Capital Projects Updates
2025:
UPDATE 1/30/2025:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
San Francisco Dept Pubic Works - Turk Blvd project - courtesy notice
The San Francisco Department of Public Works has advised us that construction is set to start on Turk Blvd in February. The first segment of work will span from Arguello Blvd. to Masonic Ave. However, only two blocks can be worked on at a time. Contractors plan on starting around February 20th. This segment of work is anticipated to reach full completion around mid-August 2025. The scope of work will include grinding (removing) asphalt, concrete base work, bus pad installment, minor sewage repair work and ADA compliant curb ramps. After that, the roadway will be repaved. Traffic patterns for this segment may be affected. The public should be aware that lanes will shift as construction crews work on Turk Blvd.
This is a SF DPW project and not related to any USF projects. Please direct inquiries to the Department of Public Works.
School of Education, 2350 Turk
- Feb 3-7: No work at the site this week
Masonic East, 270 Masonic (formerly the Blood Bank)
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
Campus Events/Academic Calendar
- Feb 4 Lunar New Year celebration, Privet Plaza, 11:45am-12:45pm
- Feb 6 Men’s Basketball vs St Mary’s, Sobrato Center 6pm. TV truck
Dogs on campus:
Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field.
Please keep your pooch leashed and clean up its waste when you visit the campus.
UPDATE 1/24/2025:
San Francisco Dept Pubic Works - Turk Blvd project - courtesy notice
The San Francisco Department of Public Works has advised us that construction is set to start on Turk Blvd in February. The first segment of work will span from Arguello Blvd. to Masonic Ave, however, only two blocks are permitted to be worked on at a time. Contractors plan on starting around February 20th. This segment of work is anticipated to reach full completion around Mid-August 2025. The scope of work will include grinding (removing) asphalt, concrete base work, bus pad installment, minor sewage repair work and ADA compliant curb ramps. After that, the roadway will be repaved. Traffic patterns for this segment may be affected. The public should be aware that lanes will shift as construction crews work on Turk Blvd.
This is a SF DPW project and not related to any USF projects. Please direct inquiries to the Department of Public Works.
Lower Campus Banners
- Jan 30: Campus contractor will remove vinyl marketing banners from 34 light poles on lower campus, using a truck with a cherry picker. Please use caution when in proximity of the work and follow any signage and worker instructions.
School of Education, 2350 Turk
- Jan 27-31: No work at the site this week
Masonic East, 270 Masonic (formerly the Blood Bank)
Dates for parking lot waterproofing and other improvements have not yet been scheduled.
Campus Events/Academic Calendar
- Jan 21 Undergrad classes start
Dogs on campus:
Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field.
Please keep your pooch leashed and clean up its waste when you visit the campus.
UPDATE 1/17/2025:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
Harney Power Shut-off
- Jan 18-19: Harney and Lo Schiavo will close at 3pm Friday Jan 17
- Power to Harney will be shut down Saturday, 1/18 to complete the electrical conduit project underneath the pathway between Gleeson and Harney.
- Harney and Lo Schiavo will close at 3pm Friday Jan 17 to enable tech staff to prepare for the shutoff
- Harney will remained closed until noon Sunday, 1/19.
School of Education, 2350 Turk
- Jan 20-24: No work at the site this week
Masonic East, 270 Masonic (formerly the Blood Bank)
Dates for parking lot waterproofing and other improvements have not yet been scheduled.
Campus Events/Academic Calendar
- Jan 21 Undergrad classes start
The Koret Health & Rec Center will observe limited hours for the upcoming winter & holiday break.
- Jan 6-19. Monday-Friday: 7am-7pm; pool closes at 7pm. Sat/Sun: 10am-5pm; pool closes at 4pm
Dogs on campus:
Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field.
Please keep your pooch leashed and clean up its waste when you visit the campus.
UPDATE 1/10/2025:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
Dogs on campus:
Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field.
Please keep your pooch leashed and clean up its waste when you visit the campus.
School of Education, 2350 Turk
- Jan 10: concrete bench delivery between 10am - 2pm
- Jan 13 - 17: Continue stone installation (some noise when cutting stone pieces)
Masonic East, 270 Masonic (formerly the Blood Bank)
Dates for parking lot waterproofing and other improvements have not yet been scheduled.
Campus Events/Academic Calendar
- Jan 2-17 Intersession classes
- Jan 6 Law school classes start
- Jan 21 Undergrad classes start
The Koret Health & Rec Center will observe limited hours for the upcoming winter & holiday break.
- Jan 6-19. Monday-Friday: 7am-7pm; pool closes at 7pm. Sat/Sun: 10am-5pm; pool closes at 4pm
UPDATE 1/03/2025:
All dates below are best estimates subject to weather and other external impacts and may change without notice.
Dogs on campus:
- Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field.
- Please keep your pooch leashed and clean up its waste when you visit the campus.
School of Education, 2350 Turk
- Continue stone installation around the statue plinth
Masonic East, 270 Masonic (formerly the Blood Bank)
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
Campus Events/Academic Calendar
- Jan 2-17 Intersession classes
- Jan 6 Law school classes start
- Jan 21 Undergrad classes start
The Koret Health & Rec Center will observe limited hours for the upcoming winter & holiday break.
- Dec 20-Jan 5 Closed for winter repairs and maintenance
- Jan 6-19. Monday-Friday: 7am-7pm; pool closes at 7pm. Sat/Sun: 10am-5pm; pool closes at 4pm
2024 in Review:
UPDATE 12/19/2024:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
Dogs on campus:
Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field.
- Please keep your pooch leashed and clean up its waste when you visit the campus.
Transformer Cleaning, Lower Campus
For the Campus Community: the following building transformer cleaning
- Dec 23 Monday Toler Hall & McLaren
- Dec 23 Monday CSI
- Dec 27 Friday Kalmanovitz Hall
- Dec 27 Friday Cowell Hall
Power will be turned off at 0500 and restored by 0900
School of Education, 2350 Turk
- Dec 20 & 23 - Continue stone installation around statue plinth
- Dec 27 & 30 - Continue stone installation around statue plinth
Masonic East, 270 Masonic (formerly the Blood Bank)
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
Campus Events/Academic Calendar
- Dec 4 Fall classes end
- Dec 6-12 Exam period
- Dec 30 MBB vs Santa Clara Sobrato Center 7pm
- Jan 2-17 Intersession classes
- Jan 6 Law school classes start
- Jan 21 Undergrad classes start
The Koret Health & Rec Center will observe limited hours for the upcoming winter & holiday break.
- Dec 16-19 Open 7am-7pm. Pool closed.
- Dec 20-Jan 5 Closed for winter repairs and maintenance
- Jan 6-19. Monday-Friday: 7am-7pm; pool closes at 7pm. Sat/Sun: 10am-5pm; pool closes at 4pm
UPDATE 12/13/2024:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
Dogs on campus:
Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field.
- Please keep your pooch leashed and clean up its waste when you visit the campus.
Transformer Cleaning, Lower Campus
For the Campus Community: the following building transformer cleaning schedule is for Monday, 12/23, and Friday, 12/27. This work will require that the buildings be powered down for a four-hour duration, as listed below. Please remember to power down any computers, office equipment, or any other sensitive electronics in preparation for the building power shutdown.
- Dec 23 Monday Toler Hall & McLaren
- Dec 23 Monday CSI
- Dec 27 Friday Kalmanovitz Hall
- Dec 27 Friday Cowell Hall
Power will be turned off at 0500 and restored by 0900
School of Education, 2350 Turk
- January TBD: remaining stone to be delivered and installed.
Masonic East, 270 Masonic (formerly the Blood Bank)
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
Campus Events/Academic Calendar
- Dec 4 Fall classes end
- Dec 6-12 Exam period
- Dec 30 MBB vs Santa Clara Sobrato Center 7pm
- Jan 2-17 Intersession classes
- Jan 6 Law school classes start
- Jan 21 Undergrad classes start
UPDATE 11/22/2024:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
Dogs on campus:
Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field.
Please keep your pooch leashed and clean up its waste when you visit the campus.
School of Education, 2350 Turk
- Early December: The concrete bench is to be delivered; the remaining stone is to be delivered and installed.
Masonic East, 270 Masonic (formerly the Blood Bank)
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
Campus Events
Academic Calendar
- Dec 4 Fall classes end
- Dec 6-12 Exam period
- Jan 2-17 Intersession classes
- Jan 6 Law school classes start
- Jan 21 Undergrad classes start
UPDATE 11/12/2024:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
Dogs on campus:
Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field.
Please keep your pooch leashed and clean up its waste when you visit the campus.
Thru November 15: Electrical conduit replacement
- at Central Walk between Gleeson Library Cogeneration plant and Harney Science Center.
- Walkway pavers to be removed for trench work needed to replace a compromised underground conduit.
- October 28: temporary fencing to be installed. Follow posted signs for rerouting access paths to Harney Science and Gleeson Library entries.
School of Education, 2350 Turk
- Nov 13-15: finish landscaping and light fixture installation
- Thru 11/18: Stone delivery, concrete bench delivery and installation delivery of remaining stone pavers
- Nov 17 Sisters of the Presentation private ceremony 2:00 -4:00pm
Masonic East, 270 Masonic (formerly the Blood Bank)
Dates for parking lot waterproofing and other improvements have not yet been scheduled.
Campus Events
Nov 21 Thursday, Passenger loading zone @ War Memorial Gym (WMG)
Student Life and Athletics sponsoring bus transportation for students to the USF Legacy basketball doubleheader at the Chase Center. Details and exact timing TBD. General plan:
- Staggered departures at WMG passenger zone, 1-2 buses at a time between approximately 3:15pm and 6:15 pm
- Return drop offs at Parker Ave loading zone will be between approximately 9:30-10:30 pm.
- USF Student Life staff will coordinate the departures to ensure quick loading with limited idling time and ensure that students disperse when they return
Academic Calendar
- Dec 4 Fall classes end
- Dec 6-12 Exam period
- Jan 2-17 Intersession classes
- Jan 6 Law school classes start
- Jan 21 Undergrad classes start
UPDATE 11/8/2024:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
Thru November 15: Electrical conduit replacement at Central Walk between Gleeson Library Cogeneration plant and Harney Science Center.
- Walkway pavers to be removed for trench work needed to replace a compromised underground conduit.
- October 28: temporary fencing to be installed. Follow posted signs for rerouting access paths to Harney Science and Gleeson Library entries.
School of Education, 2350 Turk
- Thru Nov 8: Continue painting railings, landscapers, and planting
- Thru 15: Stone delivery and installation. landscapers continue planting and mulching, light fixtures along path to be installed delivery of remaining stone pavers
- Date TBD; light fixture installation
- Nov 17 Sisters of the Presentation private ceremony 2:00 - 3:00pm
Masonic East, 270 Masonic (formerly the Blood Bank)
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
Campus Events
- Nov 9 Saturday Student Pre-Game Tailgate 6-7:30p,
- In parking lot beneath Malloy Basketball Pavilion. Amplified music until 7:30
Nov 21 Thursday, Passenger loading zone @ War Memorial Gym (WMG)
Student Life and Athletics sponsoring bus transportation for students to the USF Legacy basketball doubleheader at the Chase Center. Details and exact timing TBD. General plan:
- Staggered departures at WMG passenger zone, 1-2 buses at a time between approximately 3:15pm and 6:15 pm
- Return drop offs at Parker Ave loading zone will be between approximately 9:30-10:30 pm.
- USF Student Life staff will coordinate the departures to ensure quick loading with limited idling time and ensure that students disperse when they return
UPDATE 11/1/2024:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
Thru November 15: Electrical conduit replacement at Central Walk between Gleeson Library Cogeneration plant and Harney Science Center.
- Walkway pavers to be removed for trench work needed to replace a compromised underground conduit.
- October 28: temporary fencing to be installed. Follow posted signs for rerouting access paths to Harney Science and Gleeson Library entries.

School of Education, 2350 Turk
- Nov 1: finish railing installation (some noise drilling into concrete), painting railing
- Nov 4 - 8: Continue painting railings, landscapers planting
- Nov 11 - 15: Stone delivery and installation
- Date TBD; light fixture installation
Masonic East, 270 Masonic (formerly the Blood Bank)
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
St Ignatius Church
- Project completed
- Watch this video to see the extent of the work: https://vimeo.com/1015004329?
share=copy
Campus Events
- October 25th - CAB Fright Night Gleeson Plaza / Welch Field, 7pm - 10pm, Student only event; sound system with music, halloween games
- Music will be turned off promptly at 10pm
October 26th - Admissions Day, Sobrato Gym and Main Campus; 8am - 2pm
- Welcome in Sobrato Gym with breakout sessions throughout campus and a resource fair on Gleeson Plaza / Lawn / Welch Field
UPDATE 10/25/2024:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
October 28 - November 15: Electrical conduit replacement at Central Walk between Gleeson Library Cogeneration plant and Harney Science Center.
- Walkway pavers to be removed for trench work needed to replace a compromised underground conduit.
- October 28: temporary fencing to be installed. Follow posted signs for rerouting access paths to Harney Science and Gleeson Library entries.
School of Education, 2350 Turk
- Oct 24 -25: landscaping and planting trees
- Oct 28 - Nov1: continue landscaping and planting (minimal noise)
Masonic East, 270 Masonic (formerly the Blood Bank)
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
St Ignatius Church
- Project completed
- Watch this video to see the extent of the work completed: https://vimeo.com/1015004329?
share=copy
Campus Events
- October 25th - CAB Fright Night Gleeson Plaza / Welch Field, 7pm - 10pm, Student only event; sound system with music, halloween games
- Music will be turned off promptly at 10pm
- October 26th - Admissions Day, Sobrato Gym and Main Campus; 8am - 2pm
- Welcome in Sobrato Gym with breakout sessions throughout campus and a resource fair on Gleeson Plaza / Lawn / Welch Field
UPDATE 10/11/2024:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
School of Education, 2350 Turk
- Oct 17-18: soil and baserock deliveries
- Oct 21-25: landscaping crew continues to prep for planting trees (minimal noise)
Masonic East, 270 Masonic (formerly the Blood Bank)
Dates for parking lot waterproofing and other improvements have not yet been scheduled.
St Ignatius Church
- Project completed
- Watch this video to see the extent of the work completed: https://vimeo.com/1015004329?
share=copy
Campus Events
- Oct 17-20 Celebrate USF Alumni & Family Weekend
Oct 18 Family Welcome Reception
- Various events: McClaren, Lone Mtn, Koret Lodge 4-8pm
Oct 19
- Silk Speaker Series, St Ignatius Church
- Celebrate USF Food & Music Festival
- Food & Music Festival 1-3pm. Noisy at times
- Reunions (various campus location Lone Mountain & main campus) 3-9pm
Oct 20
- Fun Run - in and around main campus
- Reunions (Lone Mtn & main campus)
October 25th - CAB Fright Night Gleeson Plaza / Welch Field, 7pm - 10pm, Student only event; sound system with music, halloween games
- Music will be turned off promptly at 10pm
October 26th - Admissions Day, Sobrato Gym and Main Campus; 8am - 2pm
- Welcome in Sobrato Gym with breakout sessions throughout campus and a resource fair on Gleeson Plaza / Lawn / Welch Field
UPDATE 10/11/2024:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
School of Education, 2350 Turk
- Oct 10-11: landscaping crew will dig holes to prep for trees
- Oct 14-18: tree delivery and planting (minimal noise)
Masonic East, 270 Masonic (formerly the Blood Bank)
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
St Ignatius Church
- Project completed
- Watch this video to see the extent of the work completed: https://vimeo.com/1015004329?
share=copy
Campus Events
- Oct 17-20 Celebrate USF Alumni & Family Weekend
- Oct 17 School of Nursing & Health Professions 70th Anniversary, Main Campus
- Oct 18 Family Welcome Reception
Various events: McClaren, Lone Mtn, Koret Lodge 4-8pm
Oct 19
- Silk Speaker Series, St Ignatius Church
- Celebrate USF Food & Music Festival
- Food & Music Festival 1-3pm. Noisy at times
- Reunions (various campus location Lone Mountain & main campus) 3-9pm
Oct 20
- Fun Run - in and around main campus
- Reunions (Lone Mtn & main campus)
UPDATE 10/05/2024:
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
School of Education, 2350 Turk
- Oct 7-11 Ongoing paver installation (some noise with minimal stone cutting)
Masonic East, 270 Masonic (formerly the Blood Bank)
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
Fromm Hall Residential Window Replacement
- Project completed
Malloy Hall Exterior Rehab
- Project completed
Malloy Basketball Practice Facility/War Memorial Gym .
- Project completed
St Ignatius Church
- Project completed
Campus Events
Oct 17-20 Celebrate USF Alumni & Family Weekend
- Oct 17 School of Nursing & Health Professions 70th Anniversary, Main Campus
- Oct 18 Family Welcome Reception
- Various events: McClaren, Lone Mtn, Koret Lodge 4-8pm
- Oct 19
- Silk Speaker Series, St Ignatius Church
- Celebrate USF Food & Music Festival
- Food & Music Festival 1-3pm. Noisy at time
- Reunions (various campus location Lone Mountain & main campus) 3-9p
- Oct 20
- Fun Run - in and around main campus
- Reunions (Lone Mtn & main campus)
UPDATE 9/27/2024:
- Punch list
- June 12 -Sept 27 Project completed
- Sept 30-Oct 4 Ongoing irrigation installation. Paver delivery October 3; paver installation thereafter.
- Sept 30 - Oct 2 Water proofing complete. Car-stops installation Oct 1. Lot should re-open Oct 2.
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- Punch list
Campus Events
Oct 17-20 Celebrate USF Alumni & Family Weekend
- Oct 17 School of Nursing & Health Professions 70th Anniversary, Main Campus
- Oct 18 Family Welcome Reception
- Various events: McClaren, Lone Mtn, Koret Lodge 4-8pm
- Oct 19
- Silk Speaker Series, St Ignatius Church
- Celebrate USF Food & Music Festival
- Food & Music Festival 1-3pm. Noisy at time
- Reunions (various campus location Lone Mountain & main campus) 3-9p
- Oct 20
- Fun Run - in and around main campus
- Reunions (Lone Mtn & main campus)
UPDATE 9/13/2024:
- Punch list
- June 12 -Sept 27 Resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Surfacing work expected to be dusty. We recommend that windows in the areas of work remain closed. Work hours 7:30a to 3:30pm (noisy work starts after 8am)
- Sept 16-20 Ongoing irrigation lines install.
- Sept 16-20 Scaffold installation at School of Ed chimney tower. Intermittent noise 8am-4pm
- Aug 23-Sept 30 Water proofing, upper parking deck. Street level parking deck will remain closed through completion of water proofing.
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.
Punch list
- Sept 23-25 PGE overhead work and underground wire pull
- Sept 26-27 Sidewalk repairs
- Sept 24 School of Management Centennial Celebration, Welch Field 11:30 am start. Some noise: music & speakers
- Oct 1 Bruce Mahoney Volleyball Game, Sobrato Center, 5:30pm
- Oct 17-20 Celebrate USF Alumni & Family Weekend
- Oct 17 School of Nursing & Health Professions 70th Anniversary, Main Campus
- Oct 18 Family Welcome Reception
- Oct 19
- Silk Speaker Series, Sobrato Center
- Celebrate USF Food & Music Festival
- Reunions (Lone Mountain & main campus)
- Oct 20
- Fun Run - in and around main campus
- Reunions (Lone Mtn & main campus)
UPDATE 9/6/2024:
- Punch list
- June 12 -Sept 27 Resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Surfacing work expected to be dusty. We recommend that windows in the areas of work remain closed. Work hours 7:30a to 3:30pm (noisy work starts after 8am)
- Sept 9-16 Ongoing irrigation lines install.
- Scaffold installation at School of Ed chimney tower - dates TBD
- Aug 23-Sept 30 Water proofing, upper parking deck. Street level parking deck will remain closed through completion of water proofing.
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- Sept 9 PGE installs power pole on Mcallister.
- Sept 10-13 Street trench/patch street
- Sept 23-25 PGE overhead work and underground wire pull
- Sept 26-27 Sidewalk repairs
- Oct 17-20 Celebrate USF Alumni & Family Weekend
- Oct 17 School of Nursing & Health Professions 70th Anniversary, Main Campus
- Oct 18 Family Welcome Reception
- Oct 19
- Silk Speaker Series, Sobrato Center
- Celebrate USF Food & Music Festival
- Reunions (Lone Mountain & main campus
- Oct 20
- Fun Run - in and around main campus
- Reunions (Lone Mtn & main campus)
UPDATE 8/30/2024:
- Punch list
- June 12 -Sept 27 Resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Surfacing work expected to be dusty. We recommend that windows in the areas of work remain closed. Work hours 7:30a to 3:30pm (noisy work starts after 8am)
Aug 28-Sept 3 Railing installation. Some concrete drilling, noisy at times.Sept 3-6 Continue installing irrigation lines.
- Aug 23-Sept 30 Water proofing, upper parking deck. Street level parking deck will remain closed through completion of water proofing.
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- Punch list
- Sept 9 PGE install power pole on Mcallister.
- Sept 23-25 PGE overhead work and underground work
Campus Events
- Oct 17-20 Celebrate USF Alumni Weekend
- Oct 19 - Silk Series Lecture
UPDATE 8/23/2024:
- Punch list
- June 12 -Sept 27 Resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Surfacing work expected to be dusty. We recommend that windows in the areas of work remain closed. Work hours 7:30a to 3:30pm (noisy work starts after 8am)
- Aug 28 Scaffolding removal, east side: 8:00 - 9:00am on 8/28. Noisy at times.
- Aug 28-29 Railing installation. Some concrete drilling, noisy at times.
- Aug 23-Sept 13 Water proofing, upper parking deck. Street level parking deck will remain closed through completion of water proofing.
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- Punch list
- Sept 9 PGE install power pole on Mcallister.
- Sept 23-25 PGE overhead work and underground work
Campus Events
- Oct 17-20 Celebrate USF Alumni Weekend
- Oct 19 - Silk Series Lecture
UPDATE 7/19/2024:
- July 24 Harney Science - Wednesday 7/24/24 - 4:30 AM to 6:30 AM
- July 24 Fromm Hall/SI Church - Wednesday 7/24/24 - 5AM to 7AM
- July 25 Hayes Healy - Thursday 7/25/24 - 5AM to 7AM
- July 25 Gillson Hall / Malloy Pavilion - Thursday 7/25/24 - 5AM to 7AM
- Aug 12-16 Turf maintenance & repair. Some parking stalls on south side of Golden Gate near Masonic will be reserved for equipment during this period.
- July 25-26 Desk delivery & install
- July 24-Aug 2 Window shades install
- Exterior painting prep & painting: scheduled completion by July 26
- July 22-26 Scaffold removal
- Faculty and students access to Xarts through the NW loading dock door - 6am and 2:30pm.
- June 12 -Aug 14 Locate and resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Scaffold install ongoing.
- Surfacing work in preparation for painting which is expected to be dusty. We recommend that windows in the areas of work remain closed through the end of next week. Work hours 7:30a to 3:30pm (noisy work starts after 8am)
- July 22 - Aug 2: paver install and concrete work for bollard bases; begin stone install
- July 23 delivery, ground cover.
- July 31 anticipated completion for landscaping
- Parking deck; restriping & overlay; concrete repairs. Rescheduled to mid August
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- July 22-23 Fire alarm testing. Noisy at times
- July 29-Aug 2 Remove trailer, specific date TBD
- Sept 9 PGE install power pole on Mcallister.
- Sept 23-25 PGE overhead work and underground work
Campus Events
- May 20 - Aug 9 Summer sessions
- July 10 Goats start on Lone Mountain.
- Aug 10 New Student Move-in Day
- Aug 10-19 Orientation
- Aug 20 Classes begin
- Aug 22 Silk Lecture Series Sobrato Center 6-9pm
UPDATE 7/12/2024:
- Interior work ongoing: to be completed by 7/17
- Exterior painting prep & painting ongoing
- July 22-26 Scaffold removal
- July 29 estimated completion date
- Faculty and students access to Xarts through the NW loading dock door - 6am and 2:30pm.
- June 12 -Aug 14 Locate and resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Scaffold install ongoing.
- Surfacing work in preparation for painting which is expected to be dusty. We recommend that windows in the areas of work remain closed through the end of next week.
- Work hours 7:30a to 3:30pm (noisy work starts after 8am)
- July 12 concrete pour (some noise)
- July 15-19 remove form boards, clean site
- July 3 -17: Landscaping install at Golden Gate frontage; tree planting
- July 15 -16 deliveries green surface materials, planters, soils
- July 23 delivery, ground cover.
- July 8-24 Parking deck; restriping & overlay; concrete repairs
- July 31 anticipated completion
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- July 8-19 Replaster & re-stucco exterior planters on Fulton
- July 15-19 Remove perimeter fence except at transformer; that fence will stay in place until PG&E completes its work (Sept)
- July 22-23 Fire alarm testing. Noisy at times
- July 29-Aug 2 Remove trailer, specific date TBD
Campus Events
- May 20 - Aug 9 Summer sessions
- July 10 Goats start on Lone Mountain.
- Aug 10 New Student Move-in Day
- Aug 10-19 Orientation
- Aug 20 Classes begin
- Aug 22 Silk Lecture Series Sobrato Center 6-9pm
UPDATE 7/2/2024:
- Interior work ongoing: caulking, skim coating, painting
- Exterior painting prep & painting: work on south elevation will resume July 1
- July 4-5 No work
- July 29 estimated completion date
- Faculty and students access to Xarts through the NW loading dock door - 6am and 2:30pm.
- June 12 -Aug 14 Locate and resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Scaffold install ongoing.
- June 28 - July 7 surfacing work in preparation for painting which is expected to be dusty. We recommend that windows in the areas of work remain closed through the end of next week.
- Work hours 7:30a to 3:30pm (noisy work starts after 8am)
- July 3: grading work. Some noise
- July 4-5 No work
- July 8-12 continue grading work and form rebar in preparation for concrete pour (noisy at times)
- July 12 concrete pour (some noise)
- July 3 -17: Landscaping install at Golden Gate frontage; tree planting
- July 8-24 Parking deck; restriping & overlay; concrete repairs
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- Thru July 10 finishing interior and roof work
- June 3-29 Stain glass installation Delivery of portable work space to Plaza on June 29
- July 8-19 Replaster & re-stucco exterior planters on Fulton
Campus Events
- May 20 - Aug 9 Summer sessions
- July 10 Goats start on Lone Mountain.
- Aug 10 New Student Move-in Day
- Aug 10-19 Orientation
- Aug 20 Classes begin
UPDATE 6/14/2024:
- June 28 Window installation to be completed 6/28
- Interior work ongoing: caulking, skim coating, painting
- Exterior painting prep & painting: work on south elevation will resume July 1
- July 4-5 No work
- July 29 estimated completion date
- Faculty and students access to Xarts through the NW loading dock door - 6am and 2:30pm.
- June 12 -Aug 14 Locate and resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Scaffold install ongoing.
- Work hours 7:30a to 3:30pm (noisy work starts after 8am)
- June 28 - July 7 additional surfacing work in preparation for painting which is expected to be dusty. We recommend that windows in the areas of work remain closed through the end of next week..
- June 27 - 28:
- install fountain wall embeds
- finish forms for retaining wall and curb (some noise)
- June 28: concrete pour for fountain walls, retaining wall, and curb (some noise)
- July 1-3: grading and prep for sub slab
- July 4 No work
- July 8-12: continue grading for sub slab and dig footings for screen wall with goal of next concrete pour towards end of the week
- July 1 -17: Landscaping install at Golden Gate frontage
- TBD restriping parking deck
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- Thru July 10 finishing interior and roof work
- June 3-29 Stain glass installation Delivery of portable work space to Plaza on June 29
- July 8-19 Replaster & re-stucco exterior planters on Fulton
Campus Events
- May 20 - Aug 9 Summer sessions
- July 10 Goats start on Lone Mountain.
- Aug 10 New Student Move-in Day
- Aug 10-19 Orientation
- Aug 20 Classes begin
UPDATE 6/28/2024:
- June 17 begin painting building exterior, about 2 weeks duration
- Scaffolding install & window demo complete.
- On going window installations. Saturday work as needed.
- Faculty and students access to Xarts through the NW loading dock door - 6am and 2:30pm.
- June 12 -Aug 14 Locate and resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Scaffold install ongoing.
- Work hours 7:30a to 3:30pm (noisy work starts after 8am)
- The work will be done is three sections, starting from the southwest corner, moving east along the south wall on Fulton. Each section is expected to take about 3 weeks. The workers will start each section by grinding & chipping away the exterior material & draining water bubbles. This work will be noisy, with interior vibrations. The second two weeks per section should be less disruptive as they clean out & replace joints, waterproof and paint the exterior wall.
- June 10-21 Continuing form & rebar work
- June 21 Concrete pour. Will be noisy at times
- TBD: Landscaping at Golden Gate frontage
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- May 30-June 21 install flashings, lights at vrs roof locations
- Thru June 28 ongoing interior work
- June 3-28 Stain glass installation
Campus Events
- May 20 - Aug 9 Summer sessions
- June 18 Goats on Lone Mountain.
- Aug 10 New Student Move-in Day
- Aug 10-19 Orientation
- Aug 20 Classes begin
UPDATE 6/7/2024:
- Scaffolding install & millwork demo complete.
- On going window installations. Saturday work as needed.
- Faculty and students access to Xarts through the NW loading dock door - 6am and 2:30pm.
-
South facade (on Fulton): locate and resolve leaks. Paint. Scaffold install ongoing. Some noise during discovery work
- May 28-31: Prep work for fountain installation in back garden area
- June 3-7: Build forms for concrete footings (some noise)
- June 10-14 Continue form work (possible concrete pour later in week, otherwise the following week)
- TBD early - mid June concrete pour
- TBD: Landscaping at Golden Gate frontage
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- May 30-June 21 install flashings, lights at vrs roof locations
- Thru June 28 ongoing interior work
- June 3-28 Stain glass installation
Campus Events
- May 20 - Aug 9 Summer sessions
- June 18 Goats on Lone Mountain.
- Aug 10 New Student Move-in Day
- Aug 10-19 Orientation
- Aug 20 Classes begin
UPDATE 5/31/2024:
- Thru June 7- Scaffolding install, window demo.
- Saturday work as needed.
- South facade (on Fulton): locate and resolve leaks. Paint. Scaffold install ongoing. Some noise during discovery work
- May 29 power washing begins
- May 28-31: Prep work for fountain installation
- June 3-7: Build forms for concrete footings (some noise)
- TBD early June concrete pour
- TBD: Landscaping at Golden Gate frontage
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- June 3 stair tower removal
- May 30-June 21 install flashings, lights at vrs roof locations
- Thru June 14 ongoing interior work
- June 3-28 Stain glass installation
Campus Events
- May 20 - Aug 9 Summer sessions
- May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm: Load-out 1pm -9pm
- June 18 Goats on Lone Mountain.
- Aug 10 New Student Move-in Day
- Aug 10-19 Orientation
- Aug 20 Classes begin
UPDATE 5/24/2024:
- May 20-31- Scaffolding install. Noisy at times
- move furniture, deliver materiel, abate & demo
No work May 25 &28 - May 28-31: Deliveries for new windows and additional scaffolding at the XArts loading dock
- move furniture, deliver materiel, abate & demo
- South facade (on Fulton): locate and resolve leaks. Paint. Scaffold install ongoing. Some noise during discovery work
- May 29 power washing begins
- May 24 & 28: Complete paving west section of pathway
- May 28-31: Fountain contractor to do minimal excavation and begin fountain installation (some noise)
- June 3-7: Fountain contractor to continue fountain installation (some noise)
- Apr 22 - May 29: Landscaping at Golden Gate frontage
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- May 28-31 Scaffold removal at Dome & mid-roof. Detail work at upper roof.
- June 3 stair tower removal
- May 30-June 7 install flashings, lights at vrs roof locations
- June 3-14 Stain glass installation
Campus Events
- May 20 - Aug 9 Summer sessions
- May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm: Load-out 1pm -9pm
- June 18 Goats on Lone Mountain.
- Aug 10-19 Orientation
- Aug 20 Classes begin
UPDATE 5/17/2024:
- May 20 project start date, Mon - Sat, 8am start (9am Sat)
- May 20-31- Scaffolding install. Noisy at times
- move furniture, deliver materiel, abate & demo
- No work May 25 &28
- May 21 estimated start, work will continue through most of the summer
- South facade (on Fulton): locate and resolve leaks. Paint
- Scaffold install ongoing. Some noise during discovery work
- May 6-17 ongoing paver install (some noise as trucks deliver sand and gravel)
- Workers will not do loud work on 5/10 and during Finals Week 5/11-16
- Date TBD Concrete pour for footings & pedestal
- Apr 22 - May 29: Landscaping at Golden Gate frontage
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- May 23 - crane at NE corner of Church to help remove scaffolding
- Scaffold removal at Dome & mid-roof through 5/23
- May 20-24 install lighting & flashing
- June 3-14 Stain glass installation
Campus Events
- May 16-18 Commencements
- May 20 - Aug 9 Summer sessions
- May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
- June 18 Goats on Lone Mountain.
- Aug 10-19 Orientation
- Aug 20 Classes begin
UPDATE 5/10/2024:
- May 20 estimated start date
- May 21 estimated start
- South facade (on Fulton): locate and resolve leaks. Paint
- Scaffold install ongoing. Some noise during discovery work
- May 13-17 Finals week. No work will occur at the project site
- May 20-24 ongoing paver install (some noise as trucks deliver sand and gravel)
- Date TBD Concrete pour for footings & pedestal
- Apr 22 - May 29: Landscaping at Golden Gate frontage
- April 22 -29 concrete coring,
- Apr 22 - May 13 planter bed & retaining wall waterproofing
- May 16 - 29 landscaping
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- Dome painting extended through May 15
- Roof: re-roof work, by section, through 6/3
- Stain glass restoration through 6/14
Campus Events
- May 9 Last day of Spring semester classes
- May 16 Commencement Mass 3p St Ignatius Church
- May 16-18 Commencements
- May 20 - Aug 9 Summer sessions
- May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
- June Goats on Lone Mountain. Details TBD
UPDATE 5/3/2024:
- May 20 estimated start date
- May 21 estimated start
- South facade (on Fulton): locate and resolve leaks. Paint
- Scaffold install ongoing. Some noise during discovery work
- May 6-17 ongoing paver install (some noise as trucks deliver sand and gravel)
- Workers will not do loud work on 5/10 and during Finals Week 5/11-16
- Date TBD Concrete pour for footings & pedestal
- Apr 22 - May 29: Landscaping at Golden Gate frontage
- April 22 -29 concrete coring,
- Apr 22 - May 13 planter bed & retaining wall waterproofing
- May 16 - 29 landscaping
LoSchiavo Science
- May 20 -24 Date tentative. A large crane will be positioned in the Gleeson Plaza limiting pedestrian travel during work hours in that area as well as the west side of CSI and the CSI building itself. CSI building ventilation will be offline. CSI will be inaccessible during crane lift. Please exercise caution in the area.
- Crane delivery will be via truck from Parker entrance.
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- Scaffold removal, various frontages through 5/9
- West Spire - scaffold removal 3/4-4/24, subject to weather
- Fulton frontage- remove scaffold 4/15 - 4/29
- Painting - various elevations through 4/24
- Install upper roof through 4/26
- Stain glass restoration through 4/30/24
Campus Events
- May 9 Last day of Spring semester classes
- May 16-18 Commencements
- May 20 - Aug 9 Summer sessions
- May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
- June Goats on Lone Mountain. Details TBD
UPDATE 4/26/2024:
- May 20 estimated start date
- South facade (on Fulton): locate and resolve leaks. Paint
- Scaffold install ongoing. Some noise during discovery work
- April 29-May 1 begin paver install (some noise as trucks deliver sand and gravel)
- Date TBD Concrete pour for footings & pedestal
- Apr 22 - May 29: Landscaping at Golden Gate frontage
- April 22 -29 concrete coring,
- Apr 22 - May 13 planter bed & retaining wall waterproofing May 16 - 29 landscaping
LoSchiavo Science
- May 20 -24 Date tentative. A large crane will be positioned in the Gleeson Plaza limiting pedestrian travel during work hours in that area as well as the west side of CSI and the CSI building itself. CSI building ventilation will be offline. CSI will be inaccessible during crane lift. Please exercise caution in the area.
- Crane delivery will be via truck from Parker entrance.
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- Scaffold removal, various frontages through 5/9
- West Spire - scaffold removal 3/4-4/24, subject to weather
- Fulton frontage- remove scaffold 4/15 - 4/29
- Painting - various elevations through 4/24
- Install upper roof through 4/26
- Stain glass restoration through 4/30/24
Campus Events
- April 26 Admissions Tours, Sobrato Center 9am - 1pm. Buses will load and unload in front of War Memorial Gym
- May 9 Last day of Spring semester classes
- May 16-18 Commencements
- May 20 - Aug 9 Summer sessions
- May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
- June Goats on Lone Mountain. Details TBD
UPDATE 4/19/2024:
- April 15-26 Install electrical conduit and irrigation lines.
- April 29-May 1 begin paver install (some noise as trucks deliver sand and gravel)
- Date TBD Concrete pour for footings & pedestal
- Apr 22 - May 29: Landscaping at Golden Gate frontage
- April 22 -29 concrete coring,
- Apr 22 - May 13 planter bed & retaining wall waterproofing
- May 16 - 29 landscaping
LoSchiavo Science
- May 20 -24 Date tentative. Finalizing schedule for a crane lift to replace ventilation related equipment on the roof of CSI. Once time is set, the plaza area in front of Gleeson and CSI building will be cordoned off. CSI building ventilation will be offline. Access to CSI will be inaccessible during crane lift.
- Crane delivery will be via truck from Parker entrance.
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- Scaffold removal, various frontages through 5/9
- West Spire - scaffold removal 3/4-4/24, subject to weather
- Fulton frontage- remove scaffold 4/15 - 4/29
- Painting - various elevations through 4/24
- Install upper roof through 4/26
- Stain glass restoration through 4/30/24
Campus Events
- April 19 Donaroo Campus Concert. Sobrato Center. 4/19 9A -10:30pm: Production Team load-in, soundcheck. Doors open 6:30, Concert 7-9pm, 10:30 Lights off. 4/20: Production team load-out
- April 26 Admissions Tours, Sobrato Center 9am - 1pm
- May 9 Last day of Spring semester classes
- May 16-18 Commencements
- May 20 - Aug 9 Summer sessions
- May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
- June Goats on Lone Mountain. Details TBD
UPDATE 4/15/2024:
- April 15-26 Install electrical conduit and irrigation lines.
- April 29-May 1 begin paver install (some noise as trucks deliver sand and gravel)
- Date TBD Concrete pour for footings & pedestal.
- Apr 22 - May 29: Landscaping at Golden Gate frontage
- April 22 -29 concrete coring,
- Apr 22 - May 13 planter bed & retaining wall waterproofing
- May 16 - 29 landscaping
LoSchiavo Science
- May 20 -24 Date tentative. Finalizing schedule for a crane lift to replace ventilation related equipment on the roof of CSI. Once time is set, the plaza area in front of Gleeson and CSI building will be cordoned off. CSI building ventilation will be offline. Access to CSI will be inaccessible during crane lift.
- Crane delivery will be via truck from Parker entrance.
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- Scaffold removal, various frontages through 5/9
- West Spire - scaffold removal 3/4-4/24, subject to weather
- Fulton frontage- remove scaffold 4/15 - 4/29
- Painting - various elevations through 4/24
- Install upper roof through 4/26
- Stain glass restoration through 4/30/24
Campus Events
- April 19 Donaroo Campus Concert. Sobrato Center. 4/19 9A -10:30pm: Production Team load-in, soundcheck. Doors open 6:30, Concert 7-9pm, 10:30 Lights off. 4/20: Production team load-out
- April 26 Admissions Tours, Sobrato Center 9am - 1pm
- May 9 Last day of Spring semester classes
- May 16-18 CommencementsMay 20 - Aug 9 Summer sessions
- May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
- June Goats on Lone Mountain. Details TBD
UPDATE 4/15/2024:
- April 15-26 Trenching for irrigation and electrical. Begin installing electrical conduit and irrigation lines.
- Date TBD Concrete pour for footings & pedestal
- Landscaping at Golden Gate frontage to be scheduled for May, Details TBD
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- Scaffold removal, various frontages through 5/9
- West Spire - scaffold removal 3/4-4/24, subject to weather
- Fulton frontage- remove scaffold 4/15 - 4/29
- Painting - various elevations through 4/24
- Install upper roof through 4/26
- Stain glass restoration through 4/30/24
Campus Events
- April 19 Donaroo Campus Concert. Sobrato Center. 4/19 9A -10:30pm: Production Team load-in, soundcheck. Doors open 6:30, Concert 7-9pm, 10:30 Lights off. 4/20: Production team load-out
- April 26 Admissions Tours, Sobrato Center 9am - 1pm
- May 9 Last day of Spring semester classes
- May 16-18 Commencements
- May 20 - Aug 9 Summer sessions
- May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
- June Goats on Lone Mountain. Details TBD
UPDATE 4/05/2024:
- April 8-12 Landscape work including grading, dirt removal, and drain pipe installation will continue in the outdoor areas behind and adjacent to 2350 Turk and 2340 Turk. 8:30am - 5:00pm. There will be some noise when trucks remove offhaul. No jackhammering or concrete cutting is expected.
- April 15-19 Trenching for irrigation and electrical.
- Concrete pour for footings & pedestal, date TBD
- Landscaping at Golden Gate frontage to be scheduled.
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- April 12 Crane will be placed on Parker frontage between Fulton and McAllister for loading materials onto church roof. Several trucks will deliver materials. Traffic controls will be in place.
- Scaffold removal, various frontages through 5/9
- West Spire - scaffold removal 3/4-4/24, subject to weather
- Fulton frontage- painting 1st & 2nd coats
- Painting - various elevations through 4/24
- Stain glass restoration through 4/30/24
Campus Events
- April 13-14 Destination USF Campus wide event for students admitted Fall24. Multiple campus locations and events. Buses at various campus drop off zones
- April 19 Donaroo Campus Concert. Sobrato Center. 4/19 9A -10:30pm: Production Team load-in, soundcheck. Doors open 6:30, Concert 7-9pm, 10:30 Lights off. 4/20: Production team load-out
- April 26 Admissions Tours, Sobrato Center 9am - 1pm
- May 9 Last day of Spring semester classes
- May 16-18 Commencements
- May 20 - Aug 9 Summer sessions
- May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
- June Goats on Lone Mountain. Details TBD
UPDATE 03/29/2024:
- March 25 - April 5 Landscape work including grading, dirt removal, and drain pipe installation will continue in the outdoor areas behind and adjacent to 2350 Turk and 2340 Turk. 8:30am - 5:00pm, no work 3/30-31. There will be some noise when trucks remove offhaul. No jackhammering or concrete cutting is expected.
- Landscaping at Golden Gate frontage to be scheduled.
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- April 1 Crane will be placed on Parker frontage between Fulton and McAllister for loading materials onto church roof. Several trucks will deliver materials. Traffic controls will be in place.
- East Spire - scaffold removal of spire complete.
- West Spire - scaffold removal 3/4-4/24, subject to weather
- Fulton frontage- painting 1st & 2nd coats
- Mid-rooof and Dome - Paint Dome through 3/25
- Bell tower - remove scaffold complete
- Painting - north and west sides through 3/29
- Stain glass restoration through 4/30/24
Campus Events
- April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
- April 26 Admissions Tours, Sobrato Center 9am - 1pm
- May 9 Last day of Spring semester classes
- May 16-18 Commencements
- May 20 - Aug 9 Summer sessions
- June Goats on Lone Mountain. Details TBD
UPDATE 03/22/2024:
- March 25 - April 5 Landscape work including grading will continue in the outdoor areas behind and adjacent to 2350 Turk and 2340 Turk. 8:30am - 5:00pm.
- No work 3/30-31. There will be some noise when trucks remove offhaul. No jackhammering or concrete cutting is expected.
- Landscaping at Golden Gate frontage to be scheduled.
- March 25-26 Complete installation of handrails in areas around parking lot and Hayes Healy courtyard.
- Dates for parking lot waterproofing and other improvements have not yet been scheduled.
- East Spire - scaffold removal of spire complete.
- West Spire - scaffold removal 3/4-4/24, subject to weather
- Fulton frontage- painting 1st & 2nd coats
- Mid-rooof and Dome - Paint Dome through 3/25
- Bell tower - remove scaffold complete
- Painting - north and west sides through 3/29
- Stain glass restoration through 4/30/24
Campus Events
- March 25 Admissions Tours, Sobrato Center 9am - 1pm
- April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
- April 26 Admissions Tours, Sobrato Center 9am - 1pm
- June Goats on Lone Mountain. Details TBD
UPDATE 03/15/2024:
- March 18 - March 22. Grading work in landscaped area behind building, noisy at times.
- March 19 Concrete demo, jackhammering. Trucks will be onsite to remove debris.
- March 15 & 16: removal of 4 trees in front of Malloy BB Facility site.
- Landscaping at Golden Gate frontage to be scheduled.
- Installation of handrails in areas around parking lot and Hayes Healy courtyard delayed due to manufacturer schedule.
- Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled.
- East Spire - scaffold removal of spire complete.\
- West Spire - scaffold removal 3/4-4/24, subject to weather
- Fulton frontage- painting 1st & 2nd coats
- Mid-rooof and Dome - sheet metal repair through 3/15/34. Paint Dome through 3/25
- Bell tower - remove scaffold est. through 3/18-3/22
- Painting - north and west sides through 3/29
- Stain glass restoration through 4/1/24
- March 25 Admissions Tours, Sobrato Center 9am - 1pm
- April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
- April 26 Admissions Tours, Sobrato Center 9am - 1pm
- June Goats on Lone Mountain. Details TBD
UPDATE 03/08/2024:
- March 11 - 12 Plumbing contractor will replace plumbing clean outs at the Harney loading dock area. 8am starts. The work will be noisy at times.
- March 15 Lone Mtn Drive, center spur closure for tree removal.
- March 11 - March 20. Landscaping work in the area behind and to the east of 2350 Turk. The work will include the demolition of concrete pathways, the removal of some grass areas, and grading. This work is expected to last about 7 days (8:30am-4:30pm) , not including Saturday and Sunday and so should be completed by Wed March 20. The demolition work will be noisy for the first few days and will involve jackhammering to break up concrete. Trucks will be onsite to remove debris.
- March 8: removal of 4 trees in front of Malloy BB Facility site. Landscaping at Golden Gate frontage to be scheduled.
- Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled.
- East Spire - scaffold removal of spire complete.
- West Spire - scaffold removal 3/4-3/29, subject to weather
- Fulton frontage- painting 1st & 2nd coats
- Mid-rooof and Dome - sheet metal repair through 3/15/34
- Bell tower - remove scaffold est. through 3/12
- Painting - north and west sides through 3/29
- Stain glass restoration through 4/1/24
Campus Events
- March 1 - USF campus Post Office substation permanently closed
- March 11-15 Spring Break
- March 25 Admissions Tours, Sobrato Center 9am - 1pm
- April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
- April 26 Admissions Tours, Sobrato Center 9am - 1pm
- June Goats on Lone Mountain. Details TBD
UPDATE 03/01/2024:
- Installation of handrails in areas around parking lot and Hayes Healy courtyard delayed due to manufacturer schedule.
- Landscaping at Golden Gate frontage to be scheduled.
- The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired.
- Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled.
- East Spire - scaffold removal of spire complete.
- West Spire - scaffold removal 3/4-3/29, subject to weather
- Fulton frontage- painting 1st & 2nd coats
- Mid-roof and Dome - sheet metal repair through 3/15/34
- Bell tower - remove scaffold est. 3/8, subject to weather
- Painting - north and west sides through 3/29
- Stain glass restoration through 4/1/24
Campus Events
- March 1 - USF campus Post Office substation permanently closed
- March 11-15 Spring Break
- March 11-15 Lone Mtn Drive, center spur closure for tree removal; dates TBD
- March 25 Admissions Tours, Sobrato Center 9am - 1pm
- April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
- April 26 Admissions Tours, Sobrato Center 9am - 1pm
- June Goats on Lone Mountain. Details TBD
UPDATE 02/26/2024:
- Installation of handrails in areas around parking lot and Hayes Healy courtyard delayed due to manufacturer schedule.
- Landscaping at Golden Gate frontage to be scheduled.
- Preparing for final inspection
- Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled.
- Jan 29- Feb22 No work scheduled on site
- East Spire - scaffold removal of spire complete.
- West Spire - paint dome by 2/22, scaffold removal 3/4-3/29, subject to weather
- Fulton frontage- painting 1st & 2nd coats
- Mid-rooof and Dome - sheet metal repair through 3/15/34
- Bell tower - remove scaffold est. 3/4.
- Stain glass restoration through 3/11/24
Campus Events
- February 26 Baseball vs Seattle 1pm
- February 29: USF plans to provide bus service for USF students to the USF vs Gonzaga MBB at the Chase Center.
- Buses for students will be staged at the passenger loading zone in front of War Memorial Gym, departures at about 6:15 and 6:30pm, 7pm, 7:15pm. Return buses drop off on Parker, near McAllister. The USF team bus will return to the WMG location at about 11:30-midnight. USF is working to minimize idling & noise.
UPDATE 02/16/2024:
- Preparing for final inspection
- The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired.
- Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled.
- Jan 29- Feb22 No work scheduled on site
- Week of Feb 19- Concrete pour, north interior of church. One truck and one pump trailer via Parker entrance. Specific date TBD due to weather
- East Spire - scaffold removal of spire complete.
- West Spire - paint dome by 2/22, scaffold removal 3/4-3/29, subject to weather
- Fulton frontage- painting 1st & 2nd coats
- Mid-rooof and Dome - sheet metal repair through 3/15/34
- Bell tower - remove scaffold est. 3/4.
- Stain glass restoration through 3/11/24
- Presentation Theater refurbishment: project complete
Campus Events
- February 23-25 Baseball vs Nevada: 2/23 2pm; 2/24 1pm; 2/25 12pm
- February 26 Baseball vs Seattle 1pm
- February 29: USF plans to provide bus service for USF students to the USF vs Gonzaga MBB at the Chase Center.
- Buses will be staged at the passenger loading zone in front of WMG, departures at about 6:15 and 6:30pm, 7pm, 7:15 Return buses time and location TBD. USF is developing plans to minimize idling & noise.
UPDATE 02/02/2024:
- Feb 13 Complete water proofing in patio areas (subject to rain delay)
- Feb 14 Complete rebar install
- Feb 15 Concrete pour for HH plaza between Malloy BB Facility and Hayes Healy. 8am start.
- Landscaping at Golden Gate frontage to be scheduled.
- Finishing fencing install below roadway
- Preparing for final inspection
- Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled.
- Jan 29- Feb22 No work scheduled on site
- Feb 13 & 14- debris box delivered at Parker entrance, to place near trailer, remove morning of 2/14
- East Spire - scaffold removal by 2/19, subject to weather.
- West Spire - paint dome by 2/22, scaffold removal 3/4-3/29, subject to weather
- Fulton frontage- painting 1st & 2nd coats
- Mid-rooof and Dome - sheet metal repair through 3/15/34
- Bell tower - remove scaffold est. 3/4.
- Stain glass restoration through 3/11/24
- Presentation Theater:
- Final inspection to be scheduled.
Campus Events
- February 16 3-7pm Black History Month Cookout, Welch Field
- February 16-17 USF Baseball vs Fairleigh Dickinson 2pm Friday; 10a & 2p Saturday
- February 29: USF plans to provide bus service for USF students to the USF vs Gonzaga MBB at the Chase Center.
- 5 buses will be staged at the passenger loading zone in front of WMG, departures at 6:15 and 6:30pm and returns at 10:15 and 10:30pm. USF is developing plans to minimize idling & noise.
UPDATE 02/02/2024:
- Feb 5 Finish paver installation underneath Malloy BB facility and HH patio area, including delivery of pavers and base rock via Golden Gate entry drive. 8am start
- Feb 13 Complete water proofing in patio areas (subject to rain delay)
- Feb 14 Complete rebar install
- Feb 15 Concrete pour for HH plaza between Malloy BB Facility and Hayes Healy. 8am start.
- Building punch list walk TBD
- Finishing fencing install below roadway
- Preparing for final inspection
- The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired.
- Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled.
- Jan 29- Feb22 No work scheduled on site
- East Spire - finish coat complete, reinstall glass.
- West Spire - sheet metal restoration complete; finish coat through 2/13, subject to rain delays remove scaffold on west spire through 2/26
- Fulton frontage sheet metal restoration through Feb 9
- Mid-rooof and Dome - sheet metal repair through 3/1/34
- Bell tower - finish coat thru 2/16, remove scaffold est. 2/22
- Feb 6- install new light poles, east side.
- Stain glass restoration through 3/11/24
- Final inspection to be scheduled.
Campus Events
- February 2, 5:30pm Presentation Theater, Goodbye Mr. Chips, A Gordon Getty Opera
- February 6, 7-8pm Silk Series Speaker in Sobrato Center, Clarence B. Jones & Sterling K. Brown
UPDATE 01/26/2024:
- Jan 29 Sawcutting in area underneath Malloy BB facility and HH patio area. 8am start
- Jan 30 Concrete pour for HH plaza between Malloy BB Facility and Hayes Healy. 8am start.
- Jan 31 Light pole installation, sections of the perimeter
- Building punch list walk TBD
- Finishing fencing install below roadway
- Preparing for final inspection
- The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired.
- Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled.
- Jan 29- Feb22 No work scheduled on site
- Delivery of new lights poles for east side TBD
- Feb 2 - install new light poles, east side.
- West spire: sheet metal restoration complete; Paint 2 coats through 1/30
- Fulton frontage: sheet metal restoration through 2/14/24
- MidRoof and Dome: sheet metal repair through 3/1/24
- Stain glass restoration through 3/11/24
- Final inspection to be scheduled.
Campus Events
- February 6, 7-8pm Silk Series Speaker in Sobrato Center, Clarence B. Jones & Sterling K. Brown
UPDATE 01/19/2024:
- Repair work complete. Fence to be removed by 1/22
- Jan 23. Concrete pour for HH plaza between Malloy BB Facility and Hayes Healy. 8am start.
- Jan 29. Waterproofing patio and ramp areas
- Jan 25: Paving activity in area beneath building.
- Ongoing deliveries - 2-3/week
- Finishing fencing install below roadway
- Preparing for final inspection
- The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired
- Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled.
- Jan 22-29 No work scheduled on site
- Week of Jan 22: delivery of new lights poles for east side. Specific day TBD
- Jan 24-25: debris container delivery, fill, and removal
- Feb 2 - install new light poles, east side.
- West spire: sheet metal restoration thru 1/15/24; Exterior lighting through 1/
12/24 - Fulton frontage: sheet metal restoration through 2/14/24
- MidRoof and Dome: prepping sheet metal and windows for painting
- Final inspection to be scheduled.
- Jan 19-23 - cleaning space
Campus Events
- January 20 - 7pm Men’s BB vs St Mary’s. CBS TV trucks arrive at UC lot about 9am
- January 22 - First day of Spring Semester
- February 6, 7-8pm Silk Series Speaker in Sobrato Center, Clarence B. Jones & Sterling K. Brown
2023 - Year In Review:
UPDATE 12/20/2023:
- Dec 26 6AM to 8AM - Sobrato Gym & University Center
- Dec 27 6AM to 8AM - Gleeson Library & Koret Rec
- 12/22 Update: Concrete work will continue through 12/29, weather permitting. Area fenced off for safety; please heed safety instructions.
- Dec 25, 26, Jan 1: Site closed
- Dec 27 - 29. 8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall.
- Demo will involve saw cutting and jack hammering. It will be loud and disruptive.
- No work Dec 25.
- Dec 25, 26, Jan 1: Site closed
- Dec 26 - 29: install fiberglass tubing on north facade. Leveling work beneath building to prepare for pavers may be moderately noisy.
- Ongoing deliveries - 2-3/week
- Ongoing: install fencing below roadway; preparing for final inspection
- Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled.
- Dec 21-31 No work scheduled on site
- Dec 18 - 23 delivery of light poles for east side, turf removal at light sites, excavation for footings
- Dec 26-29 conduit installation at Welch Field for light poles
- East spire; sheet metal restoration through 12/23
- West spire: sheet metal restoration thru 1/15/24; Exterior lighting through 1/
12/24 - Fulton frontage: sheet metal restoration through 2/14/24
- MidRoof and Dome: prepping sheet metal and windows for painting
- No work scheduled
Campus Events
- January 2 - Intersession classes begin
- January 18 - Move-In Day, new and returning students
- January 22 - First day of Spring Semester
- February 6, 7-8pm Silk Series Speaker in Sobrato Center
Happy Holidays to all
UPDATE 12/15/2023:
- Dec 20 5AM to 7AM: Kendrick Hall & Zief Library
- Dec 26 6AM to 8AM - Sobrato Gym & University Center
- Dec 27 6AM to 8AM- Gleeson Library & Koret Rec
- Dec 1- Dec 8
- Leak in connection between Harney Science Center and the City storm sewer line at the loading dock driveway (Golden Gate & Chabot).
- 12/15 Update: Backfill complete; inspection complete. Concrete work will begin Thursday 12/21, weather permitting. Area fenced off for safety; please heed safety instructions.
- Dec 18 - 29. 8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall.
- Demo will involve saw cutting and jack hammering. It will be loud and disruptive.
- Pausing outdoor work for end of semester & Finals: no work Nov 23-Dec 15 and Dec 25.
- Dec 20-22: Fiberglass tubing delivery and painting. Punchlist
- Dec 26 - 29: install fiberglass tubing on north facade. Leveling work beneath building to prepare for pavers may be moderately noisy.
- Ongoing deliveries - 2-3/week
- Ongoing: install fencing below roadway; preparing for final inspection
- Dec 18-22 No work scheduled on site
- No work scheduled
- Dec 18 - 23 delivery of light poles for east side, turf removal at light sites, excavation for footings
- East spire; sheet metal restoration through 12/23
- West spire: sheet metal restoration thru 1/15/24; Exterior lighting through 1/12/24
- Fulton frontage: sheet metal restoration through 2/14/24
- MidRoof and Dome: prepping sheet metal and windows for painting
Campus Events
- December 15 - Mid Year Commencement
- January 2 - Intersession classes begin
- January 18 - Move-In Day, new and returning students
- January 22 - First day of Spring Semester
- February 6, 7-8pm Silk Series Speaker in Sobrato Center
UPDATE 12/08/2023:
- Presentation Theater: Dec 11-13 - Complete lift installation
- Dec 18 - 23 delivery of light poles for east side, turf removal at light sites, excavation for footings
- East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
- West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
- MidRoof and Dome: prepping sheet metal and windows for painting
Campus Events
- December 15 - Mid Year Commencement
- January 2 - Intersession classes begin
- January 18 - Move-In Day, new and returning students
- January 22 - First day of Spring Semester
UPDATE 12/01/2023:
- Dec 1- Dec 8 USF has found a leak in a pipe drain connection between Harney Science Center and the City stormsewer line at the loading dock driveway (Golden Gate & Chabot). The leak requires immediate repair. Contractors will remove a section of the sidewalk and expose the pipe. The work will require heavy equipment and may also initially involve saw-cutting and jack hammering. Once excavation is complete, quieter repair work will continue through next week.
- 12/1 Update: The excavation work is done for today 12/1. Because of underground utilities near this location, some of the excavation work will require hand digging which will slow things down.
- Nov 13 - 22; Dec 18 - 29. 8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall.
- Demo will involve saw cutting and jack hammering. It will be loud and disruptive.
- Pausing outdoor work for end of semester & Finals: no work Nov 23-Dec 15 and Dec 25.
Dec 1 - 11am - 5pm concrete demo at stairs landing near HH garage, needed to complete waterproofing and form new pathway.Completing remaining installation tasks, inspections underway. Installation of outdoor pavers.Dec 18- 22 install fiberglass tubing on north facadeOngoing deliveries - 2-3/week
- Ongoing: seal joints, minor concrete repairs, install fencing below roadway
- Dec 3-8 No work scheduled on site
- Presentation Theater: Completing lift installation
- Dec 15 No work at site
- East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
- West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
- MidRoof and Dome: prepping sheet metal and windows for painting
Campus Events
- December 15 - Mid Year Commencement
- January 2 - Intersession classes begin
- January 18 - Move-In Day, new and returning students
- January 22 - First day of Spring Semester
UPDATE 11/17/2023:
- Nov 13 - 22; Dec 18 - 29. 8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall.
- Demo will involve saw cutting and jack hammering. It will be loud and disruptive.
- Pausing outdoor work for end of semester/final: no work Nov 23-Dec 15 and Dec 25.
- Completing remaining installation tasks, inspections underway. Installation of outdoor pavers.
- Dec 18- 22 install fiberglass tubing on north facade
- Ongoing deliveries - 2-3/week
- Ongoing: seal joints, minor concrete repairs, install fencing below roadway
- Nov 14-21 guardrail work
- Nov 13-17 No work scheduled on site
- 11/17 & 11/20 - 22: install lift (3-5 days; if needed, work will continue 11/27)
- East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
- West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
- MidRoof and Dome: prepping sheet metal and windows for painting
Campus Events
- December 15 - Mid Year Commencement
UPDATE 11/10/2023:
- Nov 13 - 29. 8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. Demo will involve saw cutting and jack hammering. It will be loud and disruptive. No work on Nov 23 & 24.
- Ongoing: Completing remaining installation tasks, installing graphics, wall pads, inspections underway. Installation of outdoor pavers.
- Nov 13: ADA work on west side of Hayes Healy. Details TBD
- Ongoing deliveries - 2-3/week
- Ongoing: seal joints, minor concrete repairs, install fencing below roadway
- Nov 14: demobilize access road
- Nov 14-21 guardrail work
- Nov 13-17 No work scheduled on site
- 11/13 - 14 - install door stops for exit doors
- Mid to late next week - begin lift installation (work will last about 1 week)
- East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
- West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
- MidRoof and Dome: prepping sheet metal and windows for painting
- Coils in the AC units on the McLaren Complex roof have been replaced. Technicians will return to continue work on minor parts.
- 10/23 8am Technicians will be on site to replace some additional parts for the AC units located on McLaren Complex roof. Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units.
Campus Events
- Nov 16, 11-1pm Student event, Library Plaza
- December 15 - Mid Year Commencement
UPDATE 11/03/2023:
- Nov 8 11pm San Francisco Water Department completing a city water line replacement which will result in water shutdown in Kendrick Hall. The disruption of water service will last approximately three hours.
- This is a SFWater project and not initiated or managed by USF. This shutdown may affect nearby buildings.
- Ongoing: seal joints, minor concrete repairs, install fencing below roadway
- Nov 14: demobilize access road
- Nov 14-21 guardrail work
- Nov 6-10 No work scheduled on site
- Presentation Theater:
- 11/2 - 3: plaster work by lift
- 11/6 - 8: paint lift area
- Nov 7 - Delivery of new lighting fixtures, Parker Entrance
- Nov 10 - work on interior improvements begins
- East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
- West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
- MidRoof and Dome: prepping sheet metal and windows for painting.
- Ongoing: Completing remaining installation tasks, installing graphics, wall pads, inspections underway. Installation of outdoor pavers.
- Nov 3-4 power wash drive aisle between WMG and Malloy BB facility; paint on Saturday.
- Nov 13: ADA work on west side of Hayes Healy. Details TBD
- Ongoing deliveries - 2-3/week
- Coils in the AC units on the McLaren Complex roof have been replaced. Technicians will return to continue work on minor parts.
- 10/23 8am Technicians will be on site to replace some additional parts for the AC units located on McLaren Complex roof. Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units.
- November 3, 4-6pm USF Rising Mentorship Program at Gleeson Plaza - permit for amplified sound
- December 15 - Mid Year Commencement
UPDATE 10/27/2023:
- The Hayes Healy Garage will be closed for mandated driveway repairs from 8am Monday Oct 30 to 8am Thursday November 2.
- There will be no egress nor entry to the garage during that time.
- All vehicles must be removed from the garage by 8am Monday 10/30. Vehicles remaining in the garage after Monday morning will not be available for use until 8am Thursday.
- Continued shut down road for paving and overlay work, expected completion on Monday Oct 23. The work will be noisy and disruptive at times. Please follow flag person directions and signage.
- Oct 30-Nov 3 No work scheduled on site
- 10/30 - 11/3: dense drywall and plaster work (minimal noise)
- East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
- West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
- MidRoof and Dome: prepping sheet metal and windows for painting
- Masonry restoration ongoing through 10/31
- Ongoing: Completing remaining installation tasks, installing graphics, wall pads, inspections underway. Installation of outdoor pavers.
- Oct 30-Nov2 mandatory repair to Hayes Healy garage entry. HH garage will be closed. All vehicles must be removed from Hayes Healy garage by Monday 8am Oct 30
- Oct 31 Remove construction trailer
- Nov 2 Remove stair tower
- Ongoing deliveries - 2-3/week
- Coils in the AC units on the McLaren Complex roof have been replaced. Technicians will return to continue work on minor parts.
- 10/23 8am Technicians will be on site to replace some additional parts for the AC units located on McLaren Complex roof. Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units.
- Large attendance expected. USF lots will be ’no cite’ and open to guests
- Workshop,seminars and tours for prospective students
- USF Rising Mentorship Program at Gleeson Plaza - permit for amplified sound
UPDATE 10/13/2023:
- Monday Oct 16 Water shut off in LMM and Pac Wing for approximately 4 hours (8am - noon).
- Oct 16 - 17 Plumbing repair and pipe replacement in ROTC spaces, LMM
- Oct 6 -20. Shut down west half of viaduct for road overlay work. The work will be noisy and disruptive at times.
- Once the west section is complete, the work will move to the eastern section. Final stage will be to install overlay layer to roadway surface. Please follow flag person directions and signage.
- Please do not park on the Viaduct between the Parker entrance and the Anza St exit during this period. Such vehicles will be subject to towing.
- Oct 15 -17: Installation postponed. Date TBD
- Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
- Oct 16-20 No work scheduled on site
- 10/13 & 10/16: removal of scaffolding from stage (some noise)
- 10/13: install steel by lift (minimal noise)
- 10/16 - 20: framing by lift (some noise)
- 10/17 - 20: remove exterior scaffolding (some noise)
- 10/18: begin refinishing stage
- East spire: sheet metal restoration through 12/23
- West spire: sheet metal restoration to start 10/16, duration TBD
- MidRoof and Dome: prepping sheet metal and windows for painting
- Masonry restoration ongoing through 10/31
- Oct 14-16 Driveway btw Malloy BB facility and WMG closed until Oct 16 pm; sidewalk will be open to pedestrians Oct 16 am
- Ongoing: Flooring installation in lobbies, ongoing plastering, panel work on building’s south side (will be noisy during work hours at times), installation of outdoor pavers.
- Ongoing deliveries - 2-3/week
- Coils in the AC units on the McLaren Complex roof have been replaced. Technicians will return to continue work on minor parts.
- Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units.
Campus Events
- October 14. Student Leadership Conference at Koret. Parker btw Fulton and Golden Gate blocked off for buses.
- October 20 - 22 CelebrateUSF - alumni and family weekend
- Oct 20, Welch Field outdoor concert 12-3pm
- Oct 21 Silk Speaker Series at War Memorial Gym 11am - 12 pm
UPDATE 10/06/2023:
- Oct 6 -20. Shut down west half of viaduct for road overlay work. The work will be noisy and disruptive at times.
- Once the west section is complete, the work will move to the eastern section. Final stage will be to install overlay layer to roadway surface. Please follow flag person directions and signage.
- Please do not park on the Viaduct between the Parker entrance and the Anza St exit during this period. Such vehicles will be subject to towing.
- Oct 15 Sunday: Crane delivery and placement
- Oct 16 -17: Installation
- Oct 9-11 Engineering will be replace coils in the AC units on the McLaren Complex roof starting 8AM Monday 10/9/2023 through 10/11/2023. The coils will be delivered via truck at the Fulton St loading dock behind McLaren.
- Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units.
- 10/9 - Geotech work on site (minimal noise, start time 9:00am)
- 10/6: Demo exterior roof ladder
- 10/9 - 13: scaffolding removal from stage (some noise)
- 10/9: Install new exterior roof ladder (some noise)
- Located on outer south wall of theater loft
- 10/13: Steel installation for lift
- Through 9/29 -Ground level: strip west elevation, masonry restoration.
- MidRoof & Dome - sheet metal restoration, masonry
restoration - 10/2-17 Install east balustrades
- Thru Feb 2024 - stain glass restoration
- Oct 9-13 Flooring installation in lobbies, ongoing plastering, panel work on building’s south side (will be noisy at times).
- Oct 11-13 Driveway between WMG and Malloy BB: Oct 11: demo and saw cut existing drive (noisy work), Oct 12: install forms; Oct 13: concrete pour.
- Ongoing deliveries - 2-3/week
Campus Events
- October 20 - 22 CelebrateUSF - alumni and family weekend
UPDATE 9/15/2023:
- Oct 2 -4. Shut down west half of viaduct for road overlay work. The work will be noisy and disruptive at times. Once the west section is complete, it will be opened and the work will move to the eastern section.
- Oct 9-12 tentative: install overlay layer to roadway surface, partial road closures
- Complete; minor cleanup work through 9/29.
- 9/26: boring 1 hole in parking lot (some noise)
- 9/25 - 26: finish painting loft above stage; install emergency exit door; install handrails by emergency exit doors
- 9/27 - 29: install stage lights
- Through 9/29 -Ground level: strip west elevation, masonry restoration.
- MidRoof & Dome - sheet metal restoration, masonry restoration
- 10/2-17 Install east balustrades
- Thru Feb 2024 - stain glass restoration
- Sept 22 Complete/ close up street utility tie-in work near driveway between WMGym and Malloy site
- Sept 26-29 Installation of new driveway path at drive between WMG & Malloy BB site.
- Sept 5-26 Installation of new walkway and stairs between Malloy Pavilion and Gillson. Will involve concrete demo which will be loud at times. Please follow directions and signage.
- Ongoing - Removal of scaffolding, interior glazing, paint, hardware install, elevator, railings, exterior plastering etc.
- Ongoing deliveries - 2-3/week
Campus Events
- October 20 - 22 CelebrateUSF - alumni and family weekend
UPDATE 9/15/2023:
Lone Mountain Viaduct, 330 Parker Ave
University Community, please note:
- The garage will close end of the business day on Tuesday Sept 12.
- The garage will reopen in the morning on Tuesday Sept 19.
Ulrich Baseball Field
Lone Mountain Main & Lone Mountain North
Masonic East (formerly the Blood Bank)
School of Education Projects, 2350 Turk
- 9/15 & 9/18: set up scaffolding on stage
- 9/16 - 17: cut concrete on east side of stage (classes and seminars have been notified/relocated)
- 9/18 - 22: paint loft, paint smoke hatches, install stage lights
St Ignatius Church
- Through 9/22 -Ground level: strip west elevation, masonry restoration.
- Through 9/15 - East and West Spires: continue stripping paint, masonry restoration, repair balustrades
- Sept 18: work on interior to start; electrical infrastructure
- Thru Feb 2024 - stain glass restoration
Malloy Basketball Practice Facility/War Memorial Gym
- Sept 8 - 15 Street Utility Tie-in Work near driveway between WMGym and Malloy site Work will take place during normal hours 8am-3:30pm (not Saturday).There will be some saw cutting at beginning of work, then they will move on to the utility install. Flaggers in the street to assist with traffic. On off-hours, trench plates will be placed over work area per SFDPW requirements.
- Sept 5-26 Installation of new walkway and stairs between Malloy Pavilion and Gillson. Will involve concrete demo which will be loud at times. Please follow directions and signage.