioned at the job site gates. Two truck bosses will manage truck traffic to ensure truckers follow prescribed routes. 


1/17/2019 Update:

Work on Water Lines

The work on campus water lines and connections to City services on Turk will start January 19. The work on Turk will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. Expected end date is January  31.

Excavation & Off-Hauling

Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues. Flagmen are positioned at the job site gates. Two truck bosses will manage truck traffic to ensure truckers follow prescribed routes.

Holiday Schedule

January 18, MLK Holiday - Contractors will be working at the site.

February 18, President’s Day - No work at the site is planned.


12/19/2018 Update:

Work on Water Lines

The work on campus water lines and connections to City services on Turk, originally scheduled to start this week, has been postponed until January. The work on Turk will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. We will share the work dates with you when they are finalized. 

Schedule

USF recently made the decision to change the construction start time to 7 am, M-F, and 8 am Saturdays to allow more trucks to work to be performed on a daily basis and to meet the overall schedule. Currently, trucks off haul excavated earth to a site two to three hours away from campus. The expanded timeframe will allow significantly more loads to be removed from the site on a daily basis. For example, a truck will be able to make three trips daily instead of two; multiply that by 30 or more trucks daily and the progress is significant. Ultimately, this should reduce the total number of days required to complete the excavation phase.  While we understand and regret the disruption, our intent is to potentially shorten the overall duration of the project. 

Holiday Schedule

Dec 23, 24, 25 - No work on site

Dec 26-29  - Regular work hours

Dec 30,31/Jan 1 - No work on site

Jan 2 - 5 - Regular work hours


12/07/2018 Update:

Excavation & Off-Hauling

Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling continues. Flagmen are positioned at the job site gates. Two truck bosses will manage truck traffic to ensure truckers follow prescribed routes. Overall excavation work is expected to last about 5 months.

Work on Water Lines

Starting on Monday, December 10, contractors will work on campus water lines and connections to City services. Work on the campus water lines will be on December 10 and 11.   The work will move out to connections on Turk after the campus work is complete, specific start date TBD. The work on Turk will involve trenching, temporary re-routing of the sidewalk, installation of two new manholes, and temporary and final paving. This work will be noisy, including the use of jackhammers. We apologize in advance for any disruption. 

We encourage everyone to use extra caution at all times when walking or driving near the job site.


11/21/18 Update: 

There will be no construction activity over Thanksgiving weekend,  11/22 -25.


11/09/2018 Update:

Excavation & Shoring

Excavation at the site continues including soil stabilization, shoring, leveling, grading and off hauling. During off-hauling flagmen will be positioned at the job site gates. Two truck bosses manage truck traffic to ensure truckers follow prescribed routes.  Overall excavation work is expected to last about 5 months. 

There will be some drilling and shoring work on the site on Saturday, November 10, no off hauling is expected. 

We encourage everyone to use extra caution at all times when walking or driving near the job site gates.

Tree placement, Northeast corner

Seven Deodar Cedars (60inch boxes) were put in place on the slope on the northeast corner of the site. The landscape contractor is completing the planting process. 

East Slope grubbing 

The clusters of dead trees in the middle of the slope between the construction site and the Ewing Terrace property line have not yet been removed. The dead trees must be removed in anticipation of future landscaping. The contractor plans to start removing the dead trees as soon as shoring work in that area is complete. We have asked them to leave as much greenery on the slope as possible. Any open ground left after removal will be covered by wattles and other material to prevent erosion. 


10/31/2018 Update:

Excavation & Shoring

Excavation at the site continues including soil stabilization, shoring, leveling, grading and off hauling. During off-hauling flagmen will be positioned at the job site gates. Two truck bosses manage truck traffic to ensure truckers follow prescribed routes and do not stack in line on Turk. Overall excavation work is expected to last about 5 months. There will be off hauling on Saturday, November 2. 

East Slope grubbing 

There are a couple of clusters of dead trees in the middle of the slope between the construction site and the Ewing Terrace property line. The dead trees must be removed in anticipation of future landscaping. Because access to that area with large equipment won’t be possible after excavation, the contractor plans to start removing the dead trees starting Thursday, Nov 1. We have asked them to leave as much greenery in place as possible. Any open ground left after removal will be covered by wattles and other material to prevent erosion. 

Tree placement, Northeast corner

For the same reason as above, we plan to plant seven Deodar Cedars (60inch boxes) downhill from the northeast corner of the site. The contractor will start digging the holes for the trees tomorrow, the process will take several days and will involve some noise. Because of the size of the boxes, a crane is scheduled for Wed Nov 7 to put them in place. 


10/25/18 Update:

Excavation at the site continues including soil stabilization, shoring, leveling, and grading. Off hauling will begin Friday, October 26 which will result in an increase in truck traffic in and out of the site. Flagmen will be positioned at the job site gates. Two truck bosses will manage truck traffic to ensure truckers follow prescribed routes. Overall excavation work is expected to last about 5 months.

We encourage everyone to use extra caution at all times when walking or driving near the job site gates.


10/22/18 Update:

An excavator is scheduled for delivery Tuesday, October 23 at approximately 4:30 a.m.  As with other larger equipment, the size of the job trailer triggers travel time restrictions required by the City of San Francisco.  Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise.  We apologize for the disruption and inconvenience.


10/18/18 Update:

One trailer is scheduled for pick up Monday, October 22 at approximately 6:30 a.m. As with some larger equipment, the size of the job trailer triggers travel time restrictions required by the City of San Francisco.  Contractors will make every effort to minimize noise associated with the pickup, however, there will likely be truck backing up noise.  We apologize for any disruption and inconvenience.


10/16/18 Update:

One of the large rigs scheduled for delivery on Tuesday, October 16 was not delivered. Delivery has been rescheduled for Thursday, Oct 18 at approximately 4:00 a.m.

As with the other large equipment, the size of the equipment triggers travel time restrictions required by the City of San Francisco. The contractors will make every effort to minimize the noise associated with this delivery however it is likely to be noisy. We apologize in advance for any disruption and inconvenience. 


10/15/18 Update:

Two large rigs are scheduled to be delivered to the Lone Mountain Residence Hall construction site on Tuesday October 16. The size of the equipment requires hauling by oversize trucks which trigger travel time restrictions imposed by the City of San Francisco.  Accordingly, the trucks will arrive at the construction site entrance on Turk at approximately 4:00 a.m.  The contractors will make every effort to minimize the noise associated with this delivery however it is likely to be noisy and apologize in advance for any disruption and inconvenience. 


10/4/18 Update:

  • Thursday, Oct 5: Paving of temporary road on lawn area through Oct 6. Work will involve the application of asphalt on the temporary roadway. 
  • Monday, Oct 8: Excavation at the site is scheduled to begin on Monday, Oct 8.  Early phases of the process involve soil stabilization, shoring, leveling, and grading.  Some of the shoring work will be noisy. Continued delivery of shoring beams to the site. As the work proceeds, truck traffic in and out of the site will increase. A flagman will be in place at the job site gate but we encourage everyone to use extra caution at all times around the site. A ‘truck boss’ is assigned to the site to manage truck traffic and ensure truckers follow prescribed routes. Overall excavation work is expected to last about 5 months.
  • Wednesday, Oct 11: Deliver & install Devcon construction trailers. 

All dates are schedule estimates and may change without notice. 


9/25/18 Update: 

  • Sept 27 - 28: The temporary access road is scheduled to be completed and paved on. 
  • The construction site is cleared and prepared for excavation and shoring. The next phase at the site will involve preparation for earthwork and shoring.  
  • October 1: Construction activities will pick up significantly beginning the week of.
  • Delivery of two trailers (for construction management) is scheduled for early October. 
  • 10/1 - 10/19: Leveling and rough grading at the site is scheduled for.
  • 10/8 -10/19: Delivery of shoring beams is scheduled between.
  • Mass excavation is scheduled to begin in late October and is expected to take about five months. We will share details about these activities as the schedule develops. 
  • All of this work will involve increased truck activity both for deliveries and for off-hauling. Flagmen will be in place at the job site gate but we encourage everyone to use extra caution at all times around the site.

All dates are schedule estimates and may change without notice. 


9/13/18 Update:

work will begin on building a temporary roadway from Turk to the construction site, roughly near the Roselyn Terrace/Turk intersection. This temporary road will be used primarily by trucks off-hauling soils from the site. As with other construction activities impacting the eastern portion of the Lone Mountain lawn, the changes are temporary. The lawn will be returned to its original condition when the project is completed.  


8/31/18 Update:

Two drill rigs are scheduled to be delivered to the Lone Mtn Residence Hall construction site during the week of September 3. The first drill rig, the smaller of the two, will be delivered around noon on Tuesday, Sept 4. The Contractor will manage vehicle and pedestrian traffic around the immediate area. 

The second delivery is a large drill rig, scheduled for delivery to the site on Wednesday, Sept 5. The size of the drill rig requires hauling by an oversize truck, the dimensions of which trigger travel time restrictions imposed by the City of San Francisco. Specifically, this truck may only travel on City streets before 6 am.  Accordingly, the truck and drill rig will arrive at the construction site entrance on Turk at approximately 4:00 a.m.  The crew will take approximately 1/2 hour to unload the rig and then will drive away.  The contractors will make every effort to minimize the noise associated with this delivery however we acknowledge that it is likely to be noisy and apologize in advance for any disruption and inconvenience. 


8/21/18 Update:

Tree removal will begin on 8/21 at the Res Hall site. The work will involve some heavy equipment and chainsaw noise.


8/4/18 Update:

There will be some work at the Lone Mountain lawn site on Saturday, August 4. A team of carpenters will be building forms for a concrete pour. The work is scheduled to start at 9am


8/3/18 Update:

Site preparation and demolition activities will continue during the week of Aug 6. The schedule includes constructing a perimeter fence around the restricted construction area which borders the sidewalk along Turk, the demolition of Underhill which will involve heavy equipment, and continued site grubbing and tree removal.  


8/1/18 Update:

We are expecting to start tree removal & site “grubbing” at the Residence Hall site late this week or early next. The tree work will be noisy.


7/16/18 Update:

On Wednesday, July 18, the general contractor will fly a drone over the proposed Res Hall construction site during business hours in order to photo document current conditions. The process will take about a half-hour.


6/20/18 Update: Construction Site Closure

Beginning Monday, June 25, the following parking lots, rampways, and pedestrian pathways will close in preparation for construction of the new Sobrato Residential Complex:

  • Loyola Parking Lot 
  • Lone Mountain Drive, east of Loyola House driveway entrance 
  • Pedestrian Path from Loyola Village to Turk Blvd 
  • Underhill Tennis Courts 
  • In preparation for construction, the north-west and west Lone Mountain parking lots will be closed beginning May 21, 2018. We anticipate the Lone Mountain east parking lot and driveway to close this summer.
  • Informational signage will be posted within Lone Mountain main to direct individuals to the new locations of displaced staff. 
  • The Outtakes Cafe kitchen facility will be closed beginning May 21, 2018. The dining area will remain open as a gathering space/lounge.
  • Beginning May 21, the Lone Mountain east parking lot and east driveway will be closed.