Capital Projects Updates

2025:


UPDATE 1/30/2025:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

San Francisco Dept Pubic Works - Turk Blvd project - courtesy notice

The San Francisco Department of Public Works has advised us that construction is set to start on Turk Blvd in February. The first segment of work will span from Arguello Blvd. to Masonic Ave. However, only two blocks can be worked on at a time. Contractors plan on starting around February 20th.  This segment of work is anticipated to reach full completion around mid-August 2025. The scope of work will include grinding (removing) asphalt, concrete base work, bus pad installment, minor sewage repair work and ADA compliant curb ramps. After that, the roadway will be repaved. Traffic patterns for this segment may be affected. The public should be aware that lanes will shift as construction crews work on Turk Blvd.

This is a SF DPW project and not related to any USF projects. Please direct inquiries to the Department of Public Works. 

School of Education, 2350 Turk 

  • Feb 3-7: No work at the site this week

Masonic East, 270 Masonic (formerly the Blood Bank) 

  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

Campus Events/Academic Calendar

  • Feb 4 Lunar New Year celebration, Privet Plaza, 11:45am-12:45pm
  • Feb 6 Men’s Basketball vs St Mary’s, Sobrato Center 6pm. TV truck 

Dogs on campus: 

Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field. 

Please keep your pooch leashed and clean up its waste when you visit the campus. 

 


UPDATE 1/24/2025:

San Francisco Dept Pubic Works - Turk Blvd project - courtesy notice

The San Francisco Department of Public Works has advised us that construction is set to start on Turk Blvd in February. The first segment of work will span from Arguello Blvd. to Masonic Ave, however, only two blocks are permitted to be worked on at a time. Contractors plan on starting around February 20th.  This segment of work is anticipated to reach full completion around Mid-August 2025. The scope of work will include grinding (removing) asphalt, concrete base work, bus pad installment, minor sewage repair work and ADA compliant curb ramps. After that, the roadway will be repaved. Traffic patterns for this segment may be affected. The public should be aware that lanes will shift as construction crews work on Turk Blvd.

This is a SF DPW project and not related to any USF projects. Please direct inquiries to the Department of Public Works. 

Lower Campus Banners

  • Jan 30: Campus contractor will remove vinyl marketing banners from 34 light poles on lower campus, using a truck with a cherry picker. Please use caution when in proximity of the work and follow any signage and worker instructions. 

School of Education, 2350 Turk 

  • Jan 27-31: No work at the site this week

Masonic East, 270 Masonic (formerly the Blood Bank) 

Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

Campus Events/Academic Calendar

  • Jan 21 Undergrad classes start

Dogs on campus: 

Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field. 

Please keep your pooch leashed and clean up its waste when you visit the campus. 


UPDATE 1/17/2025:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

Harney Power Shut-off

  • Jan 18-19:  Harney and Lo Schiavo will close at 3pm Friday Jan 17
  • Power to Harney will be shut down Saturday, 1/18 to complete the electrical conduit project underneath the pathway between Gleeson and Harney. 
  • Harney and Lo Schiavo will close at 3pm Friday Jan 17 to enable tech staff to prepare for the shutoff  
  • Harney will remained closed until noon Sunday, 1/19.

School of Education, 2350 Turk 

  • Jan 20-24: No work at the site this week

Masonic East, 270 Masonic (formerly the Blood Bank) 

Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

 

Campus Events/Academic Calendar

  • Jan 21 Undergrad classes start

The Koret Health & Rec Center will observe limited hours for the upcoming winter & holiday break.

  • Jan 6-19. Monday-Friday: 7am-7pm; pool closes at 7pm.  Sat/Sun: 10am-5pm; pool closes at 4pm

Dogs on campus: 

Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field. 

Please keep your pooch leashed and clean up its waste when you visit the campus. 

 


UPDATE 1/10/2025:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

Dogs on campus: 

Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field. 

Please keep your pooch leashed and clean up its waste when you visit the campus. 

 

School of Education, 2350 Turk 

  • Jan 10: concrete bench delivery between 10am - 2pm
  • Jan 13 - 17: Continue stone installation (some noise when cutting stone pieces)

Masonic East, 270 Masonic (formerly the Blood Bank) 

Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

 

Campus Events/Academic Calendar

  • Jan 2-17 Intersession classes
  • Jan 6 Law school classes start
  • Jan 21 Undergrad classes start

The Koret Health & Rec Center will observe limited hours for the upcoming winter & holiday break.

  • Jan 6-19. Monday-Friday: 7am-7pm; pool closes at 7pm.  Sat/Sun: 10am-5pm; pool closes at 4pm

UPDATE 1/03/2025:

All dates below are best estimates subject to weather and other external impacts and may change without notice.

Dogs on campus: 

  • Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field. 
  • Please keep your pooch leashed and clean up its waste when you visit the campus. 

School of Education, 2350 Turk 

  • Continue stone installation around the statue plinth

Masonic East, 270 Masonic (formerly the Blood Bank) 

  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

Campus Events/Academic Calendar

  • Jan 2-17 Intersession classes
  • Jan 6 Law school classes start
  • Jan 21 Undergrad classes start

The Koret Health & Rec Center will observe limited hours for the upcoming winter & holiday break.

  • Dec 20-Jan 5  Closed for winter repairs and maintenance
  • Jan 6-19. Monday-Friday: 7am-7pm; pool closes at 7pm.  Sat/Sun: 10am-5pm; pool closes at 4pm

 

 


2024 in Review:


 

UPDATE 12/19/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

Dogs on campus: 

Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field. 

  • Please keep your pooch leashed and clean up its waste when you visit the campus. 

Transformer Cleaning, Lower Campus

For the Campus Community: the following building transformer cleaning schedule is for Monday 12/23 and Friday 12/27. This work will require that the buildings be powered down for a four hour duration as listed below. Please remember to power down any computers, office equipment or any other sensitive electronics in preparation for the building power shutdown.

  • Dec 23 Monday  Toler Hall & McLaren
  • Dec 23 Monday  CSI
  • Dec 27 Friday  Kalmanovitz Hall
  • Dec 27 Friday  Cowell Hall

Power will be turned off at 0500 and restored by 0900

 

School of Education, 2350 Turk 

  • Dec 20 & 23 - Continue stone installation around statue plinth
  • Dec 27 & 30 - Continue stone installation around statue plinth

Masonic East, 270 Masonic (formerly the Blood Bank) 

  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

Campus Events/Academic Calendar

  • Dec 4 Fall classes end
  • Dec 6-12 Exam period
  • Dec 30 MBB vs Santa Clara Sobrato Center 7pm 
  • Jan 2-17 Intersession classes
  • Jan 6 Law school classes start
  • Jan 21 Undergrad classes start

The Koret Health & Rec Center will observe limited hours for the upcoming winter & holiday break.

  • Dec 16-19 Open 7am-7pm. Pool closed. 
  • Dec 20-Jan 5  Closed for winter repairs and maintenance
  • Jan 6-19. Monday-Friday: 7am-7pm; pool closes at 7pm.  Sat/Sun: 10am-5pm; pool closes at 4pm

UPDATE 12/13/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

Dogs on campus: 

Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field. 

  • Please keep your pooch leashed and clean up its waste when you visit the campus. 

Transformer Cleaning, Lower Campus

For the Campus Community: the following building transformer cleaning schedule is for Monday, 12/23, and Friday, 12/27. This work will require that the buildings be powered down for a four-hour duration, as listed below. Please remember to power down any computers, office equipment, or any other sensitive electronics in preparation for the building power shutdown.

  • Dec 23 Monday  Toler Hall & McLaren
  • Dec 23 Monday  CSI
  • Dec 27 Friday  Kalmanovitz Hall
  • Dec 27 Friday  Cowell Hall

Power will be turned off at 0500 and restored by 0900

School of Education, 2350 Turk 

  • January TBD: remaining stone to be delivered and installed.

Masonic East, 270 Masonic (formerly the Blood Bank) 

  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

Campus Events/Academic Calendar

  • Dec 4 Fall classes end
  • Dec 6-12 Exam period
  • Dec 30 MBB vs Santa Clara Sobrato Center 7pm 
  • Jan 2-17 Intersession classes
  • Jan 6 Law school classes start
  • Jan 21 Undergrad classes start 

UPDATE 11/22/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

 

Dogs on campus: 

Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field. 

Please keep your pooch leashed and clean up its waste when you visit the campus. 

 

School of Education, 2350 Turk 

  • Early December: The concrete bench is to be delivered; the remaining stone is to be delivered and installed.

Masonic East, 270 Masonic (formerly the Blood Bank) 

  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

Campus Events

 

Academic Calendar

  • Dec 4 Fall classes end
  • Dec 6-12 Exam period
  • Jan 2-17 Intersession classes
  • Jan 6 Law school classes start
  • Jan 21 Undergrad classes start 

UPDATE 11/12/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

Dogs on campus: 

Disturbances from off-leash dogs and associated waste have increased recently, especially disrupting the community's quiet enjoyment of Welch Field. 

Please keep your pooch leashed and clean up its waste when you visit the campus. 

Thru November 15: Electrical conduit replacement

  • at Central Walk between Gleeson Library Cogeneration plant and Harney Science Center.
  • Walkway pavers to be removed for trench work needed to replace a compromised underground conduit.
  • October 28: temporary fencing to be installed. Follow posted signs for rerouting access paths to Harney Science and Gleeson Library entries.

School of Education, 2350 Turk 

  • Nov 13-15:  finish landscaping and light fixture installation
  • Thru 11/18: Stone delivery, concrete bench delivery and installation delivery of remaining stone pavers
  • Nov 17  Sisters of the Presentation private ceremony 2:00 -4:00pm

Masonic East, 270 Masonic (formerly the Blood Bank) 

Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

Campus Events

Nov 21 Thursday, Passenger loading zone @ War Memorial Gym (WMG)

Student Life and Athletics sponsoring bus transportation for students to the USF Legacy basketball doubleheader at the Chase Center.  Details and exact timing TBD.  General plan:

  • Staggered departures at WMG passenger zone, 1-2 buses at a time between approximately 3:15pm and 6:15 pm
  • Return drop offs at Parker Ave loading zone will be between approximately 9:30-10:30 pm.
  • USF Student Life staff will coordinate the departures to ensure quick loading with limited idling time and ensure that students disperse when they return

Academic Calendar

  • Dec 4 Fall classes end
  • Dec 6-12 Exam period
  • Jan 2-17 Intersession classes
  • Jan 6 Law school classes start
  • Jan 21 Undergrad classes start 

UPDATE 11/8/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

Thru November 15: Electrical conduit replacement at Central Walk between Gleeson Library Cogeneration plant and Harney Science Center.

  • Walkway pavers to be removed for trench work needed to replace a compromised underground conduit.
  • October 28: temporary fencing to be installed. Follow posted signs for rerouting access paths to Harney Science and Gleeson Library entries.

School of Education, 2350 Turk 

  • Thru Nov 8: Continue painting railings, landscapers, and planting
  • Thru 15: Stone delivery and installation. landscapers continue planting and mulching, light fixtures along path to be installed delivery of remaining stone pavers
  • Date TBD; light fixture installation
  • Nov 17  Sisters of the Presentation private ceremony 2:00 - 3:00pm

Masonic East, 270 Masonic (formerly the Blood Bank) 

  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

Campus Events

  • Nov 9 Saturday  Student Pre-Game Tailgate 6-7:30p,
  • In parking lot beneath Malloy Basketball Pavilion.  Amplified music until 7:30

Nov 21 Thursday, Passenger loading zone @ War Memorial Gym (WMG)

Student Life and Athletics sponsoring bus transportation for students to the USF Legacy basketball doubleheader at the Chase Center.  Details and exact timing TBD.  General plan:

  • Staggered departures at WMG passenger zone, 1-2 buses at a time between approximately 3:15pm and 6:15 pm
  • Return drop offs at Parker Ave loading zone will be between approximately 9:30-10:30 pm.
  • USF Student Life staff will coordinate the departures to ensure quick loading with limited idling time and ensure that students disperse when they return 

UPDATE 11/1/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

Thru November 15: Electrical conduit replacement at Central Walk between Gleeson Library Cogeneration plant and Harney Science Center.

  • Walkway pavers to be removed for trench work needed to replace a compromised underground conduit.
  • October 28: temporary fencing to be installed. Follow posted signs for rerouting access paths to Harney Science and Gleeson Library entries.
"Central Walkways Closure Route Map"
Central Walkways Closure Route Map

 

 

 

 

 

 

 

 

 

 

 

School of Education, 2350 Turk 

  • Nov 1:  finish railing installation (some noise drilling into concrete), painting railing
  • Nov 4 - 8: Continue painting railings, landscapers planting
  • Nov 11 - 15: Stone delivery and installation 
  • Date TBD; light fixture installation

Masonic East, 270 Masonic (formerly the Blood Bank) 

  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

St Ignatius Church

Campus Events

  • October 25th - CAB Fright Night  Gleeson Plaza / Welch Field, 7pm - 10pm, Student only event; sound system with music, halloween games 
  • Music will be turned off promptly at 10pm 

October 26th - Admissions Day, Sobrato Gym and Main Campus; 8am - 2pm 

  • Welcome in Sobrato Gym with breakout sessions throughout campus and a resource fair on Gleeson Plaza / Lawn / Welch Field

UPDATE 10/25/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

October 28 - November 15: Electrical conduit replacement at Central Walk between Gleeson Library Cogeneration plant and Harney Science Center.

  • Walkway pavers to be removed for trench work needed to replace a compromised underground conduit.
  • October 28: temporary fencing to be installed. Follow posted signs for rerouting access paths to Harney Science and Gleeson Library entries.

School of Education, 2350 Turk 

  • Oct 24 -25: landscaping and planting trees
  • Oct 28 - Nov1: continue landscaping and planting (minimal noise)

Masonic East, 270 Masonic (formerly the Blood Bank) 

  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

St Ignatius Church

Campus Events

  • October 25th - CAB Fright Night  Gleeson Plaza / Welch Field, 7pm - 10pm, Student only event; sound system with music, halloween games 
  • Music will be turned off promptly at 10pm 
  • October 26th - Admissions Day, Sobrato Gym and Main Campus; 8am - 2pm 
  • Welcome in Sobrato Gym with breakout sessions throughout campus and a resource fair on Gleeson Plaza / Lawn / Welch Field

 


UPDATE 10/11/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

School of Education, 2350 Turk 

  • Oct 17-18: soil and baserock deliveries
  • Oct 21-25: landscaping crew continues to prep for planting trees (minimal noise)

Masonic East, 270 Masonic (formerly the Blood Bank) 

Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

St Ignatius Church

Campus Events

  • Oct 17-20  Celebrate USF Alumni & Family Weekend

Oct 18 Family Welcome Reception

  • Various events: McClaren, Lone Mtn, Koret Lodge 4-8pm

Oct 19 

  • Silk Speaker Series, St Ignatius Church
  • Celebrate USF Food & Music Festival
  • Food & Music Festival 1-3pm. Noisy at times
  • Reunions (various campus location Lone Mountain & main campus) 3-9pm

Oct 20

  • Fun Run - in and around main campus
  • Reunions (Lone Mtn & main campus)

October 25th - CAB Fright Night  Gleeson Plaza / Welch Field, 7pm - 10pm, Student only event; sound system with music, halloween games 

  • Music will be turned off promptly at 10pm 

October 26th - Admissions Day, Sobrato Gym and Main Campus; 8am - 2pm 

  • Welcome in Sobrato Gym with breakout sessions throughout campus and a resource fair on Gleeson Plaza / Lawn / Welch Field

UPDATE 10/11/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

 

School of Education, 2350 Turk 

  • Oct 10-11: landscaping crew will dig holes to prep for trees
  • Oct 14-18: tree delivery and planting (minimal noise)

Masonic East, 270 Masonic (formerly the Blood Bank) 

  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

St Ignatius Church

Campus Events

  • Oct 17-20  Celebrate USF Alumni & Family Weekend
  • Oct 17 School of Nursing & Health Professions 70th Anniversary, Main Campus
  • Oct 18 Family Welcome Reception

Various events: McClaren, Lone Mtn, Koret Lodge 4-8pm

Oct 19 

  • Silk Speaker Series, St Ignatius Church
  • Celebrate USF Food & Music Festival
  • Food & Music Festival 1-3pm. Noisy at times
  • Reunions (various campus location Lone Mountain & main campus) 3-9pm

Oct 20

  • Fun Run - in and around main campus
  • Reunions (Lone Mtn & main campus)

UPDATE 10/05/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.

School of Education, 2350 Turk 

  • Oct 7-11 Ongoing paver installation (some noise with minimal stone cutting)

Masonic East, 270 Masonic (formerly the Blood Bank) 

  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 

Fromm Hall Residential Window Replacement

  • Project completed

Malloy Hall Exterior Rehab

  • Project completed

Malloy Basketball Practice Facility/War Memorial Gym .

  • Project completed

St Ignatius Church

  • Project completed

Campus Events

Oct 17-20  Celebrate USF Alumni & Family Weekend

  • Oct 17 School of Nursing & Health Professions 70th Anniversary, Main Campus
  • Oct 18 Family Welcome Reception
  • Various events: McClaren, Lone Mtn, Koret Lodge 4-8pm
  • Oct 19 
  • Silk Speaker Series, St Ignatius Church
  • Celebrate USF Food & Music Festival
  • Food & Music Festival 1-3pm. Noisy at time
  • Reunions (various campus location Lone Mountain & main campus) 3-9p
  • Oct 20
  • Fun Run - in and around main campus
  • Reunions (Lone Mtn & main campus)

UPDATE 9/27/2024:

 
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement
  • Punch list  
Malloy Hall Exterior Rehab
  • June 12 -Sept 27  Project completed
 
School of Education, 2350 Turk 
  • Sept 30-Oct 4 Ongoing irrigation installation. Paver delivery October 3; paver installation thereafter. 
Malloy Basketball Practice Facility/War Memorial Gym .
  • Sept 30 - Oct 2 Water proofing complete. Car-stops installation Oct 1. Lot should re-open Oct 2. 
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • Punch list 

Campus Events

Oct 17-20  Celebrate USF Alumni & Family Weekend

  • Oct 17 School of Nursing & Health Professions 70th Anniversary, Main Campus
  • Oct 18 Family Welcome Reception
  • Various events: McClaren, Lone Mtn, Koret Lodge 4-8pm
  • Oct 19 
  • Silk Speaker Series, St Ignatius Church
  • Celebrate USF Food & Music Festival
  • Food & Music Festival 1-3pm. Noisy at time
  • Reunions (various campus location Lone Mountain & main campus) 3-9p
  • Oct 20
  • Fun Run - in and around main campus
  • Reunions (Lone Mtn & main campus)

 


UPDATE 9/13/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement
  • Punch list  
Malloy Hall Exterior Rehab
  • June 12 -Sept 27  Resolve leaks on south side of Malloy Hall, Fulton frontage. PaintSurfacing work expected to be dusty. We recommend that windows in the areas of work remain closed.  Work hours 7:30a to 3:30pm (noisy work starts after 8am)
School of Education, 2350 Turk 
  • Sept 16-20 Ongoing irrigation lines install.  
  • Sept 16-20 Scaffold installation at School of Ed chimney tower. Intermittent noise 8am-4pm 
Malloy Basketball Practice Facility/War Memorial Gym .
  • Aug 23-Sept 30 Water proofing, upper parking deck. Street level parking deck will remain closed through completion of water proofing. 
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
  • St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  

Punch list 

  • Sept 23-25 PGE overhead work and underground wire pull
  • Sept 26-27 Sidewalk repairs 
Campus Events
  • Sept 24 School of Management Centennial Celebration, Welch Field 11:30 am start. Some noise: music & speakers 
  • Oct 1 Bruce Mahoney Volleyball Game, Sobrato Center, 5:30pm
  • Oct 17-20  Celebrate USF Alumni & Family Weekend
  • Oct 17 School of Nursing & Health Professions 70th Anniversary, Main Campus
  • Oct 18 Family Welcome Reception
  • Oct 19 
    • Silk Speaker Series, Sobrato Center
    • Celebrate USF Food & Music Festival
    • Reunions (Lone Mountain & main campus)
  • Oct 20
    • Fun Run - in and around main campus
    • Reunions (Lone Mtn & main campus)

UPDATE 9/6/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement
  • Punch list  
Malloy Hall Exterior Rehab
  • June 12 -Sept 27  Resolve leaks on south side of Malloy Hall, Fulton frontage. PaintSurfacing work expected to be dusty. We recommend that windows in the areas of work remain closed.  Work hours 7:30a to 3:30pm (noisy work starts after 8am)
School of Education, 2350 Turk 
  • Sept 9-16 Ongoing irrigation lines install.  
  • Scaffold installation at School of Ed chimney tower - dates TBD
Malloy Basketball Practice Facility/War Memorial Gym .
  • Aug 23-Sept 30 Water proofing, upper parking deck. Street level parking deck will remain closed through completion of water proofing. 
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled.
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
 
Punch list 
  • Sept 9 PGE installs power pole on Mcallister. 
  • Sept 10-13 Street trench/patch street
  • Sept 23-25 PGE overhead work and underground wire pull
  • Sept 26-27 Sidewalk repairs 
Campus Events
  • Oct 17-20  Celebrate USF Alumni & Family Weekend
  • Oct 17 School of Nursing & Health Professions 70th Anniversary, Main Campus
  • Oct 18 Family Welcome Reception
  • Oct 19 
    • Silk Speaker Series, Sobrato Center
    • Celebrate USF Food & Music Festival
    • Reunions (Lone Mountain & main campus
  • Oct 20
    • Fun Run - in and around main campus
    • Reunions (Lone Mtn & main campus)

UPDATE 8/30/2024:

 
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement
  • Punch list
Malloy Hall Exterior Rehab
  • June 12 -Sept 27  Resolve leaks on south side of Malloy Hall, Fulton frontage. PaintSurfacing work expected to be dusty. We recommend that windows in the areas of work remain closed.  Work hours 7:30a to 3:30pm (noisy work starts after 8am)
School of Education, 2350 Turk 
Aug 28-Sept 3 Railing installation. Some concrete drilling, noisy at times.
Sept 3-6 Continue installing irrigation lines.  
 
Malloy Basketball Practice Facility/War Memorial Gym .
  • Aug 23-Sept 30 Water proofing, upper parking deck. Street level parking deck will remain closed through completion of water proofing. 
 
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • Punch list 
  • Sept 9 PGE install power pole on Mcallister. 
  • Sept 23-25 PGE overhead work and underground work 

Campus Events 

  • Oct 17-20  Celebrate USF Alumni Weekend
  • Oct 19 - Silk Series Lecture 

UPDATE 8/23/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement
  • Punch list  
Malloy Hall Exterior Rehab
  • June 12 -Sept 27  Resolve leaks on south side of Malloy Hall, Fulton frontage. PaintSurfacing work expected to be dusty. We recommend that windows in the areas of work remain closed.  Work hours 7:30a to 3:30pm (noisy work starts after 8am)
School of Education, 2350 Turk 
  • Aug 28  Scaffolding removal, east side: 8:00 - 9:00am on 8/28. Noisy at times. 
  • Aug 28-29 Railing installation. Some concrete drilling, noisy at times. 
Malloy Basketball Practice Facility/War Memorial Gym .
  • Aug 23-Sept 13 Water proofing, upper parking deck. Street level parking deck will remain closed through completion of water proofing. 
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • Punch list 
  • Sept 9 PGE install power pole on Mcallister. 
  • Sept 23-25 PGE overhead work and underground work 

Campus Events 

  • Oct 17-20  Celebrate USF Alumni Weekend
  • Oct 19 - Silk Series Lecture 

UPDATE 7/19/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Campus Transformer Maintenance 
This work will require that the buildings be powered down for the two hour duration listed below. Please remember to power down any computers, office equipment or any other sensitive electronics in preparation for the building power shutdown.
  • July 24 Harney Science - Wednesday 7/24/24 - 4:30 AM to 6:30 AM
  • July 24 Fromm Hall/SI Church - Wednesday 7/24/24 - 5AM to 7AM
  • July 25 Hayes Healy - Thursday 7/25/24 - 5AM to 7AM
  • July 25 Gillson Hall / Malloy Pavilion - Thursday 7/25/24 - 5AM to 7AM
Ulrich Field Turf Repair
  • Aug 12-16   Turf maintenance & repair. Some parking stalls on south side of Golden Gate near Masonic will be reserved for equipment during this period. 
Fromm Hall Residential Window Replacement
  • July 25-26 Desk delivery & install  
  • July 24-Aug 2 Window shades install
  • Exterior painting prep & painting: scheduled completion by July 26
  • July 22-26 Scaffold removal 
  • Faculty and students access to Xarts through the NW loading dock door -  6am and 2:30pm.
Malloy Hall Exterior Rehab
  • June 12 -Aug 14 Locate and resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Scaffold install ongoing. 
  • Surfacing work in preparation for painting which is expected to be dusty. We recommend that windows in the areas of work remain closed through the end of next week.  Work hours 7:30a to 3:30pm (noisy work starts after 8am)
School of Education, 2350 Turk 
  • July 22 - Aug 2: paver install and concrete work for bollard bases; begin stone install
Malloy Basketball Practice Facility/War Memorial Gym 
  • July 23 delivery, ground cover.
  • July 31 anticipated completion for landscaping
  • Parking deck; restriping & overlay; concrete repairs. Rescheduled to mid August  
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • July 22-23 Fire alarm testing. Noisy at times
  • July 29-Aug 2 Remove trailer, specific date TBD
  • Sept 9 PGE install power pole on Mcallister. 
  • Sept 23-25 PGE overhead work and underground work 

Campus Events 

  • May 20 - Aug 9 Summer sessions
  • July 10  Goats start on Lone Mountain. 
  • Aug 10 New Student Move-in Day
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 
  • Aug 22 Silk Lecture Series Sobrato Center 6-9pm

UPDATE 7/12/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
A large tractor trailer will be on Gleeson Plaza Tuesday/Wednesday July 9-10 from 6am to 3pm. Please use caution in the area.
 
Fromm Hall Residential Window Replacement
  • Interior work ongoing:  to be completed by 7/17
  • Exterior painting prep & painting ongoing
  • July 22-26 Scaffold removal 
  • July 29 estimated completion date
  • Faculty and students access to Xarts through the NW loading dock door -  6am and 2:30pm.
Malloy Hall Exterior Rehab
  • June 12 -Aug 14 Locate and resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Scaffold install ongoing. 
  • Surfacing work in preparation for painting which is expected to be dusty. We recommend that windows in the areas of work remain closed through the end of next week.
  • Work hours 7:30a to 3:30pm (noisy work starts after 8am)
School of Education, 2350 Turk 
  • July 12 concrete pour (some noise)
  • July 15-19 remove form boards, clean site
Malloy Basketball Practice Facility/War Memorial Gym 
  • July 3 -17: Landscaping install at Golden Gate frontage; tree planting
  • July 15 -16 deliveries green surface materials, planters,  soils 
  • July 23 delivery, ground cover.
  • July 8-24  Parking deck; restriping & overlay; concrete repairs 
  • July 31 anticipated completion
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • July 8-19  Replaster & re-stucco exterior planters on Fulton
  • July 15-19 Remove perimeter fence except at transformer; that fence will stay in place until PG&E completes its work (Sept)
  • July 22-23 Fire alarm testing. Noisy at times
  • July 29-Aug 2 Remove trailer, specific date TBD

Campus Events 

  • May 20 - Aug 9 Summer sessions
  • July 10  Goats start on Lone Mountain. 
  • Aug 10 New Student Move-in Day
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 
  • Aug 22 Silk Lecture Series Sobrato Center 6-9pm

UPDATE 7/2/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
A large tractor trailer will be on Gleeson Plaza Tuesday/Wednesday July 9-10 from 6am to 3pm. Please use caution in the area.
 
Fromm Hall Residential Window Replacement
  • Interior work ongoing:  caulking, skim coating, painting
  • Exterior painting prep & painting: work on south elevation will resume July 1
  • July 4-5 No work
  • July 29 estimated completion date
  • Faculty and students access to Xarts through the NW loading dock door -  6am and 2:30pm.
Malloy Hall Exterior Rehab
  • June 12 -Aug 14 Locate and resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Scaffold install ongoing. 
  • June 28 - July 7  surfacing work in preparation for painting which is expected to be dusty. We recommend that windows in the areas of work remain closed through the end of next week.
  • Work hours 7:30a to 3:30pm (noisy work starts after 8am)
School of Education, 2350 Turk 
  • July 3: grading work. Some noise
  • July 4-5 No work
  • July 8-12 continue grading work and form rebar in preparation for concrete pour (noisy at times)
  • July 12 concrete pour (some noise)
Malloy Basketball Practice Facility/War Memorial Gym 
  • July 3 -17: Landscaping install at Golden Gate frontage; tree planting
  • July 8-24  Parking deck; restriping & overlay; concrete repairs 
 
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • Thru July 10 finishing interior  and roof work
  • June 3-29 Stain glass installation  Delivery of portable work space to Plaza on June 29
  • July 8-19  Replaster & re-stucco exterior planters on Fulton

Campus Events 

  • May 20 - Aug 9 Summer sessions
  • July 10  Goats start on Lone Mountain. 
  • Aug 10 New Student Move-in Day
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 

UPDATE 6/14/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
PG&E continuing underground work near Parker & McAlister. 
 
Fromm Hall Residential Window Replacement
  • June 28 Window installation to be completed 6/28
  • Interior work ongoing:  caulking, skim coating, painting
  • Exterior painting prep & painting: work on south elevation will resume July 1
  • July 4-5 No work
  • July 29 estimated completion date
  • Faculty and students access to Xarts through the NW loading dock door -  6am and 2:30pm.
Malloy Hall Exterior Rehab
  • June 12 -Aug 14 Locate and resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Scaffold install ongoing. 
  • Work hours 7:30a to 3:30pm (noisy work starts after 8am)
  • June 28 - July 7   additional surfacing work in preparation for painting which is expected to be dusty. We recommend that windows in the areas of work remain closed through the end of next week..
 
School of Education, 2350 Turk 
  • June 27 - 28: 
    • install fountain wall embeds
    • finish forms for retaining wall and curb (some noise)
  • June 28: concrete pour for fountain walls, retaining wall, and curb (some noise)
  • July 1-3: grading and prep for sub slab
  • July 4 No work
  • July 8-12: continue grading for sub slab and dig footings for screen wall with goal of next concrete pour towards end of the week
Malloy Basketball Practice Facility/War Memorial Gym 
  • July 1 -17: Landscaping install at Golden Gate frontage
  • TBD restriping parking deck
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • Thru July 10 finishing interior  and roof work
  • June 3-29 Stain glass installation  Delivery of portable work space to Plaza on June 29
  • July 8-19  Replaster & re-stucco exterior planters on Fulton

Campus Events 

  • May 20 - Aug 9 Summer sessions
  • July 10  Goats start on Lone Mountain. 
  • Aug 10 New Student Move-in Day
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 

UPDATE 6/28/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
Through June 21 (estimated) : SFPUC plans to upgrade the storm sewer line on Parker between McAllister and Fulton. Trenching & traffic re-routes. This is a PUC project and not related to USF or ST Ignatius Church.  
PG&E will also start underground work in the same area around June 17, digging a trench & installing pipe across Parker at McAllister. A third effort will be the installation of a water line in the same area, est June 10-14. The work will be noisy. Please follow traffic controls. 
 
Fromm Hall Residential Window Replacement 
  • June 17  begin painting building exterior, about 2 weeks duration
  • Scaffolding install & window demo complete. 
  • On going window installations. Saturday work as needed.
  • Faculty and students access to Xarts through the NW loading dock door -  6am and 2:30pm.
Malloy Hall Exterior Rehab
  • June 12 -Aug 14 Locate and resolve leaks on south side of Malloy Hall, Fulton frontage. Paint. Scaffold install ongoing. 
  • Work hours 7:30a to 3:30pm (noisy work starts after 8am)
  • The work will be done is three sections, starting from the southwest corner, moving east along the south wall on Fulton. Each section is expected to take about 3 weeks. The workers will start each section by grinding & chipping away the exterior material & draining water bubbles. This work will be noisy, with interior vibrations. The second two weeks per section should be less disruptive as they clean out & replace joints, waterproof and paint the exterior wall. 
School of Education, 2350 Turk 
  • June 10-21 Continuing form & rebar work 
  • June 21 Concrete pour. Will be noisy at times
Malloy Basketball Practice Facility/War Memorial Gym 
  • TBD: Landscaping at Golden Gate frontage
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • May 30-June 21 install flashings, lights at vrs roof locations
  • Thru June 28 ongoing interior work
  • June 3-28 Stain glass installation  

Campus Events 

  • May 20 - Aug 9 Summer sessions
  • June 18  Goats on Lone Mountain. 
  • Aug 10 New Student Move-in Day
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 

UPDATE 6/7/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Through June 21 (estimated) : SFPUC plans to upgrade the storm sewer line on Parker between McAllister and Fulton. Trenching & traffic re-routes. This is a PUC project and not related to USF or ST Ignatius Church.  PG&E will also start underground work in the same area around June 15, digging a trench & installing pipe across Parker at McAllister. A third effort will be the installation of a water line in the same area, est June 10-14. The work will be noisy. Please follow traffic controls. 
 
Fromm Hall Residential Window Replacement 
  • Scaffolding install & millwork demo complete. 
  • On going window installations. Saturday work as needed.
  • Faculty and students access to Xarts through the NW loading dock door -  6am and 2:30pm.
Malloy Hall Exterior Rehab
  • South facade (on Fulton): locate and resolve leaks. Paint. Scaffold install ongoing. Some noise during discovery work

School of Education, 2350 Turk 
  • May 28-31: Prep work for fountain installation in back garden area
  • June 3-7: Build forms for concrete footings (some noise)
  • June 10-14 Continue form work (possible concrete pour later in week, otherwise the following week)
  • TBD early - mid June concrete pour
Malloy Basketball Practice Facility/War Memorial Gym 
  • TBD: Landscaping at Golden Gate frontage
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • May 30-June 21 install flashings, lights at vrs roof locations
  • Thru June 28 ongoing interior work
  • June 3-28 Stain glass installation  

Campus Events 

  • May 20 - Aug 9 Summer sessions
  • June 18  Goats on Lone Mountain. 
  • Aug 10 New Student Move-in Day
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 

UPDATE 5/31/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
May 28 - June 10:  SFPUC plans to upgrade the storm sewer line on Parker between McAllister and Fulton. Trenching & traffic re-routes. This is a PUC project and not related to USF or ST Ignatius Church.
 
Fromm Hall Residential Window Replacement 
  • Thru June 7- Scaffolding install, window demo. 
  • Saturday work as needed.
Malloy Hall Exterior Rehab
  • South facade (on Fulton): locate and resolve leaks. Paint. Scaffold install ongoing. Some noise during discovery work
  • May 29 power washing begins
School of Education, 2350 Turk 
  • May 28-31: Prep work for fountain installation 
  • June 3-7: Build forms for concrete footings (some noise)
  • TBD early June concrete pour
Malloy Basketball Practice Facility/War Memorial Gym 
  • TBD: Landscaping at Golden Gate frontage
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church.  
  • June 3 stair tower removal 
  • May 30-June 21 install flashings, lights at vrs roof locations
  • Thru June 14 ongoing interior work
  • June 3-28 Stain glass installation  

Campus Events 

  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm: Load-out 1pm -9pm
  • June 18  Goats on Lone Mountain. 
  • Aug 10 New Student Move-in Day
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 

UPDATE 5/24/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
May 28 - June 10:  SFPUC plans to upgrade the storm sewer line on Parker between McAllister and Fulton. Trenching & traffic re-routes. This is a PUC project and not related to USF or ST Ignatius Church.
 
Fromm Hall Residential Window Replacement 
  • May 20-31- Scaffolding install. Noisy at times
    • move furniture, deliver materiel, abate & demo
      No work May 25 &28
    • May 28-31: Deliveries for new windows and additional scaffolding at the XArts loading dock
Malloy Hall Exterior Rehab
  • South facade (on Fulton): locate and resolve leaks. Paint. Scaffold install ongoing. Some noise during discovery work
  • May 29 power washing begins
School of Education, 2350 Turk 
  • May 24 & 28: Complete paving west section of pathway
  • May 28-31: Fountain contractor to do minimal excavation and begin fountain installation (some noise)
  • June 3-7: Fountain contractor to continue fountain installation (some noise)
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • May 28-31 Scaffold removal at Dome & mid-roof. Detail work at upper roof. 
  • June 3 stair tower removal 
  • May 30-June 7 install flashings, lights at vrs roof locations
  • June 3-14 Stain glass installation  

Campus Events 

  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm: Load-out 1pm -9pm
  • June 18  Goats on Lone Mountain. 
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 

UPDATE 5/17/2024:

 
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement 
  • May 20 project start date, Mon - Sat, 8am start (9am Sat)
  • May 20-31- Scaffolding install. Noisy at times
  • move furniture, deliver materiel, abate & demo
  • No work May 25 &28
Malloy Hall Exterior Rehab
  • May 21 estimated start, work will continue through most of the summer
  • South facade (on Fulton): locate and resolve leaks. Paint
  • Scaffold install ongoing. Some noise during discovery work
School of Education, 2350 Turk 
  • May 6-17  ongoing paver install (some noise as trucks deliver sand and gravel)
  • Workers will not do loud work on 5/10 and during Finals Week 5/11-16
  • Date TBD Concrete pour for footings & pedestal 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
 
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • May 23 - crane at NE corner of Church to help remove scaffolding
  • Scaffold removal at Dome & mid-roof through 5/23
  • May 20-24 install lighting & flashing
  • June 3-14 Stain glass installation 

Campus Events 

  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June 18  Goats on Lone Mountain. 
  • Aug 10-19 Orientation 
  • Aug 20 Classes begin 

UPDATE 5/10/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement 
  • May 20 estimated start date
Malloy Hall Exterior Rehab
  • May 21 estimated start
  • South facade (on Fulton): locate and resolve leaks. Paint
  • Scaffold install ongoing. Some noise during discovery work
School of Education, 2350 Turk 
  • May 13-17 Finals week. No work will occur at the project site
  • May 20-24  ongoing paver install (some noise as trucks deliver sand and gravel)
  • Date TBD Concrete pour for footings & pedestal 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
  • April 22 -29  concrete coring, 
  • Apr 22 - May 13 planter bed & retaining wall waterproofing 
  • May 16 - 29  landscaping 
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Dome painting extended through May 15
  • Roof: re-roof work, by section, through 6/3
  • Stain glass restoration through 6/14 

Campus Events 

  • May 9 Last day of Spring semester classes
  • May 16 Commencement Mass 3p St Ignatius Church
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

 


UPDATE 5/3/2024:

 
All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement 
  • May 20 estimated start date
Malloy Hall Exterior Rehab
  • May 21 estimated start
  • South facade (on Fulton): locate and resolve leaks. Paint
  • Scaffold install ongoing. Some noise during discovery work
School of Education, 2350 Turk 
  • May 6-17  ongoing paver install (some noise as trucks deliver sand and gravel)
  • Workers will not do loud work on 5/10 and during Finals Week 5/11-16
  • Date TBD Concrete pour for footings & pedestal
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
  • April 22 -29  concrete coring, 
  • Apr 22 - May 13 planter bed & retaining wall waterproofing 
  • May 16 - 29  landscaping 

LoSchiavo Science 

  • May 20 -24 Date tentative. A large crane will be positioned in the Gleeson Plaza limiting pedestrian travel during work hours in that area as well as the west side of CSI and the CSI building itself. CSI building ventilation will be offline. CSI will be inaccessible during crane lift.  Please exercise caution in the area.
  • Crane delivery will be via truck from Parker entrance.
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Scaffold removal, various frontages through 5/9
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- remove scaffold 4/15 - 4/29
  • Painting - various elevations through 4/24
  • Install upper roof through 4/26
  • Stain glass restoration through 4/30/24 

Campus Events 

  • May 9 Last day of Spring semester classes
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 4/26/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
Fromm Hall Residential Window Replacement 
  • May 20 estimated start date
Malloy Hall Exterior Rehab
  • South facade (on Fulton): locate and resolve leaks. Paint
  • Scaffold install ongoing. Some noise during discovery work
School of Education, 2350 Turk 
  • April 29-May 1 begin paver install (some noise as trucks deliver sand and gravel)
  • Date TBD Concrete pour for footings & pedestal 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
    • April 22 -29  concrete coring, 
    • Apr 22 - May 13 planter bed & retaining wall waterproofing May 16 - 29  landscaping 

LoSchiavo Science 

  • May 20 -24 Date tentative. A large crane will be positioned in the Gleeson Plaza limiting pedestrian travel during work hours in that area as well as the west side of CSI and the CSI building itself. CSI building ventilation will be offline. CSI will be inaccessible during crane lift.  Please exercise caution in the area.
  • Crane delivery will be via truck from Parker entrance.
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Scaffold removal, various frontages through 5/9
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- remove scaffold 4/15 - 4/29
  • Painting - various elevations through 4/24
  • Install upper roof through 4/26
  • Stain glass restoration through 4/30/24 

Campus Events 

  • April 26 Admissions Tours, Sobrato Center 9am - 1pm. Buses will load and unload in front of War Memorial Gym
  • May 9 Last day of Spring semester classes
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 4/19/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
School of Education, 2350 Turk 
  • April 15-26 Install electrical conduit and irrigation lines.
  • April 29-May 1 begin paver install (some noise as trucks deliver sand and gravel)
  • Date TBD Concrete pour for footings & pedestal 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
  • April 22 -29  concrete coring, 
  • Apr 22 - May 13 planter bed & retaining wall waterproofing 
  • May 16 - 29  landscaping 

LoSchiavo Science 

  • May 20 -24 Date tentative. Finalizing schedule for a crane lift to replace ventilation related equipment on the roof of CSI. Once time is set, the plaza area in front of Gleeson and CSI building will be cordoned off. CSI building ventilation will be offline. Access to CSI will be inaccessible during crane lift.
  • Crane delivery will be via truck from Parker entrance.
Masonic East, 270 Masonic (formerly the Blood Bank)
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Scaffold removal, various frontages through 5/9
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- remove scaffold 4/15 - 4/29
  • Painting - various elevations through 4/24
  • Install upper roof through 4/26
  • Stain glass restoration through 4/30/24 

Campus Events 

  • April 19 Donaroo Campus Concert. Sobrato Center. 4/19 9A -10:30pm: Production Team load-in, soundcheck. Doors open 6:30, Concert 7-9pm, 10:30 Lights off. 4/20: Production team load-out
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • May 9 Last day of Spring semester classes
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 4/15/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
School of Education, 2350 Turk 
  • April 15-26 Install electrical conduit and irrigation lines.
  • April 29-May 1 begin paver install (some noise as trucks deliver sand and gravel)
  • Date TBD Concrete pour for footings & pedestal.
Malloy Basketball Practice Facility/War Memorial Gym 
  • Apr 22 - May 29: Landscaping at Golden Gate frontage
  • April 22 -29  concrete coring, 
  • Apr 22 - May 13 planter bed & retaining wall waterproofing 
  • May 16 - 29  landscaping 

LoSchiavo Science 

  • May 20 -24 Date tentative. Finalizing schedule for a crane lift to replace ventilation related equipment on the roof of CSI. Once time is set, the plaza area in front of Gleeson and CSI building will be cordoned off. CSI building ventilation will be offline. Access to CSI will be inaccessible during crane lift.
  • Crane delivery will be via truck from Parker entrance.
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Scaffold removal, various frontages through 5/9
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- remove scaffold 4/15 - 4/29
  • Painting - various elevations through 4/24
  • Install upper roof through 4/26
  • Stain glass restoration through 4/30/24 

Campus Events 

  • April 19 Donaroo Campus Concert. Sobrato Center. 4/19 9A -10:30pm: Production Team load-in, soundcheck. Doors open 6:30, Concert 7-9pm, 10:30 Lights off. 4/20: Production team load-out
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • May 9 Last day of Spring semester classes
  • May 16-18 CommencementsMay 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 4/15/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
School of Education, 2350 Turk 
  • April 15-26 Trenching for irrigation and electrical. Begin installing electrical conduit and irrigation lines.
  • Date TBD Concrete pour for footings & pedestal 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Landscaping at Golden Gate frontage to be scheduled for May, Details TBD
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Scaffold removal, various frontages through 5/9
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- remove scaffold 4/15 - 4/29
  • Painting - various elevations through 4/24
  • Install upper roof through 4/26
  • Stain glass restoration through 4/30/24 

Campus Events 

  • April 19 Donaroo Campus Concert. Sobrato Center. 4/19 9A -10:30pm: Production Team load-in, soundcheck. Doors open 6:30, Concert 7-9pm, 10:30 Lights off. 4/20: Production team load-out
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • May 9 Last day of Spring semester classes
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

 


UPDATE 4/05/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
School of Education, 2350 Turk 
  • April 8-12  Landscape work including grading, dirt removal, and drain pipe installation will continue in the outdoor areas behind and adjacent to 2350 Turk and 2340 Turk. 8:30am - 5:00pm.  There will be some noise when trucks remove offhaul. No jackhammering or concrete cutting is expected
  • April 15-19 Trenching for irrigation and electrical. 
  • Concrete pour for footings & pedestal, date TBD
Malloy Basketball Practice Facility/War Memorial Gym 
  • Landscaping at Golden Gate frontage to be scheduled.
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • April 12 Crane will be placed on Parker frontage between Fulton and McAllister for loading materials onto church roof. Several trucks will deliver materials. Traffic controls will be in place.
    • Scaffold removal, various frontages through 5/9
    • West Spire - scaffold removal 3/4-4/24, subject to weather
    • Fulton frontage- painting 1st & 2nd coats
    • Painting - various elevations through 4/24
    • Stain glass restoration through 4/30/24

Campus Events 

  • April 13-14 Destination USF Campus wide event for students admitted Fall24. Multiple campus locations and events. Buses at various campus drop off zones
  • April 19 Donaroo Campus Concert. Sobrato Center. 4/19 9A -10:30pm: Production Team load-in, soundcheck. Doors open 6:30, Concert 7-9pm, 10:30 Lights off. 4/20: Production team load-out
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • May 9 Last day of Spring semester classes
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • May 25 St Ignatius Prep graduation, War Memorial Gym, 10am-12pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 03/29/2024:

All dates below are best estimate subject to weather and other external impacts, and may change without notice.
 
School of Education, 2350 Turk 
  • March 25 - April 5  Landscape work including grading, dirt removal, and drain pipe installation will continue in the outdoor areas behind and adjacent to 2350 Turk and 2340 Turk. 8:30am - 5:00pm, no work 3/30-31.  There will be some noise when trucks remove offhaul. No jackhammering or concrete cutting is expected
Malloy Basketball Practice Facility/War Memorial Gym 
  • Landscaping at Golden Gate frontage to be scheduled.
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • April 1 Crane will be placed on Parker frontage between Fulton and McAllister for loading materials onto church roof. Several trucks will deliver materials. Traffic controls will be in place.
    • East Spire - scaffold removal of spire complete.
    • West Spire - scaffold removal 3/4-4/24, subject to weather
    • Fulton frontage- painting 1st & 2nd coats
    • Mid-rooof and Dome - Paint Dome through 3/25
    • Bell tower - remove scaffold complete
    • Painting - north and west sides through 3/29
    • Stain glass restoration through 4/30/24 

Campus Events 

  • April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • May 9 Last day of Spring semester classes
  • May 16-18 Commencements
  • May 20 - Aug 9 Summer sessions
  • June Goats on Lone Mountain. Details TBD

UPDATE 03/22/2024:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
School of Education, 2350 Turk 
  • March 25 - April 5  Landscape work including grading will continue in the outdoor areas behind and adjacent to 2350 Turk and 2340 Turk. 8:30am - 5:00pm.
  • No work 3/30-31.  There will be some noise when trucks remove offhaul. No jackhammering or concrete cutting is expected.
Malloy Basketball Practice Facility/War Memorial Gym 
  • Landscaping at Golden Gate frontage to be scheduled.
  • March 25-26 Complete installation of handrails in areas around parking lot and Hayes Healy courtyard.
Masonic East, 270 Masonic (formerly the Blood Bank) 
  • Dates for parking lot waterproofing and other improvements have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • East Spire - scaffold removal of spire complete.
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-rooof and Dome - Paint Dome through 3/25
  • Bell tower - remove scaffold complete
  • Painting - north and west sides through 3/29
  • Stain glass restoration through 4/30/24 

Campus Events 

  • March 25 Admissions Tours, Sobrato Center 9am - 1pm
  • April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 03/15/2024:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Harney Science Center, loading dock area
 March 11 - 12  Plumbing contractor will replace plumbing clean outs at the Harney loading dock area. 8am starts. The work will be noisy at times. 
 
Lone Mountain Drive, center spur
 March 15 Lone Mtn Drive, center spur closure for tree removal
 
School of Education, 2350 Turk
  • March 18 - March 22. Grading work in landscaped area behind building, noisy at times. 
  • March 19 Concrete demo, jackhammering. Trucks will be onsite to remove debris.
Malloy Basketball Practice Facility/War Memorial Gym 
  • March 15 & 16: removal of 4 trees in front of Malloy BB Facility site. 
  • Landscaping at Golden Gate frontage to be scheduled.
  • Installation of handrails in areas around parking lot and Hayes Healy courtyard delayed due to manufacturer schedule.  
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired.
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • East Spire - scaffold removal of spire complete.\
  • West Spire - scaffold removal 3/4-4/24, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-rooof and Dome - sheet metal repair through 3/15/34. Paint Dome through 3/25
  • Bell tower - remove scaffold est. through 3/18-3/22
  • Painting - north and west sides through 3/29
  • Stain glass restoration through 4/1/24 
Campus Events 
  • March 25 Admissions Tours, Sobrato Center 9am - 1pm
  • April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 03/08/2024:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Harney Science Center, loading dock area
  •  March 11 - 12  Plumbing contractor will replace plumbing clean outs at the Harney loading dock area. 8am starts. The work will be noisy at times. 
Lone Mountain Drive, center spur
  •  March 15 Lone Mtn Drive, center spur closure for tree removal.
School of Education, 2350 Turk
  • March 11 - March 20. Landscaping work in the area behind and to the east of 2350 Turk. The work will include the demolition of concrete pathways, the removal of some grass areas, and grading. This work is expected to last about 7 days (8:30am-4:30pm) , not including Saturday and Sunday and so should be completed by Wed March 20. The demolition work will be noisy for the first few days and will involve jackhammering to break up concrete. Trucks will be onsite to remove debris.
 
Malloy Basketball Practice Facility/War Memorial Gym 
Installation of handrails in areas around parking lot and Hayes Healy courtyard delayed due to manufacturer schedule. 
  • March 8: removal of 4 trees in front of Malloy BB Facility site.  Landscaping at Golden Gate frontage to be scheduled. 
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • East Spire - scaffold removal of spire complete.
  • West Spire - scaffold removal 3/4-3/29, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-rooof and Dome - sheet metal repair through 3/15/34
  • Bell tower - remove scaffold est. through 3/12
  • Painting - north and west sides through 3/29
  • Stain glass restoration through 4/1/24 

Campus Events 

  • March 1 - USF campus Post Office substation permanently closed
  • March 11-15 Spring Break
  • March 25 Admissions Tours, Sobrato Center 9am - 1pm
  • April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 03/01/2024:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Installation of handrails in areas around parking lot and Hayes Healy courtyard delayed due to manufacturer schedule.
  • Landscaping at Golden Gate frontage to be scheduled. 
Masonic East (formerly the Blood Bank)
  • The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • East Spire - scaffold removal of spire complete.
  • West Spire - scaffold removal 3/4-3/29, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-roof and Dome - sheet metal repair through 3/15/34
  • Bell tower - remove scaffold est. 3/8, subject to weather
  • Painting - north and west sides through 3/29
  • Stain glass restoration through 4/1/24 

Campus Events 

  • March 1 - USF campus Post Office substation permanently closed
  • March 11-15 Spring Break
  • March 11-15 Lone Mtn Drive, center spur closure for tree removal; dates TBD
  • March 25 Admissions Tours, Sobrato Center 9am - 1pm
  • April 19 Donaroo Spring campus concert. Sobrato Center. Details TBD
  • April 26 Admissions Tours, Sobrato Center 9am - 1pm
  • June Goats on Lone Mountain. Details TBD

UPDATE 02/26/2024:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Installation of handrails in areas around parking lot and Hayes Healy courtyard delayed due to manufacturer schedule. 
  • Landscaping at Golden Gate frontage to be scheduled.  
Lone Mountain Viaduct, 330 Parker Ave 
  • Preparing for final inspection
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
  • Jan 29- Feb22 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • East Spire - scaffold removal of spire complete.
  • West Spire - paint dome by 2/22, scaffold removal 3/4-3/29, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-rooof and Dome - sheet metal repair through 3/15/34
  • Bell tower - remove scaffold est. 3/4
  • Stain glass restoration through 3/11/24 

Campus Events 

  • February 26 Baseball vs Seattle 1pm
  • February 29: USF plans to provide bus service for USF students to the USF vs Gonzaga MBB at the Chase Center
  • Buses for students will be staged at the passenger loading zone in front of War Memorial Gym, departures at about 6:15 and 6:30pm, 7pm, 7:15pm. Return buses drop off on Parker, near McAllister. The USF team bus will return to the WMG location at about 11:30-midnight.  USF is working to minimize idling & noise. 

UPDATE 02/16/2024:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Malloy Basketball Practice Facility/War Memorial Gym 
Landscaping at Golden Gate frontage to be scheduled. 
 
Lone Mountain Viaduct, 330 Parker Ave 
  • Preparing for final inspection
Masonic East (formerly the Blood Bank)
  • The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
  • Jan 29- Feb22 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Week of Feb 19- Concrete pour, north interior of church. One truck and one pump trailer via Parker entrance. Specific date TBD due to weather 
  • East Spire - scaffold removal of spire complete.
  • West Spire - paint dome by 2/22, scaffold removal 3/4-3/29, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-rooof and Dome - sheet metal repair through 3/15/34
  • Bell tower - remove scaffold est. 3/4
  • Stain glass restoration through 3/11/24
School of Education Projects,  2350 Turk
  • Presentation Theater refurbishment: project complete 

Campus Events 

  • February 23-25 Baseball vs Nevada: 2/23 2pm; 2/24 1pm; 2/25 12pm
  • February 26 Baseball vs Seattle 1pm
  • February 29: USF plans to provide bus service for USF students to the USF vs Gonzaga MBB at the Chase Center. 
  • Buses will be staged at the passenger loading zone in front of WMG, departures at about 6:15 and 6:30pm, 7pm, 7:15 Return buses time and location TBD. USF is developing plans to minimize idling & noise. 

UPDATE 02/02/2024:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
Hayes Healy & Gillson entry paths
  • Feb 13 Complete water proofing in patio areas (subject to rain delay)
  • Feb 14 Complete rebar install
  • Feb 15 Concrete pour for HH plaza between Malloy BB Facility and Hayes Healy. 8am start.
Malloy Basketball Practice Facility/War Memorial Gym 
  • Landscaping at Golden Gate frontage to be scheduled. 
Lone Mountain Viaduct, 330 Parker Ave 
  • Finishing fencing install below roadway 
  • Preparing for final inspection
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
  • Jan 29- Feb22 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration. This project is managed by St. Ignatius Church. which is independent of the University. Please exercise caution in areas near the Church. 
  • Feb 13 & 14- debris box delivered at Parker entrance, to place near trailer, remove morning of 2/14
  • East Spire - scaffold removal by 2/19, subject to weather.
  • West Spire - paint dome by 2/22, scaffold removal 3/4-3/29, subject to weather
  • Fulton frontage- painting 1st & 2nd coats
  • Mid-rooof and Dome - sheet metal repair through 3/15/34
  • Bell tower - remove scaffold est. 3/4
  • Stain glass restoration through 3/11/24
School of Education Projects,  2350 Turk
  • Presentation Theater:
  • Final inspection to be scheduled. 

Campus Events 

  • February 16 3-7pm Black History Month Cookout, Welch Field
  • February 16-17 USF Baseball vs Fairleigh Dickinson 2pm Friday; 10a & 2p Saturday
  • February 29: USF plans to provide bus service for USF students to the USF vs Gonzaga MBB at the Chase Center. 
  • 5 buses will be staged at the passenger loading zone in front of WMG, departures at 6:15 and 6:30pm and returns at 10:15 and 10:30pm. USF is developing plans to minimize idling & noise. 

UPDATE 02/02/2024:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
Hayes Healy & Gillson entry paths
  • Feb 5  Finish paver installation underneath Malloy BB facility and HH patio area, including delivery of pavers and base rock via Golden Gate entry drive.  8am start 
  • Feb 13 Complete water proofing in patio areas (subject to rain delay)
  • Feb 14 Complete rebar install
  • Feb 15 Concrete pour for HH plaza between Malloy BB Facility and Hayes Healy. 8am start.
Malloy Basketball Practice Facility/War Memorial Gym 
  • Building punch list walk TBD 
Lone Mountain Viaduct, 330 Parker Ave 
  • Finishing fencing install below roadway 
  • Preparing for final inspection
Masonic East (formerly the Blood Bank)
  • The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
    • Jan 29- Feb22 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • East Spire - finish coat complete, reinstall glass.
  • West Spire - sheet metal restoration complete; finish coat through 2/13, subject to rain delays remove scaffold on west spire through 2/26
  • Fulton frontage sheet metal restoration through Feb 9
  • Mid-rooof and Dome - sheet metal repair through 3/1/34
  • Bell tower - finish coat thru 2/16, remove scaffold est. 2/22
  • Feb 6- install new light poles, east side. 
  • Stain glass restoration through 3/11/24
School of Education Projects,  2350 Turk
Presentation Theater:
  • Final inspection to be scheduled. 

Campus Events 

  • February 2, 5:30pm Presentation Theater, Goodbye Mr. Chips, A Gordon Getty Opera
  • February 6, 7-8pm Silk Series Speaker in Sobrato Center, Clarence B. Jones & Sterling K. Brown

UPDATE 01/26/2024:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
Hayes Healy & Gillson entry paths
  • Jan 29  Sawcutting in area underneath Malloy BB facility and HH patio area. 8am start 
  • Jan 30 Concrete pour for HH plaza between Malloy BB Facility and Hayes Healy. 8am start.
  • Jan 31 Light pole installation, sections of the perimeter
 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Building punch list walk TBD
Lone Mountain Viaduct, 330 Parker Ave 
  • Finishing fencing install below roadway 
  • Preparing for final inspection
Masonic East (formerly the Blood Bank)
  • The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. 
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
    • Jan 29- Feb22 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Delivery of new lights poles for east side TBD 
  • Feb 2 - install new light poles, east side. 
  • West spire: sheet metal restoration complete; Paint 2 coats through 1/30
  • Fulton frontage: sheet metal restoration through 2/14/24
  • MidRoof and Dome: sheet metal repair through 3/1/24
  • Stain glass restoration through 3/11/24
School of Education Projects,  2350 Turk
Presentation Theater:
  • Final inspection to be scheduled. 

Campus Events 

  • February 6, 7-8pm Silk Series Speaker in Sobrato Center, Clarence B. Jones & Sterling K. Brown

 


UPDATE 01/19/2024:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Harney Science plumbing leak
  • Repair work complete. Fence to be removed by 1/22
Hayes Healy & Gillson entry paths
  • Jan 23.  Concrete pour for HH plaza between Malloy BB Facility and Hayes Healy. 8am start.
  • Jan 29.   Waterproofing patio and ramp areas
 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Jan 25: Paving activity in area beneath building.  
  • Ongoing deliveries - 2-3/week
 
Lone Mountain Viaduct, 330 Parker Ave 
  • Finishing fencing install below roadway 
  • Preparing for final inspection
 
Masonic East (formerly the Blood Bank)
  • The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
    • Jan 22-29 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Week of Jan 22: delivery of new lights poles for east side. Specific day TBD 
  • Jan 24-25: debris container delivery, fill, and removal 
  • Feb 2 - install new light poles, east side. 
  • West spire: sheet metal restoration thru 1/15/24; Exterior lighting through 1/12/24
  • Fulton frontage: sheet metal restoration through 2/14/24
  • MidRoof and Dome: prepping sheet metal and windows for painting
School of Education Projects,  2350 Turk
Presentation Theater:
  • Final inspection to be scheduled. 
  • Jan 19-23 - cleaning space

Campus Events 

  • January 20 - 7pm Men’s BB vs St Mary’s. CBS TV trucks arrive at UC lot about 9am
  • January 22 - First day of Spring Semester
  • February 6, 7-8pm Silk Series Speaker in Sobrato Center, Clarence B. Jones & Sterling K. Brown

 

 


2023 - Year In Review:


UPDATE 12/20/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Transformer cleaning schedule for winter break
The transformer cleaning requires a two hour electrical power down of each building
Please note buildings, dates and times below.
  • Dec 26 6AM to 8AM - Sobrato Gym & University Center
  • Dec 27 6AM to 8AM - Gleeson Library & Koret Rec
Harney Science plumbing leak
Leak in connection between Harney Science Center and the City storm sewer line at the loading dock driveway (Golden Gate & Chabot). 
  • 12/22 Update:  Concrete work will continue through 12/29, weather permitting. Area fenced off for safety; please heed safety instructions. 
Hayes Healy & Gillson entry paths
  • Dec 25, 26, Jan 1: Site closed 
  • Dec 27 - 29.  8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. 
  • Demo will involve saw cutting and jack hammering. It will be loud and disruptive. 
  • No work Dec 25. 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Dec 25, 26, Jan 1: Site closed 
  • Dec 26 - 29: install fiberglass tubing on north facade. Leveling work beneath building to prepare for pavers may be moderately noisy.  
  • Ongoing deliveries - 2-3/week
Lone Mountain Viaduct, 330 Parker Ave 
  • Ongoing: install fencing below roadway; preparing for final inspection
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Start dates for the parking lot waterproofing and for the interior renovation work have not yet been scheduled. 
  • Dec 21-31 No work scheduled on site
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Dec 18 - 23 delivery of light poles for east side, turf removal at light sitesexcavation for footings
  • Dec 26-29 conduit installation at Welch Field for light poles
  • East spire; sheet metal restoration through 12/23
  • West spire: sheet metal restoration thru 1/15/24; Exterior lighting through 1/12/24
  • Fulton frontage: sheet metal restoration through 2/14/24
  • MidRoof and Dome: prepping sheet metal and windows for painting
School of Education Projects,  2350 Turk
Presentation Theater:
  • No work scheduled

Campus Events 

  • January 2 - Intersession classes begin
  • January 18 - Move-In Day, new and returning students
  • January 22 - First day of Spring Semester
  • February 6, 7-8pm Silk Series Speaker in Sobrato Center

❄️Happy Holidays to all ❄️


UPDATE 12/15/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Transformer cleaning schedule for winter break
The transformer cleaning requires a two hour electrical power down of each building
Please note buildings, dates and times below.
  • Dec 20 5AM to 7AM:  Kendrick Hall & Zief Library
  • Dec 26 6AM to 8AM - Sobrato Gym & University Center
  • Dec 27 6AM to 8AM-  Gleeson Library & Koret Rec
Harney Science plumbing leak
  • Dec 1- Dec 8 
  • Leak in connection between Harney Science Center and the City storm sewer line at the loading dock driveway (Golden Gate & Chabot). 
  • 12/15 Update:  Backfill complete; inspection complete. Concrete work will begin Thursday 12/21, weather permitting. Area fenced off for safety; please heed safety instructions. 
Hayes Healy & Gillson entry paths
  • Dec 18 - 29.  8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. 
  • Demo will involve saw cutting and jack hammering. It will be loud and disruptive. 
  • Pausing outdoor work for end of semester & Finals: no work Nov 23-Dec 15 and Dec 25. 
Malloy Basketball Practice Facility/War Memorial Gym 
  • Dec 20-22: Fiberglass tubing delivery and paintingPunchlist  
  • Dec 26 - 29: install fiberglass tubing on north facade. Leveling work beneath building to prepare for pavers may be moderately noisy.  
  • Ongoing deliveries - 2-3/week
Lone Mountain Viaduct, 330 Parker Ave 
  • Ongoing: install fencing below roadway; preparing for final inspection
 
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Dec 18-22 No work scheduled on site
 
School of Education Projects,  2350 Turk
Presentation Theater:
  • No work scheduled 
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Dec 18 - 23 delivery of light poles for east side, turf removal at light sitesexcavation for footings
  • East spire; sheet metal restoration through 12/23
  • West spire: sheet metal restoration thru 1/15/24; Exterior lighting through 1/12/24
  • Fulton frontage: sheet metal restoration through 2/14/24
  • MidRoof and Dome: prepping sheet metal and windows for painting

Campus Events 

  • December 15 - Mid Year Commencement
  • January 2 - Intersession classes begin
  • January 18 - Move-In Day, new and returning students
  • January 22 - First day of Spring Semester
  • February 6, 7-8pm Silk Series Speaker in Sobrato Center

UPDATE 12/08/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Transformer cleaning schedule for winter break. 
The transformer cleaning requires a two hour electrical power down of each building. 
Please note buildings, dates and times below.
Dec 20 5AM to 7AM:  Kendrick Hall & Zief Library
Dec 26 6AM to 8AM - Sobrato Gym & University Center
Dec 27 6AM to 8AM-  Gleeson Library & Koret Rec
 
Harney Science plumbing leak
Dec 1- Dec 8 USF has found a leak in a pipe drain connection between Harney Science Center and the City stormsewer line at the loading dock driveway (Golden Gate & Chabot). 
12/8 Update: Excavation complete. Plumbing repair will continue into next week. Backfill and reconstruction of sidewalk will occur after plumbing is repaired. Area fenced off for safety; please heed safety instructions.  
 
Hayes Healy & Gillson entry paths
Dec 18 - 29.  8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. 
Demo will involve saw cutting and jack hammering. It will be loud and disruptive. 
Pausing outdoor work for end of semester & Finals: no work Nov 23-Dec 15 and Dec 25. 
 
Malloy Basketball Practice Facility/War Memorial Gym 
Dec 11 - 15: Fiberglass tubing delivery and paintingPunchlist  
Dec 18- 22: install fiberglass tubing on north facade. Leveling work beneath building to prepare for pavers may be moderately noisy.  
Ongoing deliveries - 2-3/week
 
Lone Mountain Viaduct, 330 Parker Ave 
Ongoing: install fencing below roadway; preparing for final inspection
 
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
Dec 11-15 No work scheduled on site
 
School of Education Projects,  2350 Turk
  • Presentation Theater: Dec 11-13 - Complete lift installation
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Dec 18 - 23 delivery of light poles for east side, turf removal at light sitesexcavation for footings
  • East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
  • West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
  • MidRoof and Dome: prepping sheet metal and windows for painting

Campus Events 

  • December 15 - Mid Year Commencement
  • January 2 - Intersession classes begin
  • January 18 - Move-In Day, new and returning students
  • January 22 - First day of Spring Semester

 

UPDATE 12/01/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Harney Science plumbing leak
  • Dec 1- Dec 8 USF has found a leak in a pipe drain connection between Harney Science Center and the City stormsewer line at the loading dock driveway (Golden Gate & Chabot). The leak requires immediate repair. Contractors will remove a section of the sidewalk and expose the pipe. The work will require heavy equipment and may also initially involve saw-cutting and jack hammering. Once excavation is complete, quieter repair work will continue through next week.
  • 12/1 Update: The excavation work is done for today 12/1. Because of underground utilities near this location, some of the excavation work will require hand digging which will slow things down.
Hayes Healy & Gillson entry paths
  • Nov 13 - 22; Dec 18 - 29.  8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. 
  • Demo will involve saw cutting and jack hammering. It will be loud and disruptive. 
  • Pausing outdoor work for end of semester & Finals: no work Nov 23-Dec 15 and Dec 25. 
Malloy Basketball Practice Facility/War Memorial Gym 
Dec 1 - 11am - 5pm concrete demo at stairs landing near HH garage, needed to complete waterproofing and form new pathway. 
Completing remaining installation tasks, inspections underway. Installation of outdoor pavers. 
Dec 18- 22 install fiberglass tubing on north facade
Ongoing deliveries - 2-3/week
 
Lone Mountain Viaduct, 330 Parker Ave 
  • Ongoing: seal joints, minor concrete repairs, install fencing below roadway
Masonic East (formerly the Blood Bank)
The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Dec 3-8 No work scheduled on site
School of Education Projects,  2350 Turk
  • Presentation Theater: Completing lift installation
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Dec 15 No work at site
  • East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
  • West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
  • MidRoof and Dome: prepping sheet metal and windows for painting

Campus Events 

  • December 15 - Mid Year Commencement
  • January 2 - Intersession classes begin
  • January 18 - Move-In Day, new and returning students
  • January 22 - First day of Spring Semester

UPDATE 11/17/2023:

Hayes Healy & Gillson entry paths
  • Nov 13 - 22; Dec 18 - 29.  8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. 
  • Demo will involve saw cutting and jack hammering. It will be loud and disruptive. 
  • Pausing outdoor work for end of semester/final: no work Nov 23-Dec 15 and Dec 25. 
     
Malloy Basketball Practice Facility/War Memorial Gym 
  • Completing remaining installation tasks, inspections underway. Installation of outdoor pavers. 
  • Dec 18- 22 install fiberglass tubing on north facade
  • Ongoing deliveries - 2-3/week
Lone Mountain Viaduct, 330 Parker Ave 
  • Ongoing: seal joints, minor concrete repairs, install fencing below roadway
  • Nov 14-21 guardrail work
Masonic East (formerly the Blood Bank)
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Nov 13-17 No work scheduled on site
School of Education Projects,  2350 Turk
Presentation Theater:
  • 11/17 & 11/20 - 22: install lift (3-5 days; if needed, work will continue 11/27)
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
  • West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
  • MidRoof and Dome: prepping sheet metal and windows for painting

Campus Events 

  • December 15 - Mid Year Commencement

UPDATE 11/10/2023:

Hayes Healy & Gillson entry paths
  • Nov 13 - 29. 8am starts. Demo, layout, and installation of ADA pathways and pavers outside Hayes Healy and Gillson forecourts; removal of retaining wall. Demo will involve saw cutting and jack hammering. It will be loud and disruptive. No work on Nov 23 & 24. 
Malloy Basketball Practice Facility/War Memorial Gym
Nov 11 10am-noon Donor recognition event:  a brief ceremony on the parking deck parking of the facility from about 10am-10:30 will include comments from the podium, appearance by USF’s ROTC Color Guard and the National Anthem played by the USF band. A reception will follow in the Sobrato Center.  Event will end at 12pm. Guests will be provided parking in the HH parking lot. 
  • Ongoing: Completing remaining installation tasks, installing graphics, wall pads, inspections underway. Installation of outdoor pavers. 
  • Nov 13: ADA work on west side of Hayes Healy. Details TBD
  • Ongoing deliveries - 2-3/week
Lone Mountain Viaduct, 330 Parker Ave 
  • Ongoing: seal joints, minor concrete repairs, install fencing below roadway
  • Nov 14: demobilize access road
  • Nov 14-21 guardrail work
 
Masonic East (formerly the Blood Bank)
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Nov 13-17 No work scheduled on site
School of Education Projects,  2350 Turk
Presentation Theater:
  • 11/13 - 14 - install door stops for exit doors
  • Mid to late next week - begin lift installation (work will last about 1 week)
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
  • West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
  • MidRoof and Dome: prepping sheet metal and windows for painting
McLaren Center & Toler Hall Coil replacement
  • Coils in the AC units on the McLaren Complex roof have been replaced. Technicians will return to continue work on minor parts. 
  • 10/23 8am Technicians will be on site to replace some additional parts for the AC units located on McLaren Complex roof.  Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units. 

Campus Events 

  • Nov 16, 11-1pm Student event, Library Plaza
  • December 15 - Mid Year Commencement

UPDATE 11/03/2023:


UPDATE 10/27/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Hayes Healy Garage Closure Oct30-Nov2
  • The Hayes Healy Garage will be closed for mandated driveway repairs from 8am Monday Oct 30 to 8am Thursday November 2.
  • There will be no egress nor entry to the garage during that time. 
  • All vehicles must be removed from the garage by 8am Monday 10/30.  Vehicles remaining in the garage after Monday morning will not be available for use until 8am Thursday. 
Lone Mountain Viaduct, 330 Parker Ave 
Oct 6-23
  • Continued shut down road for paving and overlay work, expected completion on Monday Oct 23. The work will be noisy and disruptive at times.  Please follow flag person directions and signage.
Masonic East (formerly the Blood Bank)
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Oct 30-Nov 3 No work scheduled on site
School of Education Projects,  2350 Turk
Presentation Theater:
  • 10/30 - 11/3: dense drywall and plaster work (minimal noise)
 
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • East spire: prep & paint windows through 11/3; sheet metal restoration through 12/23
  • West spire: window restoration through 11/10; sheet metal restoration to start 10/23-1/15/23
  • MidRoof and Dome: prepping sheet metal and windows for painting
  • Masonry restoration ongoing through 10/31
 
Malloy Basketball Practice Facility/War Memorial Gym
  • Ongoing: Completing remaining installation tasks, installing graphics, wall pads, inspections underway. Installation of outdoor pavers. 
  • Oct 30-Nov2 mandatory repair to Hayes Healy garage entry. HH garage will be closed. All vehicles must be removed  from Hayes Healy garage by Monday 8am Oct 30 
  • Oct 31 Remove construction trailer
  • Nov 2 Remove stair tower 
  • Ongoing deliveries - 2-3/week
McLaren Center & Toler Hall Coil replacement
  • Coils in the AC units on the McLaren Complex roof have been replaced. Technicians will return to continue work on minor parts. 
  • 10/23 8am Technicians will be on site to replace some additional parts for the AC units located on McLaren Complex roof.  Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units. 
Campus Events 
Saturday, October 28: Day In the Bay/Admissions Open House. 8am-4pm
  • Large attendance expected. USF lots will be ’no cite’ and open to guests
  • Workshop,seminars and tours for prospective students
November 3, 4-6pm 
  • USF Rising Mentorship Program at Gleeson Plaza - permit for amplified sound

 


UPDATE 10/13/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Lone Mountain Main/Pacific Wing Plumbing Repair
  • Monday Oct 16 Water shut off in LMM and Pac Wing for approximately 4 hours (8am - noon).
  • Oct 16 - 17  Plumbing repair and pipe replacement in ROTC spaces, LMM
Lone Mountain Viaduct, 330 Parker Ave 
  • Oct 6 -20.  Shut down west half of viaduct for road overlay work. The work will be noisy and disruptive at times. 
  • Once the west section is complete, the work will move to the eastern section. Final stage will be to install overlay layer to roadway surface. Please follow flag person directions and signage.
  • Please do not park on the Viaduct between the Parker entrance and the Anza St exit during this period. Such vehicles will be subject to towing. 
Crane at Center for Scientific Innovation (CSI)
One of the primary exhaust fans on the roof of CSI must be replaced. Replacing the exhaust fan requires that the ventilation system in the CSI building must be shut off so the work must be completed during the Fall Break (no classes). Placing the crane on the roof requires a crane which will arrive on Sunday morning at 8am at the Golden Gate driveway entrance between WMGym and University Center. 
  • Oct 15 -17: Installation postponed. Date TBD
Masonic East (formerly the Blood Bank)
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. 
  • Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled.
  • Oct 16-20 No work scheduled on site
School of Education Projects,  2350 Turk
Presentation Theater:
  • 10/13 & 10/16: removal of scaffolding from stage (some noise)
  • 10/13: install steel by lift (minimal noise)
  • 10/16 - 20: framing by lift (some noise)
  • 10/17 - 20: remove exterior scaffolding (some noise)
  • 10/18: begin refinishing stage
St Ignatius Church
St Ignatius Church exterior envelope restoration project.  This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • East spire: sheet metal restoration through 12/23
  • West spire: sheet metal restoration to start 10/16, duration TBD
  • MidRoof and Dome: prepping sheet metal and windows for painting
  • Masonry restoration ongoing through 10/31
Malloy Basketball Practice Facility/War Memorial Gym
  • Oct 14-16  Driveway btw Malloy BB facility and WMG closed until Oct 16 pm; sidewalk will be open to pedestrians Oct 16 am
  • Ongoing: Flooring installation in lobbies, ongoing plastering, panel work on building’s south side (will be noisy during work hours at times), installation of outdoor pavers. 
  • Ongoing deliveries - 2-3/week
McLaren Center & Toler Hall Coil replacement
  • Coils in the AC units on the McLaren Complex roof have been replaced. Technicians will return to continue work on minor parts. 
  • Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units. 

Campus Events 

  • October 14. Student Leadership Conference at KoretParker btw Fulton and Golden Gate blocked off for buses. 
  • October 20 - 22 CelebrateUSF - alumni and family weekend 
  • Oct 20, Welch Field outdoor concert 12-3pm
  • Oct 21 Silk Speaker Series at War Memorial Gym 11am - 12 pm
 

UPDATE 10/06/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Lone Mountain Viaduct, 330 Parker Ave 
  • Oct 6 -20.  Shut down west half of viaduct for road overlay work. The work will be noisy and disruptive at times. 
  • Once the west section is complete, the work will move to the eastern section. Final stage will be to install overlay layer to roadway surface. Please follow flag person directions and signage.
  • Please do not park on the Viaduct between the Parker entrance and the Anza St exit during this period. Such vehicles will be subject to towing. 
Crane at Center for Scientific Innovation (CSI)
One of the primary exhaust fans on the roof of CSI must be replaced. Replacing the exhaust fan requires that the ventilation system in the CSI building must be shut off so the work must be completed during the Fall Break (no classes). Placing the crane on the roof requires a crane which will arrive on Sunday morning at 8am at the Golden Gate driveway entrance between WMGym and University Center. 
  • Oct 15 Sunday: Crane delivery and placement
  • Oct 16 -17: Installation 
McLaren Center & Toler Hall
  • Oct 9-11 Engineering will be replace coils in the AC units on the McLaren Complex roof starting 8AM Monday 10/9/2023 through 10/11/2023. The coils will be delivered via truck at the Fulton St loading dock behind McLaren. 
  • Student residents living in Toler on the side that faces the McLaren Complex should be aware that technicians will be working on the roof top units. 
 
Masonic East (formerly the Blood Bank)
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. 
Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled. 
  • 10/9 - Geotech work on site (minimal noise, start time 9:00am)
School of Education Projects,  2350 Turk
Presentation Theater:
  • 10/6: Demo exterior roof ladder
  • 10/9 - 13: scaffolding removal from stage (some noise)
  • 10/9: Install new exterior roof ladder (some noise)
    • Located on outer south wall of theater loft
  • 10/13: Steel installation for lift
St Ignatius Church
St Ignatius Church exterior envelope restoration project.
This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Through 9/29 -Ground level: strip west elevation, masonry restoration.
  • MidRoof & Dome - sheet metal restoration, masonry restoration
  • 10/2-17 Install east balustrades
  • Thru Feb 2024 - stain glass restoration
 
Malloy Basketball Practice Facility/War Memorial Gym
  • Oct 9-13  Flooring installation in lobbies, ongoing plastering, panel work on building’s south side (will be noisy at times). 
  • Oct 11-13 Driveway between WMG and Malloy BB: Oct 11: demo and saw cut existing drive (noisy work), Oct 12: install forms; Oct 13: concrete pour. 
  • Ongoing deliveries - 2-3/week

Campus Events 

  • October 20 - 22 CelebrateUSF - alumni and family weekend 

UPDATE 9/15/2023:

All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 
Lone Mountain Viaduct, 330 Parker Ave 
  • Oct 2 -4.  Shut down west half of viaduct for road overlay work. The work will be noisy and disruptive at times. Once the west section is complete, it will be opened and the work will move to the eastern section. 
Please follow flag person directions and signage.
  • Oct 9-12 tentative: install overlay layer to roadway surface, partial road closures
Ulrich Baseball Field
  • Complete; minor cleanup work through 9/29.
Lone Mountain Main & Lone Mountain North
Saturday Sept 23 Fire Inspection & Emergency generator test: 4 hour test of LMM generator; the work may be noisy at times. 
 
Masonic East (formerly the Blood Bank)
Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. 
Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. Work has yet to be scheduled. 
  • 9/26: boring 1 hole in parking lot (some noise)
School of Education Projects,  2350 Turk
Presentation Theater:
  • 9/25 - 26: finish painting loft above stage; install emergency exit door; install handrails by emergency exit doors
  • 9/27 - 29: install stage lights
St Ignatius Church
St Ignatius Church exterior envelope restoration project.
This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Through 9/29 -Ground level: strip west elevation, masonry restoration.
  • MidRoof & Dome - sheet metal restoration, masonry restoration
  • 10/2-17 Install east balustrades
  • Thru Feb 2024 - stain glass restoration
Malloy Basketball Practice Facility/War Memorial Gym
  • Sept 22  Complete/ close up street utility tie-in work near driveway between WMGym and Malloy site
  • Sept 26-29 Installation of new driveway path at drive between WMG & Malloy BB site. 
  • Sept 5-26  Installation of new walkway and stairs between Malloy Pavilion and Gillson. Will involve concrete demo which will be loud at times. Please follow directions and signage.
  • Ongoing - Removal of scaffolding, interior glazing, paint, hardware install, elevator, railings, exterior plastering etc. 
  • Ongoing deliveries - 2-3/week

Campus Events 

  • October 20 - 22 CelebrateUSF - alumni and family weekend 

UPDATE 9/15/2023:

 
All dates below are best estimates, subject to weather and other external impacts and may change without notice.
 

Lone Mountain Viaduct, 330 Parker Ave

The Lone Mountain Viaduct, located on the north slope of Lone Mountain, will be closed all day on Thursday Sept 21 Please follow flag person directions and signage.
 
Screenshot 2023-09-14 at 11.31.55 AM.png
 
 

University Community, please note: 

Sept 12-19 The Hayes Healy garage will be closed for adjacent driveway and sidewalk construction next week.
  • The garage will close end of the business day on Tuesday Sept 12.  
  • The garage will reopen in the morning on Tuesday Sept 19. 
The garage is completely closed to all vehicle traffic during this time.  
Any cars remaining in the garage after Sept 12 will not be able to be retrieved until the garage reopens. 
 

Ulrich Baseball Field

Sept 8-12 - Patch and repair turf; infield, bullpen, pitching mound. 95% complete; minor patching through 9/22.
 

Lone Mountain Main & Lone Mountain North

Saturday Sept 23 Fire Inspection & Emergency generator test: 4 hour test of LMM generator; may be noisy at times. 
 

Masonic East (formerly the Blood Bank)

Decisions on academic programming for the Masonic East are being finalized. The University intends to prepare the building for teaching and research in nursing and life sciences which will maximize the use of the building’s existing labs and interior space. Before interior renovations can begin, a leaky basement underneath the parking lot at the Turk/Masonic corner must be repaired. That work requires us to pull up the asphalt and waterproof the basement structure’s roof. Work has yet to be scheduled. 
 

School of Education Projects,  2350 Turk

Presentation Theater:
  • 9/15 & 9/18: set up scaffolding on stage
  • 9/16 - 17: cut concrete on east side of stage (classes and seminars have been notified/relocated)
  • 9/18 - 22: paint loft, paint smoke hatches, install stage lights

St Ignatius Church

St Ignatius Church exterior envelope restoration project. This project is managed by St. Ignatius Church. which is independent of the University. 
Please exercise caution in areas near the Church. 
  • Through 9/22 -Ground level: strip west elevation, masonry restoration.
  • Through 9/15 - East and West Spires: continue stripping paint, masonry restoration, repair balustrades
  • Sept 18: work on interior to start; electrical infrastructure 
  • Thru Feb 2024 - stain glass restoration

Malloy Basketball Practice Facility/War Memorial Gym

  • Sept 8 - 15  Street Utility Tie-in Work near driveway between WMGym and Malloy site Work will take place during normal hours 8am-3:30pm (not Saturday).There will be some saw cutting at beginning of work, then they will move on to the utility install. Flaggers in the street to assist with traffic. On off-hours, trench plates will be placed over work area per SFDPW requirements.
  • Sept 5-26  Installation of new walkway and stairs between Malloy Pavilion and Gillson. Will involve concrete demo which will be loud at times. Please follow directions and signage.